15.81.030 Permit Required

No person shall conduct a surface mining operation, or substantially change an existing or previously approved operation, or expand a surface mining operation beyond the boundaries of any area in which vested rights to mine exist, without first obtaining a conditional use permit from the county for such a surface mining operation. The reclamation plan required by SMARA and this chapter shall be included in each such use permit, and the right to conduct surface mining operations pursuant to the permit is contingent upon the prior filing with the county of adequate financial assurances to secure the completion of the reclamation plan. (Ord. 1183 § 2, 2006)

15.81.040 Reclamation Plan Standards

Each reclamation plan shall:

  1. Include measures specified by the county to implement state policy on grading, backfilling, resoiling, revegetation, soil compaction, other reclamation requirements, and measures for soil erosion control, water quality and watershed control, waste disposal, and flood control;

  2. Be applicable to a specific piece of property or properties, shall be based upon the character of the surrounding area and such characteristics of the property as type of overburden, soil stability, topography, geology, climate, stream characteristics, and principal mineral commodities, and shall establish site-specific criteria for evaluating compliance with the approved reclamation plan, including topography, revegetation, and sediment and erosion control;

  3. Be subject to the reclamation performance standards in 14 CCR § 3700 through 3713. These standards shall apply to each mining operation, but only to the extent that they are consistent with the planned or actual subsequent use or uses of the mining site;

  4. Include any additional performance standards developed either in review of individual projects, as warranted, or through the formulation and adoption of countywide performance standards. (Ord. 1183 § 2, 2006)

15.81.050 Activities Excepted

The provisions of this chapter do not apply to any activities excepted from the application of SMARA pursuant to Public Resources Code Section 2714. (Ord. 1183 § 2, 2006)

15.81.060 Designated Areas And State Policy

Areas of regional significance” and “areas of statewide significance,” as may be designated by the State Mining and Geology Board, and “state policy” and related regulations as may be adopted by the State Mining and Geology Board, shall be recognized in the administration of this chapter per provisions of the act. (Ord. 1183 § 2, 2006)

15.81.070 Relation To Other Provisions Of Law

Surface mining and related operations regulated by this chapter shall be subject to zoning regulations and other applicable provisions of law. (Ord. 1183 § 2, 2006)

15.81.080 Submittal Of Application

Application for a conditional use permit for surface mining and approval of a reclamation plan shall be submitted by, or with the written approval of, the landowner, on forms provided by the director. The reclamation plan shall constitute a part of the permit application, and shall include both operations and reclamation proposals. (Ord. 1183 § 2, 2006)

15.81.090 Contents Of Application

The application shall include the following information and documents, except as may otherwise be determined by the TAC:

  1. Names and addresses of the landowners, the holder of mineral rights, the operator, and any persons designated as their agents for the service or process;

  2. A signed statement that the person submitting the application accepts responsibility for conducting the operations and reclaiming the mined lands in accordance with the permit and plan as approved, and that all owners of possessory interest in the land have been notified of the application and proposals therein. The statement shall also include: 1. The proposed dates for the initiation and termination of the mining operation; and

    1. The anticipated type and quantity of minerals to be mined, and the maximum depth of mining.
  3. Site location, description, including maps, plans and descriptive statements to show: 1. Legal description of lands in application; and

  4. A map showing boundaries, topographic details, and the general geology of the total area; detailed geology of the proposed surface mining area; location and identification of all streams, roads, railroads, utility facilities, and dwellings and other structures on or adjacent to the permit site; and names and addresses of owners of adjoining lands and of mineral rights thereon.

  5. Operations plan, including maps, plans, and descriptive statements to show: 1. The type of mining to be employed, and a schedule showing locations and dates for the start and completion of mining on segments of the total mining area, and when reclamation may be anticipated to be started on each of such segments; and

  6. A description of the proposed operation, including seasons, days and hours of operations; access and trucking route and the number and timing of daily truck trips; measures for control of noise, dust, erosion, flooding and water pollution, proposed fencing, screening, landscaping, etc.

