(a) Upon completion of review of a development review permit the Development Review Committee shall either:
Make such findings as are required by Section 56.5 and approve the application; or
Notify the applicant of those changes and modifications required for approval of the application; or
56-2
Deny the application if the Development Review Committee finds that:
i. The application cannot be conditioned by adequate requirements to insure compliance with applicable regulations, or
ii. The application cannot reasonably be modified to conform to the applicable regulations.
(b) Development review permits shall be effective upon issuance, unless within seven (7) calendar days of a decision by the Committee, the decision is appealed as provided for in Section 56.7. In case an appeal is filed, the development review permit shall not have any force or effect until a decision is made by the Review Authority on such appeal.
(c) Development review permits shall not have any force or effect until the permittee acknowledges receipt thereof and has agreed in writing to each and every term and condition thereof.