14.02.010 - Declaration of necessity and intent.

A. This chapter establishes certain mandatory and permanent water management requirements necessary to conserve water, enable effective water supply planning, assure reasonable and beneficial use of water, prevent waste of water, prevent unreasonable use of water, prevent unreasonable methods of use of water within the City of El Paso de Robles service area in order to assure adequate supplies of water to meet the needs of the public, and further the public health, safety, and welfare, recognizing that water is a scarce natural resource that requires careful management not only in times of drought, but at all times.

B. This chapter also establishes regulations to be implemented during times of declared water shortages, or declared water shortage emergencies. It establishes four levels of actions to be implemented in times of shortage, with increasing restrictions on water use in response decreasing water supply or production capabilities.

C. Level 1 water supply shortage measures are voluntary and will be reinforced through local and regional public education and awareness measures. Levels 2 through 4 water supply shortage conditions mandate increasingly restrictive measures in order to attain escalating conservation goals. Those city water customers who violate the measures imposed under a condition of Level 2 through Level 4 are subject to criminal, civil, and administrative penalties and remedies as provided in Chapter 1 of this Code.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Exceptions & meaning →

14.02.020 - Application.

A. This chapter applies to all customers in the use of any water provided by the city, including customers located within or outside the city, and to all private well owners and operators within the city limits.

B. This chapter is intended solely to further the conservation of water. It is not intended to implement or replace any provision of federal, state, or local statutes, ordinances, or regulations relating to protection of water quality or control of drainage or runoff.

C. The provisions of this chapter do not apply to uses of water necessary to protect public health and safety or for essential government services, such as police, fire and other similar emergency services.

D. Nothing in this Chapter 14.02 is intended to affect or limit the ability of the city manager or his designee to declare and respond to an unforeseeable disaster or water emergency such as an earthquake, or other major disruption in the water supply, pursuant to the general laws of the city or other provisions of this Code.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009; Ord. No. 1021 N.S. § 1, 1-5-2016)

Exceptions & meaning →

14.02.030 - Definitions.

The following words and phrases whenever used in this Chapter 14.02 will have the meaning defined in this section:

A. Customer means any person, corporation, public or private entity, public or private association, public or private agency, government agency or institution, school district, college, university, or any other user of water provided by the City of El Paso de Robles.

B. Days are defined as calendar days, unless otherwise indicated.

C. Water Conservation means the efficient management of water resources for beneficial uses, preventing waste, or accomplishing additional benefits with the same amount of water.

D. Condition means a declared water supply shortage condition, which may be at Level 1, Level 2, Level 3 or Level 4, as described in this Chapter 14.02.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Exceptions & meaning →

14.02.040 - Mandatory minimum water conservation requirements—Prohibition against waste.

The following water conservation requirements shall be in effect at all times and are permanent. Violations will be considered waste and an unreasonable use of water and are subject to penalties.

A. No Excessive Water Flow or Runoff: Watering or irrigating of any lawn, landscape or other vegetated area in a manner that causes or allows excessive water flow or runoff onto an adjoining sidewalk, driveway, street, alley, gutter or ditch is prohibited.

B. No Overfilling of Swimming Pools and Spas: Overfilling of a swimming pools and spas such that overflow water is discharged onto an adjoining sidewalk, driveway, street, alley, gutter or ditch is prohibited.

C. No Washing Down Hard or Paved Surfaces: Washing down hard or paved surfaces, including but not limited to sidewalks, walkways, driveways, parking areas, tennis courts, patios or alleys, is prohibited except under the following conditions:

  1. To alleviate safety or sanitary hazards, and then only by use of a hand-held bucket or similar container, a hand-held hose equipped with a positive self-closing water shut-off device.

  2. When a low-volume, high-pressure cleaning machine or a low-volume high-pressure water broom is used.

  3. All wash-down activities must comply with all state or local regulations pertaining to discharges to the city's storm drain system.

D. Obligation to Fix Leaks, Breaks or Malfunctions: Excessive use, loss or escape of water through breaks, leaks or other malfunctions in the customers' plumbing or distribution system for any period of time after such escape of water should have reasonably been discovered and corrected and in no event more than seven days after written notification by the City of El Paso de Robles, is prohibited.