  7. Reclamation plan, to be a plan applicable to the particular property, and based upon the character of the surrounding area and on reclamation site characteristics such as type of overburden, soil stability, topography, geology, climate, stream characteristics, and principal mineral commodities. The plan shall include:

    1. A description of the manner in which reclamation, adequate for the proposed use or potential uses, will be accomplished, and including the manner in which contaminants will be controlled, and mining waste will be disposed of; the manner in which rehabilitation of affected stream channels and banks, and drainage ways, will be accomplished to minimize erosion and sedimentation; proposals for backfilling, grading, bank sloping, resoiling, revegetation, soil compaction and stabilization, and other reclamation measures; and

including the manner in which contaminants will be controlled, and mining waste will be disposed of; the manner in which rehabilitation of affected stream channels and banks, and drainage ways, will be accomplished to minimize erosion and sedimentation; proposals for backfilling, grading, bank sloping, resoiling, revegetation, soil compaction and stabilization, and other reclamation measures; and

  1. A description of the proposed use or potential uses of the land after reclamation, and an assessment of the effect of the reclamation plan on future mining in the area; 3. Other information which the commission may find necessary in particular cases including the amount and type of financial assurances proposed; 4. A statement that the person submitting the plan accepts responsibility for reclaiming the mined lands in accordance with the reclamation plan. (Ord. 1183 § 2, 2006) 15.81.100 Filing Of Application 1. When all required information related to the application has been submitted to the director together with the fees as adopted by the board of supervisors and checked and found acceptable, the director shall accept the application as being properly filed. 2. The director shall then notify the Department of Conservation of the filing, and shall furnish the department with copies of the application, plan and other related documents, and the director may request that the department furnish technical assistance in its review of the reclamation plan. 3. The fees required for determinations under this chapter shall be as adopted by the board of supervisors in the county book of administrative policies and procedures. 4. Whenever surface mining operations are proposed in the one-hundred-year floodplain for any stream, as shown in Zone A of the Flood Insurance Rate Maps issued by the Federal Emergency Management Agency, and within one mile, upstream or downstream, of any state highway bridge, the planning authority upon receiving the application for the issuance or renewal of a permit to conduct the surface mining operations shall notify the Department of Transportation that the application has been received. The Department of Transportation shall have a period of not more than forty-five days to review and comment on the proposed surface mining operations with respect to any potential damage to the state highway bridge from the proposed surface mining operations. The planning commission shall not issue or renew the permit until the Department of Transportation has submitted its comments or until forty-five days from the date the application for the permit was submitted, whichever occurs first. (Ord. 1183 § 2, 2006) 15.81.110 Public Hearing And Notice 1. The application for the conditional use permit shall be processed and approved, conditionally approved, or denied according to the processes prescribed in Chapter 15.22, Conditional Use Permit, of this code. 2. The decision on a conditional use permit may be appealed according to the process prescribed in Chapter 15.050, Appeals, of this code. 3. Prior to approving a reclamation plan, the approving body shall find that: 1. The project has been reviewed pursuant to CEQA and the county’s environmental review guidelines, all adverse impacts related to the reclamation plan have been mitigated by the plan or the recommended conditions of approval, and the appropriate environmental determination has been adopted; 2. The reclamation plan complies with the requirements of SMARA, specifically Public Resources Code Sections 2772 and 2773, and the Reclamation Standards specified in California Code of Regulations, Title 14, Division 2, Chapter 8, Subchapter 1, Article 9, Sections 3700 through 3713;

plan or the recommended conditions of approval, and the appropriate environmental determination has been adopted; 2. The reclamation plan complies with the requirements of SMARA, specifically Public Resources Code Sections 2772 and 2773, and the Reclamation Standards specified in California Code of Regulations, Title 14, Division 2, Chapter 8, Subchapter 1, Article 9, Sections 3700 through 3713;

  3. The reclamation plan has been forwarded to the Department of Conservation pursuant to Section 15.81.180; 
  1. The reclamation plan complies with the purpose, intent, and requirements of Chapter 15.81, Surface Mining and Reclamation, of the Glenn County Code; 5. The proposed goal of reclamation is consistent with the general plan policies and the zone district for the area. (Ord. 1183 § 2, 2006)

15.81.120 Appeal Of Planning Commission Action 1. Any aggrieved person or entity adversely affected by a formal action under the “Surface Mining and Reclamation Act” (SMARA) of the Glenn County Planning Commission, may appeal such action by filing a written notice thereof with the Clerk of the Board of Supervisors within ten (10) calendar days after the action of the Planning Commission.

