§ 12.36.130. Requirement at subdivision, reversion or conversion.¶
Pursuant to the requirements of Sections 12.36.130 through 12.36.180, whenever any tentative tract or parcel maps or map for the reversion of lots to acreage is filed or whenever a building permit is requested for the development or redevelopment of new or relocated buildings or structures, or whenever a residential building or use is converted to any purpose or use other than that which existed at the time of conversion, then all electrical, telephone, community antenna television and similar service wires or cables, which provide direct service to the property being developed shall, within the exterior boundary lines of such property and the off-site service line from the point of source, be installed underground.
(Ord. 771 § 4, 1970; Ord. 1125, 1980)
§ 12.36.140. Requirement at addition or electrical renovation.¶
Whenever a use or building permit is requested for the addition of floor space equal to or in excess of two hundred square feet is added to an existing building or structure in any zone except R-1, or whenever a new electrical service is installed in an existing building in any zone except R-1, then all electrical, telephone, community antenna television and similar service wires or cables which provide direct service to the property being developed shall, within the exterior boundary lines of such property, be installed underground.
(Ord. 771 § 4, 1970; Ord. 1125, 1980)
§ 12.36.150. Aboveground appurtenances.¶
For the purposes of Sections 12.36.130 through 12.36.180, appurtenances and associated equipment such as, but not limited to, surface-mounted transformers, pedestal-mounted terminal bases and meter cabinets, may be placed aboveground.
(Ord. 771 § 4, 1970; Ord. 1125, 1980)
§ 12.36.160. Compliance.¶
The developer or owner is responsible for complying with the requirements of Sections 12.36.130 through 12.36.180 and shall provide all necessary facilities on their premises so as to receive such services from the supplying utility or utilities subject to the applicable rules, regulations and tariffs of the respective utility or utilities on file with the State Public Utilities Commission.
(Ord. 771 § 4, 1970; Ord. 1125, 1980)
§ 12.36.170. Waiver, modification or delay.¶
Where practical difficulties or unnecessary hardships inconsistent with the purposes of Sections 12.36.130 through 12.36.180 result from their literal interpretation or enforcement, the planning commission may waive, modify or delay the application of any undergrounding requirement upon written request by a building site owner. Such request shall be filed with the planning commission and shall contain any and all facts which are offered in support.
(Ord. 771 § 4, 1970; Ord. 1125, 1980)
§ 12.36.180. Deposit for delayed compliance.¶
If the planning commission's action is to delay the installation of required underground utilities as provided in Section 12.36.170, it may require the building site owner to file with the city a cash deposit, and record a covenant sufficient to provide for the future installation of the underground features which are to be delayed. The amount of the cash deposit shall be determined by the building director.
(Ord. 771 § 4, 1970; Ord. 1125, 1980)