E. Re-Circulating Water Required for Water Fountains and Decorative Water Features: Operating a water fountain or other decorative water feature that does not use re-circulated water is prohibited.

F. Limits on Washing Vehicles: Using water to wash or clean a vehicle, including but not limited to any automobile, truck, van, bus, motorcycle, boat or trailer, whether motorized or not is prohibited, except by use of a hand-held bucket or similar container or a hand-held hose equipped with a positive self-closing water shut-off nozzle or device. This subsection does not apply to any commercial car washing facility.

G. Commercial Lodging Establishments Must Provide Guests Option to Decline Daily Linen Services: Hotels, motels and other commercial lodging establishments must provide customers the option of not having towels and linen laundered daily. Commercial lodging establishments must prominently display notice of this option in each bathroom using clear and easily understood language.

H. No Installation of Single Pass Cooling Systems: Installation of single pass cooling systems is prohibited in buildings requesting new water service.

I. No Installation of Non-Recirculating Systems in Commercial Car Wash and Laundry Systems: Installation of non-recirculating water systems is prohibited in new commercial conveyor car wash and new commercial laundry systems.

J. New or Remodeled Restaurants Required to Use Water Conserving Dish Wash Spray Valves: All new or remodeled food preparation establishments, such as restaurants or cafes, are prohibited from using non-water conserving dish wash spray valves.

K. Water Served Only Upon Request: Restaurants and other food establishments will only serve water upon request.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Exceptions & meaning →

14.02.050 - Level 1 water supply shortage—Voluntary reductions.

A. The city council or, in the event prompt action is necessary, the city manager, may declare a Level 1 water supply shortage condition (a "Level 1 Condition") when there is a reasonable probability, due to a projected imbalance in available water supply and projected peak demand, that there will be a supply shortage and that a consumer demand reduction of up to ten percent is needed in order to ensure that sufficient supplies will be available to meet anticipated demands. Upon such declaration, the city manager or his designee shall take the necessary actions to implement the voluntary Level 1 condition conservation practices identified in this chapter. In the event a Level 1 condition has been declared by the city manager, the city council shall consider the ratification of such declaration at its next regularly scheduled meeting or at a special meeting called for such purpose.

B. During the period of a declared Level 1 condition, the City of El Paso de Robles will increase its public education and outreach efforts to increase public awareness of the need to implement the following water conservation practices.

  1. Irrigation of residential and commercial landscapes, including golf courses, parks, school grounds and recreation fields, before 9:00 a.m. and after 7:00 p.m. except for renovation or repair of the irrigation system with an operator present.

  2. Repair or prevention of all water leaks upon discovery or within five days of notification by the City of El Paso de Robles.

  3. Use of recycled, non-potable, or water imported from outside city limits for construction purposes.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Exceptions & meaning →

14.02.060 - Level 2 water supply shortage—Mandatory reductions.

A. The city council, or in the event prompt action is necessary, the city manager, may recommend and declare a Level 2 water supply shortage condition (a "Level 2 Condition") when there is a reasonable probability, due to a projected imbalance in available water supply and projected peak demand, that there will be a supply shortage and that a consumer demand reduction of up to twenty percent is required in order to ensure that sufficient supplies will be available to meet anticipated demands. Upon the declaration of a Level 2 condition, the city manager or his designee shall take the necessary actions to notify the public and implement the mandatory Level 2 condition conservation practices identified in this chapter. In the event a Level 2 condition has been declared by the city manager, the city council shall consider the ratification of such declaration at its next regularly scheduled meeting or at a special meeting called for such purpose.

B. During the period of a declared Level 2 condition, all water customers shall be required to comply with all Level 1 condition measures, set forth in Section 14.020.050, and also shall comply with the following conservation measure:

  1. The city shall establish and post a schedule for the months in which all landscape irrigation shall be limited to no more than three assigned days per week. Such schedule shall also specify any limited exceptions to such restrictions.

  2. Watering of landscaping shall be prohibited during and within forty-eight hours of rainfall.

  3. All irrigation of ornamental turf in public street medians shall be prohibited.

C. At its discretion, the city may suspend the issuance of new hydrant meters and/or recall all outstanding meters in accordance with the city's existing hydrant meter rental agreement.