  1. Within thirty calendar days from the date of filing the appeal, the Clerk of the Board shall schedule the date for the hearing. 3. The hearing shall be held within sixty calendar days from the date of filing the appeal. Notice of hearing shall be given as required by the California Government Code. The Board of Supervisors may continue such hearing for one additional meeting, to be held within thirty days, any further continuances shall be with the consent of the appellant.

  2. The Board of Supervisors shall hear the matter de novo (a new hearing): 1. The written documents relied on by the Planning Commission to take the action and the minutes of the hearing(s) before the Planning Commission shall be a part of the Board’s record at the appeal hearing on the matter.

  3. As part of the hearing do novo the Board shall hear such additional relevant evidence as may be offered.

    1. Appeal Hearing – Procedure and Order of Presentation

      1. Staff Reports(s)

      2. Open the Public Hearing on the matter.

        1. Appellant’s Presentation.

        2. Respondent’s Presentation.

  4. Additional Public Testimony in favor of the appeal. 4. Additional Public Testimony opposed to the appeal.

  5. Respondent’s Rebuttal (if any).

  6. Appellant’s Rebuttal (if any).

      7. Close the Public Hearing. 
    
    1. Discussion of the matter by the Board of Supervisors.

    2. Decision of the Board of Supervisors. Affirm, reverse or modify, in whole of in part, the order, requirement, decision, recommendation, interpretation, or ruling of the Planning Commission appealed from, or make and substitute such other or additional decision(s) or determination(s) as it may find warranted under the laws and facts as follows:

  7. Ask the staff to prepare written finding for the Board to adopt at the next regularly scheduled Board meeting setting forth the reasons for their decision sustaining, reversing or modifying the decision for the Planning Commission; or

  8. May adopt a motion as a result of the hearing which is recorded in the minutes and may incorporate by reference all or part of the proposed findings in the staff report which the Board relied on to reach their decision; and the Clerk of the Board shall transmit a copy of the decision to the appellant and the applicant, if different than the appellant. (Ord. 1183 § 2, 2006)

15.81.130 Appeal From Action Of The Board Of Supervisors Within ten days of the board of supervisors actions on an appeal related to a site in an area of statewide or regional significance, an aggrieved person may file a written appeal with the State Mining and Geology Board, as provided in the act. (Ord. 1183 § 2, 2006) 15.81.140 Minor Modifications To Reclamation Plans 1. Minor modifications to reclamation plans may be approved by the director without public notice or consultation with the Department of Conservation. A minor modification to a reclamation plan may be approved only if it meets the following standards:

  1. To allow the minor recontouring of final topography effecting no more than ten percent of the site, provided that slope stability is maintained and substantiated; 

  2. To allow minor modification or addition of site access including new on-site roads and encroachments directly from the site to a public road, but not including new off-site roads; 3. To allow a minor substitution in the reclamation plan such as a substitution in the type and/or number of plant species, minor change in topsoil treatment, etc., provided it does not substantially alter the intended end-use described in the approved reclamation plan; 

  4. To allow minor technological or administrative changes in methods used to achieve reclamation; 

  5. To allow measures to be taken which will ensure or maintain public safety (e.g. fences, gates, signs, or hazard removal), provided such measures do not substantially alter the intended enduse described in the approved reclamation plan; 

  6. To allow minor modifications to a previously approved phasing plan; 

  7. To allow compliance with the requirements of other public agencies, provided the requirements are not inconsistent with the approved conditional use permit; 8. A minor modification shall not include changing the end use of the land. 
  1. Applications for a minor modification shall be made on a checklist form provided by and filed with the planning authority.

