Division 13B.3 — MINISTERIAL ACTION
Los Angeles Zoning Code — LAMC Chapter 1A · 2025 edition · ingested 2026-07-08 · Los Angeles
Sec. 13B.3.1. ADMINISTRATIVE REVIEW ¶
A. Applicability
i
City of Los Angeles Zoning Code Chapter 1A
i
- An Administrative Review is a ministerial approval for applications that comply with all
applicable regulations and standards of this Code.
- This Section applies where any provision of this Code requires an Administrative Review.
B. Initiation
An application for an Administrative Review is filed with the Department.
An Administrative Review is initiated as required in order to obtain a building permit.
C. Notice
- Notice of Public Hearing
There is no public hearing required for an Administrative Review, and therefore no notice of a
public hearing is required.
D. Review
- Review
The Department shall determine compliance with the applicable regulations and standards for
projects requiring an Administrative Review.
- Clearance
Clearance shall be issued as required pursuant to the applicable ordinance or building permit
requirement.
E. Criteria for Compliance Review
The Department shall review the application for compliance with the applicable regulations and
standards of this Code or the applicable Specifc Plani, including the zone standards, established
development standards, and any supplemental use regulations.
F. Scope of Action
After the Administrative Review determines that the application is in compliance with the
applicable regulations and standards, the following actions must comply with the approved plans:
The erection, enlargement or maintenance of buildings;
Any development or construction work; or
Issuance of a grading, building, demolition, or change of use permit.
i
Sec. 13B.3.1. (Administrative Review) Last Amended by Ord. No. 188,418, Eff. 01/20/2025, Oper. 01/27/2025
i
| 13-116
Administration | ARTICLE 13 Div. 13B.3. (Ministerial Action)
G. Appeals
There is no appeal.
H. Modification of Action
No modification is available.
Sec. 13B.3.1. (Administrative Review) Last Amended by Ord. No. 188,418, Eff. 01/20/2025, Oper. 01/27/2025
City of Los Angeles Zoning Code Chapter 1A
| 13-117
Administration | ARTICLE 13 Div. 13B.3. (Ministerial Action)
Sec. 13B.3.2. EXPANDED ADMINISTRATIVE REVIEW ¶
A. Applicability
- This Section (Expanded Administrative Review) applies where
any provision of this Code requires an Expanded Administrative
Review.
B. Initiation
- An application for an Expanded Administrative Review is filed
with the Department.
- An Expanded Administrative Review is initiated as required in
order to obtain a building permit.
C. Notice
- Notice of Public Hearing
The following notice is required for the public informational
hearing on the decision, if held.
APPROVE
OR DENY
APPEAL AVAILABLE
City of Los Angeles Zoning Code Chapter 1A
Sec. 13B.3.2. Expanded Administrative Review
1 Initiation
| Type of Notice |
When | Where / To Whom / Additional Requirements |
|---|---|---|
| 24 days | • The applicant; • The owner(s) of the property involved; • The owners and tenants of all properties within 300 feet of the boundary of the subject site; • The Certifed Neighborhood Council representing the area in which the property is located; and • Interested parties who have requested in writing to be notifed. |
|
| Posting | 10 days | • The applicant will post notice in a conspicuous place on the property. |
D. Review
- The Department shall determine compliance with the applicable regulations and standards for
projects requiring an Expanded Administrative Review.
- Clearance
A clearance shall be issued as required pursuant to the applicable ordinance or building permit
requirement.
Sec. 13B.3.2. (Expanded Administrative Review) Last amended by Ord. 188,478 (Resolution), Eff. 06/18/2025
| 13-118
Administration | ARTICLE 13 Div. 13B.3. (Ministerial Action)
- Public Hearing
i
i
City of Los Angeles Zoning Code Chapter 1A
i
i
If the matter has a significant effect on neighboring properties, or if required where any
provision of this Code requires an Expanded Administrative Review and a public hearing,
the Department may require an informational public hearing subject to giving notice in the manner specified in Subsection C. (Notice) .
E. Criteria for Compliance Review
The Department shall review the application for compliance with the applicable regulations
and standards of this Code, any applicable Specifc Plani, Supplemental District, or Special Zone,
including the zoning standards, established development standards, and any supplemental use
regulations.
F. Scope of Action
After the Expanded Administrative Review determines that the application complies with the
applicable regulations and standards, the following actions must comply with the approved plans:
The erection, enlargement or maintenance of buildings;
Any development or construction work; or
Issuance of a grading, building, demolition, or change of use permit.
G. Appeals
There is no appeal.
H. Modification Procedures
- Modifications Equal to or Less than 10%
a. A project approved pursuant to this Section (Expanded Administrative Review) may seek a
modification to modify conditions of approval for the original action prior to the issuance
of the Certificate of Occupancy.
b. For purposes of this Section (Expanded Administrative Review), a “modification” means any
changes in the proposed physical development or related conditions of approval that were
approved in the original action by no more than 10 percent.
c. A modification does not include the granting of any new rights or increased or additional
incentives, nor does it include the granting of any new deviation from zoning regulations
in this Chapter or Chapter I. (General Provisions and Zoning) of this Code.
d. An application for a modification pursuant to this Section (Expanded Administrative
Review) shall be filed with the Department before the original action expires and include development plans showing the requested modifications.
i
i
Sec. 13B.3.2. (Expanded Administrative Review) Last amended by Ord. 188,478 (Resolution), Eff. 06/18/2025
i
i
| 13-119
Administration | ARTICLE 13 Div. 13B.3. (Ministerial Action)
i
City of Los Angeles Zoning Code Chapter 1A
i
e. In approving a modification pursuant to this Section (Expanded Administrative Review), the
Department shall review the application for compliance with the applicable regulations
and standards of this Code or any applicable Specifc Plani, Supplemental District, or
Special Zone, including the zoning standards, established development standards, and any
supplemental use regulations
- Modifications Greater than 10%
Any request for a modification that exceeds the ten percent limitation will not be processed as a modification of the original action under this Subsection (Modification Procedures) and shall instead require a filing of a new Expanded Administrative Review Application pursuant to this
Section (Expanded Administrative Review) .
i
Sec. 13B.3.2. (Expanded Administrative Review) Last amended by Ord. 188,478 (Resolution), Eff. 06/18/2025
i
| 13-120
Administration | ARTICLE 13 Div. 13B.4. (Specific Plan Implementation)