D. The city manager may recommend and, upon resolution of the city council, implement a water allocation per customer account served by the City of El Paso de Robles, and a schedule of per unit penalties for use exceeding the water allocation. If the city council adopts or modifies water allocations, the city manager will post notice of the water allocation prior to the effective date(s). Following the effective date(s) of the water allocation as established by the city council, any customer that uses water in excess of the allocation will be subject to a penalty for each billing unit of water in excess of the allocation. The per unit penalty for excess water usage will be in addition to any other remedy, penalty, or fine that may be imposed for violation of this chapter. At the city's discretion, the water conservation measures required under Level 1 and Level 2 conditions may be suspended during the period a water allocation is in effect.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009; Ord. No. 09-962 N.S., § 1, 10-20-2009; Ord. No. 1014 N.S., § 2, 5-5-2015; Ord. No. 1032 N.S., § 1, 7-19-2016)

Exceptions & meaning →

14.02.070 - Level 3 water supply shortage—Critical condition.

A. The city council or, in the event prompt action is necessary, the city manager, may recommend and declare a Level 3 water supply shortage condition (a "Level 3 Condition") when there is a reasonable probability, due to a projected imbalance in available water supply and projected peak demand, that there will be a supply shortage and that a consumer demand reduction of up to thirty percent is required in order to ensure that sufficient supplies will be available to meet anticipated demands. Upon declaration of Level 3 water supply shortfall, the city manager or his designee shall take the necessary actions to implement the mandatory Level 3 condition conservation practices identified in this chapter. In the event a Level 3 condition has been declared by the city manager, the city council shall consider the ratification of such declaration at its next regularly scheduled meeting or at a special meeting called for such purpose.

B. During a the period of a declared Level 3 condition, all water customers shall comply with all Level 1 condition and Level 2 condition water conservation measures and shall also comply with the following additional mandatory conservation measures:

  1. All landscape irrigation shall be limited to no more than two assigned days per week on a schedule established and posted by the city manager or his designee.

  2. Filling or re-filling of ornamental lakes or ponds is prohibited except to the extent needed to sustain plants or animals that have been actively managed within the water feature prior to the declaration of a Level 3 condition.

  3. All water leaks, breaks or other plumbing malfunctions shall be repaired upon discovery or within forty-eight hours of notification by the City of El Paso de Robles, with the exception of rental properties, which shall have up to seventy-two hours to repair interior unit leaks, in order to comply with state laws regarding the provision of notice to tenants.

  4. Using water to wash vehicles, whether motorized or not, is prohibited except at commercial car washing facilities.

  5. Washing down hard or paved surfaces, including but not limited to sidewalks, walkways, driveways, parking areas, tennis courts, patios or alleys, is prohibited except under the following conditions:

a. To alleviate safety or sanitary hazards, and then only by use of a hand-held bucket or similar container, a hand-held hose equipped with a positive self-closing water shut-off device, a low-volume, high-pressure cleaning machine or a low-volume high-pressure water broom.

C. Upon the declaration of a Level 3 condition, new potable water services, temporary or permanent water meters, and statements of immediate ability to serve or provide potable water service (including, but not limited to, will serve letters, certificates, or letters of availability) will be allowed only under the circumstances listed below. This provision does not preclude the resetting or turn-on of meters to provide continuation of water service or to restore service that has been interrupted.

  1. A valid building permit has been issued for the project; or

  2. The project is necessary to protect the public's health, safety, and welfare; or

  3. The applicant provides substantial evidence satisfactory to the city manager or his designee of an enforceable commitment that the new water demands for the project will be offset prior to the provision of new water meter(s). The applicant's offset program must be approved by the city's water manager. Such offsets may be in the form of additional water conservation measures, the provision of recycled water use in place of existing potable water demands (if available), or other such offsets developed and approved by the city manager or his designee. To obtain approval, the applicant's plan must demonstrate that the development will not increase the demand on the city's water system.

During the period of a Level 3 condition, the expiration dates of approved tentative maps and related entitlements for such development projects shall be tolled until such time as the Level III condition has improved to a Level II condition or better. Notwithstanding the foregoing, an applicant with an approved tentative map and related entitlements may choose to proceed with development under the conditions set forth in subsection c.3., above.