  2. Prior to approval of a minor modification, the director shall make the following written findings which shall include the reasons for the findings: 1. The minor modification is consistent with the approved conditional use permit and does not represent a significant change to the approved reclamation plan for the subject surface mining operations.

  3. The minor modification is not subject to CEQA.

  4. The director shall approve, conditionally approve, or disapprove an application for a minor modification within 45 days of accepting the application as complete, and give notice by mail of the decision, including any conditions of approval, to the applicant.

  5. The decision of the director regarding a minor modification of a conditional use permit shall be appealable to the planning commission within 5 calendar days of said decision. The decision of the planning commission regarding the appeal shall be appealable to the board of supervisors within 5 calendar days of said decision.

  6. Within 30 days of final action, the director shall send a copy of an approved minor modification to the Department of Conservation. (Ord. 1183 § 2, 2006)

15.81.150 Idle Mines

  1. Within 90 days of a surface mining operation becoming idle, the operator shall submit to the department of planning authority for review and approval, an interim management plan. The review and approval of an interim management plan shall not be considered a project within the meaning of the California Environmental Quality Act.

  2. The approved interim management plan shall be considered an amendment to the surface mining operation’s approved reclamation plan, for purposes of this chapter. The interim management plan shall provide measures the operator will implement to maintain the site in compliance with this chapter, including, but not limited to, all permit conditions.

  3. Prior to county approval, interim management plans shall be submitted for review to the Department of Conservation for a 45-day review period.

  4. The director may approve an interim management plan without a public notice or public hearing if the director determines that the interim management plan does not require significant changes to the reclamation plan. The decision of the director shall be appealable to the planning commission within five calendar days of the decision. The decision of the planning commission shall be appealable to the board of supervisors within five calendar days of the decision.

  5. The interim management plan may remain in effect for a period not to exceed five years, at which time the director shall do one of the following:

  6. Renew the interim management plan for another period not to exceed five years, if the director finds that the surface mining operator has complied fully with the interim management plan; 2. Require the surface mining operator to commence reclamation in accordance with its approved reclamation plan.

  7. In any event, financial assurances required shall remain in effect during the period the surface mining operation is idle. If the surface mining operation is still idle after expiration of its interim management plan, the surface mining operation shall commence reclamation in accordance with its approved reclamation plan.

  8. Within 60 days of the receipt of the interim management plan or a longer period mutually agreed upon by the county and the operator, the county shall review and approve the plan in accordance with this chapter and so notify the operator in writing of any deficiencies in the plan. The operator shall have thirty days, or a longer period mutually agreed upon by the operator and the county, to submit a revised plan. The operator shall have 30 days, or a longer period mutually agreed upon by the operator and the county, to submit a revised plan.

  9. The director shall approve or deny approval of the revised interim management plan within 60 days of receipt. If the director denies approval of the revised interim management plan, the operator may appeal the action to the planning commission which shall schedule a public hearing to be held within 45 days of the filing of the appeal or any longer period mutually agreed upon by the operator and the planning commission. The action of the planning commission may be appealed to the board of supervisors within 10 days of said action.

  10. Unless review of an interim management plan is pending before the director, or an appeal is pending before the planning commission, a surface mining operation which remains idle for over one year after becoming idle as defined in this chapter without obtaining approval of an interim management plan shall be considered abandoned and the operator shall commence and complete reclamation in accordance with the approved reclamation plan. (Ord. 1183 § 2, 2006)

15.81.160 Financial Assurances

  1. Financial assurances are required to secure performance of the reclamation plan approved for each surface mining operation to which this chapter applies and shall be sufficient to perform reclamation of lands remaining disturbed. Financial assurances determined to substantially meet these requirements shall be approved by the county for purposes of this chapter. Except as specified in Public Resources Code Section 2770(e) or (i), unless the operator has filed on or before January 1, 1994, an appeal pursuant to Public Resources Code Section 2770(e) with regard to non-approval of financial assurances, and that appeal is pending before the State Mining and Geology Board, the continuation of the surface mining operation is prohibited until financial assurances for reclamation are approved by the county.

  2. The county shall require financial assurances of each surface mining operation to ensure reclamation is performed in accordance with the surface mining operation’s approved reclamation plan, as follows: 1. Financial assurances may take the form of surety bonds, irrevocable letters of credit, trust funds, or other forms of financial assurances specified by the State Mining and Geology Board pursuant to Public Resources Code Section 2773.1(e), which the county reasonably determines are adequate to perform reclamation in accordance with the surface mining operation’s approved reclamation plan.

    1. The financial assurances shall remain in effect for the duration of the surface mining operation and any additional period until reclamation is completed.
  3. The amount of financial assurances required of a surface mining operation for any one year shall be adjusted annually to account for new lands disturbed by surface mining operations, inflation, and reclamation of lands accomplished in accordance with the approved reclamation plan.

    1. The financial assurances shall be made payable to the county and the Department of Conservation. Financial assurances that were approved by the county prior to January 1, 1993, and were made payable to the State Geologist shall be considered payable to the Department of Conservation for purposes of this chapter. However, if a surface mining operation has received approval of its financial assurances from a public agency other than the county, the county shall deem those financial assurances adequate for purposes of this section, or shall credit them toward fulfillment of the financial assurances required by this section, if they are made payable to the public agency, the county, and the Department of Conservation and otherwise meet the requirements of this section. In any event, if the county and one or more public agencies exercise jurisdiction over a surface mining operation, the total amount of financial assurances required by the county and the public agencies for any one year shall not exceed that amount which is necessary to perform reclamation of lands remaining disturbed. For purposes of this paragraph, a “public agency” may include a federal agency.

    2. Estimates for financial assurances shall include descriptions of the tasks to be performed, identification of equipment, labor and materials requirements, definition of units costs, total cost per task, total direct cost of reclamation, and administrative costs including costs of supervision, profit and overhead, contingencies and mobilization. Additional required information may include a site plan showing the present limits of the disturbed area to be reclaimed, and other information necessary to verify the estimate. In projecting the costs of financial assurances, it shall be assumed without prejudice or insinuation that the surface mining operation could be abandoned by the operator and, consequently, that the county or state may need to contract with a third-party commercial company for reclamation of the site.

    3. Financial assurances determined not to substantially meet the requirements of Public Resources Code Section 2773.1 shall be returned to the operator within 60 days. The operator has 60 days to revise the financial assurances to address identified deficiencies, at which time the revised financial assurances shall be returned to the county for review and approval.

    4. Prior to county approval, financial assurances shall be forwarded to the Department of Conservation pursuant to Section 15.81.180.

  4. The decision to approve financial assurance estimates and mechanisms shall be made by the director. The financial assurance estimates shall be based on an approved reclamation plan. No public notice or public hearing is required. The decision to approve financial assurance estimates and mechanisms is not subject to CEQA. The director’s decision is appealable to the Planning Commission within 10 calendar days of the decision. The decision of the planning commission is appealable to the Board of Supervisors within 10 calendar days of the decision.

    1. Financial assurances shall no longer be required of a surface mining operation, and shall be released, upon written notification by the county, which shall be forwarded to the operator and the Director of the Department of Conservation, that reclamation has been completed in accordance with the approved reclamation plan. If a mining operation is sold or ownership is transferred to another person, the existing financial assurances shall remain in force and shall not be released by the county until new financial assurances are secured from the new owner and have been approved by the county in accordance with Section 2770.

    2. If the county, following a public hearing, determines that the operator is financially incapable of performing reclamation in accordance with its approved reclamation plan, or has abandoned its surface mining operation without commencing reclamation, the director shall do all of the following:

      1. Notify the operator by personal service or certified mail that the county intends to take appropriate action to forfeit the financial assurances and specify the reasons for so doing. 2. Allow the operator 60 days to commence or cause the commencement of reclamation in accordance with its approved reclamation plan and require that reclamation be completed within the time limits specified in the approved reclamation plan or some other time period mutually agreed upon by the county and the operator.