D. Upon the declaration of a Level 3 condition, the city will suspend consideration of any annexation to its service area. This subsection does not apply to boundary corrections and annexations that will not result in any increased use of water.

E. At its discretion, the city may suspend the issuance of new hydrant meters and/or recall all outstanding meters in accordance with the city's existing hydrant meter rental agreement.

F. The city manager may recommend and, upon resolution of the city council, implement a water allocation per customer account served by the City of El Paso de Robles, and a schedule of penalty surcharges for exceeding the water allocation. If the city council adopts or modifies water allocations, the city manager will post notice of the water allocation prior to the effective date(s). Following the effective date(s) of the water allocation as established by the city council, any customer that uses water in excess of the allocation will be subject to a penalty surcharge for each billing unit of water in excess of the allocation. The penalty surcharge for excess water usage will be in addition to any other remedy, penalty, or fine that may be imposed for violation of this chapter. At the city's discretion, the water conservation measures required under Level 1, Level 2, and Level 3 conditions may be suspended during the period a water allocation is in effect.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Exceptions & meaning →

14.02.080 - Level 4 water supply shortage—Emergency condition.

A. The city manager may declare a water shortage emergency pursuant to California Water Code section 350 and declare a Level 4 water supply shortage condition (a Level 4 Condition") when there is a reasonable probability, due to a projected imbalance in available water supply and projected peak demand, that there will be a supply shortage and that a consumer demand reduction of up to fifty percent is required in order to ensure that sufficient supplies will be available to meet anticipated demands. Upon declaration of Level 4 condition, the city manager or his designee shall take all necessary actions to implement the mandatory Level 4 conservation practices identified in this chapter and on the grounds provided in California Water Code section 350. In the event a Level 4 condition has been declared by the city manager, the city council shall consider the ratification of such declaration at its next regularly scheduled meeting or at a special meeting called for such purpose.

B. During the period of a declared Level 4 condition, all water customers shall be required to comply with all Level 1 condition, Level 2 condition and Level 3 condition water conservation measures and shall also comply with the following additional mandatory conservation measures:

  1. All landscape irrigation, except crops and landscape products of commercial growers and nurseries, shall be prohibited. This restriction does not apply to:

a. Watering of livestock; and

b. Essential public works projects and actively irrigated environmental mitigation projects.

  1. All water leaks, breaks of other plumbing malfunctions shall be repaired upon discovery or within twenty-four hours of notification by the City of El Paso de Robles, with the exception of rental properties, which shall be have up to seventy-two hours to repair interior unit leaks, in order to comply with state laws regarding the provision of notice to tenants.

  2. Filling or refilling of residential pools and spas is prohibited.

C. The city shall not enter into any new commitments or agreements to provide water to customers or agencies either inside or outside of the City of El Paso de Robles.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Exceptions & meaning →

14.02.090 - Procedures for determination and notification of water supply shortage level.

A. The existence of a Level 1 condition may be declared upon recommendation by the city manager along with a written determination of the existence of the facts and circumstances supporting the determination. A copy of the written determination will be filed with the city clerk. The city manager or his designee will publish a notice of the determination of existence of a Level 1 condition in the city's official newspaper. The city may also post notice of the condition on its website or include it in its regular billing statement.

The water department will monitor the projected supply and demand for water during periods of emergency or drought and will recommend to the city manager the extent of the conservation required. The city manager will recommend to the city council the implementation or termination of the appropriate level of water conservation in accordance with this chapter.

B. The existence of a Level 2 or Level 3 condition may be declared upon recommendation by the city manager and notification of the city council. The mandatory conservation measures applicable to Level 2 or Level 3 condition, as applicable, will take effect on the tenth day after the date the shortage level is declared. Within five days following the declaration of the applicable condition, the city manager or his designee will publish a notice providing the extent, terms and conditions, and any applicable exceptions respecting the use and consumption of water. In addition, the city shall provide thirty days' notice of any changes to such water use measures and exceptions. Notices shall be published, at a minimum, for three consecutive days in the newspaper used for official city notices. The city may also post notice of the condition and applicable water use measures on its website and/or include it in its regular billing statement.