      2. Proceed to take appropriate action to require forfeiture of the financial assurances if the operator does not substantially comply with paragraph 2, above.

      3. Use the proceeds from the forfeited financial assurances to conduct and complete reclamation in accordance with the approved reclamation plan. In no event shall the financial assurances be used for any other purpose. The operator is responsible for the costs of conducting and completing reclamation in accordance with the approved reclamation plan which are in excess of the proceeds from the forfeited financial assurances. (Ord. 1183 § 2, 2006)

  • 15.81.170 Annual Reports And Inspection 1. As a condition of approval of the permit and reclamation plan, a schedule for annual inspections of the site shall be established to evaluate continuing compliance with the permit and reclamation plan.

    1. The planning authority shall conduct an inspection of a surface mining operation within six months of receipt by the planning authority of the surface mining operation’s report submitted pursuant to this chapter, solely to determine whether the surface mining operation is in compliance with this chapter. In no event shall the planning authority inspect a surface mining operation less than once in any calendar year.
    1. All inspections shall be conducted using a form developed by the Department of Conservation and approved by the State Mining and Geology Board. The operator shall be solely responsible for the reasonable cost of the inspection.
    1. The planning authority shall notify the Department of Conservation within thirty days of completion of the inspection that the inspection has been conducted. The notice shall contain a statement regarding the surface mine’s compliance with this chapter, shall include a copy of the completed inspection form, and shall specify which aspects of the surface mining operation, if any, are inconsistent with this chapter.
    1. If the surface mining operation has an appeal pending in the case of a surface mining operator with vested rights, a review of existing financial assurances pending, or an appeal pending, the notice shall so indicate.
    1. The planning authority shall forward to the operator a copy of the notice and any supporting documentation, including, without limitation, any inspection report prepared by the geologist, civil engineer, landscape architect, or forester. (Ord. 1183 § 2, 2006)
  • 15.81.180 State Review

    1. Prior to approving a surface mining operation’s use permits, financial assurances, including existing financial assurances reviewed by the county pursuant to subdivision (C) of Public Resources Code Section 2770, the county shall submit the plan, assurances, or amendments to the Director of the Department of Conservation for review.

    2. The Director of the Department of Conservation shall have 30 days to prepare written comments for use permits and amendments and 45 days for review of financial assurances and amendments, if the Director of the Department of Conservation so chooses. The county shall evaluate written comments received from the Director of the Department of Conservation during the comment period. The county shall prepare a written response describing the disposition of the major issues raised. In particular, when the county’s position is at variance with the recommendations and objections raised in the Director of the Department of Conservation’s comments, the written response shall address, in detail, why specific comments and suggestions were not accepted. Copies of any written comments received and responses prepared by the county shall be forwarded to the operator.

r issues raised. In particular, when the county’s position is at variance with the recommendations and objections raised in the Director of the Department of Conservation’s comments, the written response shall address, in detail, why specific comments and suggestions were not accepted. Copies of any written comments received and responses prepared by the county shall be forwarded to the operator.

  1. The county shall notify the Director of the Department of Conservation of the filing of an application for a permit to conduct surface mining operations within 30 days of such an application being filed with the county. By July 1 of each year, the county shall submit to the Director of the Department of Conservation for each active or idle mining operation a copy of any permit or reclamation plan amendments, as applicable, or a statement that there have been no changes during the previous year. Failure to file with the Director of the Department of Conservation the information required under this section shall be cause for action under Public Resources Code Section 2774.4.

  2. Whenever a permit application proposes surface mining operations in the 100-year flood plain for any stream, as shown in Zone A of Flood Insurance Rate Maps issued by the Federal Emergency Management Agency, and within one mile, upstream or downstream, of any state highway bridge, the county shall notify the Department of Transportation that the application has been received. The Department of Transportation shall have a period of not more that 45 days to review and comment on the proposed surface mining operations with respect to any potential damage to the state highway bridge from the proposed surface mining operations. The county shall not issue or renew the permit until the Department of Transportation has submitted its comments or until 45 days from the date the application for the permit was submitted, whichever occurs first. (Ord. 1183 § 2, 2006) 15.81.190 Transferability 1. Whenever one operator succeeds to the interest of another in any uncompleted surface mining operation by sale, assignment, transfer, conveyance, exchange, or other means, the successor shall be bound by the provisions of the approved reclamation plan and the provisions of this chapter. 2. Financial assurances provided by the operator’s successor to the county and the Department of Conservation shall have been approved, and the financial assurance mechanism shall be in place prior to the continuation of surface mining operations. (Ord. 1183 § 2, 2006) 15.81.200 Permit Revocation Following a hearing held pursuant to Chapter 15.04, the commission may revoke a permit on a finding of noncompliance with any term or condition of the permit, this chapter or SMARA. (Ord. 1183 § 2, 2006) 15.82 Vendor Permits 15.82.010 Application For A Vendor's Permit 15.82.020 Standards For Vendor Permits 15.82.030 Where Allowed 15.82.010 Application For A Vendor's Permit

1.200 Permit Revocation Following a hearing held pursuant to Chapter 15.04, the commission may revoke a permit on a finding of noncompliance with any term or condition of the permit, this chapter or SMARA. (Ord. 1183 § 2, 2006) 15.82 Vendor Permits 15.82.010 Application For A Vendor's Permit 15.82.020 Standards For Vendor Permits 15.82.030 Where Allowed 15.82.010 Application For A Vendor's Permit

  1. Whenever one operator succeeds to the interest of another in any uncompleted surface mining operation by sale, assignment, transfer, conveyance, exchange, or other means, the successor shall be bound by the provisions of the approved reclamation plan and the provisions of this chapter.

  2. Applications for a vendor’s permit shall be accompanied by photos or renderings of sales structures to be used, and shall be submitted to the planning authority.

  3. The application shall specify all locations where sales are proposed.

  4. The application shall be accompanied by an itinerant business permit, if applicable, for proposed use issued by the County.

  5. An application involving the sale of any prepared food, seafood, snack bars, pre-packaged food, approved unpacked food, or similar food item for retail sale, or distribution at no cost, shall be accompanied by a food service or food facility permit issued by the Glenn County Health Department pursuant to the requirements of the California Retail Food Facilities Law.

  6. Vendor permits may be issued for the retail sale of items such as flowers, balloons, souvenirs, news publications, and food items such as hot dogs, sandwiches, candy, ice cream and similar items. 6. The vendor shall post the permit in a conspicuous space for the immediate inspection by the Sheriff or other officer of the county. (Ord. 1183 § 2, 2006)

15.82.020 Standards For Vendor Permits

  1. Only one (1) vendor permit may be permitted per lot.

  2. Hours of operation shall be limited to the hours between 8:00 a.m. and 9:00 p.m. daily.

  3. Only two (2) carts, push carts, stands, trailers, kiosks or similar sales structures not exceeding one hundred sixty (160) square feet in area shall be used in conjunction with a vendor’s permit. 4. A vendor’s permit shall only be valid for sixty (60) days. (Ord. 1183 § 2, 2006)

15.82.030 Where Allowed

Vendor permits shall only be granted for the Commercial, Industrial, Service Commercial, Local Commercial, Highway Commercial, Planned Development Commercial and Planned Development Residential Zoning Districts. No vendor permits shall be required for nonprofit organizations or for sales of produce. (Ord. 1183 § 2, 2006)

15.83 Well, Class II Injection 15.83.010 Purpose And Findings 15.83.020 Conditional Use Permit 15.83.030 Permit Requirement Of Applicant 15.83.040 Permit Term 15.83.050 Fees 15.83.060 Conditions Of Permit 15.83.070 Suspension Of Permit

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — Glenn County Zoning Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.