C. The existence of Level 4 condition may be declared upon recommendation by the city manager. The mandatory conservation measures applicable to Level 2, Level 3, or Level 4 conditions will take effect on the fourth day after the date the shortage level is declared. Within twenty-four hours following the declaration of the shortage level, the city manager or his designee will publish a notice giving the extent, terms and conditions respecting the use and consumption of water. The notice shall be published, at a minimum, for three consecutive days in the newspaper used for official city notices. The city may also post notice of the condition on its website or include it in its regular billing statement.

D. The city council may declare an end to a particular condition upon the recommendation of the city manager by the adoption of a resolution at any regular or special meeting of the city council.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009; Ord. No. 09-962 N.S., § 1, 10-20-2009)

Exceptions & meaning →

14.02.100 - Billing adjustments.

A. If, due to unique circumstances, a specific requirement of this chapter would result in undue hardship to a customer using city water or to property upon which water is used, that is disproportionate to the impacts to water users generally or to similar property or classes of water uses, then the customer may apply for a variance to the requirements as provided in this Section 14.02.100. Unique circumstances include, but not limited to, significant water leaks (two-times average usage).

B. The variance may be granted or conditionally granted only upon a written finding of the existence of facts demonstrating an undue hardship to a customer or to property upon which water is used, that is disproportionate to the impacts to water users generally or to similar property or classes of water user due to specific and unique circumstances of the user or the user's property.

  1. Application. Application for a variance will be in written form prescribed by the city manager or his designee.

  2. Supporting Documentation. The written application will be accompanied by photographs, maps, drawings, or other pertinent information as applicable, including a written statement of the applicant.

  3. Approval Authority. The Utility Billing Adjustment Committee and/or Administrative Services personnel will exercise approval authority and act upon any completed application after submittal and may approve, conditionally approve, or deny the variance. The applicant requesting the variance will be promptly notified in writing of any action taken. The decision of the Utility Billing Adjustment Committee and/or Administrative Services personnel is final unless the applicant files a written appeal to the city manager within ten days. Unless specified otherwise at the time a variance is approved, the variance applies to the subject property during the term of the applicable condition.

  4. Required Findings for Variance. An application for a variance will be denied unless the approving authority finds, based on the information provided in the application, supporting documents, or such additional information as may be requested, and on water use information for the property as shown by the records of the City of El Paso de Robles, all of the following:

a. That the variance does not constitute a grant of special privilege inconsistent with the limitations upon other City of El Paso de Robles customers.

b. That because of special circumstances applicable to the property or its use, the strict application of this chapter would have a disproportionate impact on the property or use that exceeds the impacts upon customers generally.

c. That the authorizing of such variance will not be of substantial detriment to adjacent properties, and will not materially affect the ability of the City of El Paso de Robles to effectuate the purpose of this Chapter 14.02 and will not be detrimental to the public interest.

d. That the condition or situation of the subject property or the intended use of the property for which the variance is sought is not common, recurrent or general in nature.

  1. No relief will be granted to any customer for any reason in the absence of a showing by the customer that the customer has achieved the maximum practical reduction in water consumption in the customer's residential, commercial, industrial, institutional, agricultural or governmental water consumption.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009; Ord. No. 1081 N.S., § 3, 7-16-2019)

Exceptions & meaning →

14.02.110 - Violations and penalties.

It is unlawful for any customer to violate the mandatory provisions of this chapter. Violations are subject to criminal, civil, and administrative penalties and remedies as provided in Chapter 1 of this Code. In addition, service of water may be discontinued or appropriately limited through the installation of flow-restricting devices to any customer who willfully uses water in violation of this chapter.

(Ord. No. 956 N.S., § 2, 6-2-2009; Ord. No. 957 N.S., § 2, 6-16-2009)

Editor's note— As specified in Chapter 1.02 Penalties, Section 1.02.010, following the issuance of two warnings, a fine not exceeding one hundred dollars shall be assessed for a first violation, a fine not exceeding two hundred dollars shall be assessed for a second violation of this ordinance within one year, and a fine not exceeding five hundred dollars shall be assessed for a third violation of this ordinance within one year.

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Paso Robles Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.