Earlier editions: 2026-09
Chapter 8A — Flood Damage Prevention
Fairfield Municipal Code Art. II Definitions
Fairfield Municipal Code · 2026-10 edition · updated 2026-10-04 · Fairfield
Cite as: Fairfield Municipal Code Article II · Text as of 2026-10-04
§ 8A.2.1. Definitions.¶
Unless specifically defined below, words or phrases used in this chapter shall be interpreted so as to give them the meaning they have in common usage to give this ordinance its most reasonable application.
"Area of shallow flooding"
means a designated AO or AH Zone on the Flood Insurance Rate Map (FIRM). The base flood depths range from one to three feet; a clearly defined channel does not exist; the path of flooding is unpredictable and indeterminate; and, velocity flow may be evident.
"Area of special flood hazard"
means the land in the floodplain within a community subject to a one percent or greater chance of flooding in any given year. This area is designated as Zone A, AO, AH, AE, A1-30 on the FIRM.
"Base flood"
means the flood having a one percent chance of being equalled or exceeded in any given year.
"Basement"
means any area of the building having its floor subgrade - i.e. below ground level - on all sides.
"Development"
means any manmade change to improved or unimproved real estate, including, but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials.
"Encroachment"
means the advance or infringement of uses, plant growth, fill, excavation, buildings, permanent structures, or development into a flood plain which may impede or alter the flow capacity of a flood plain.
"Existing manufactured home park or subdivision"
means a manufactured home, park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed before July 5, 1984, which is the original adoption date of the floodplain management regulations adopted by the City of Fairfield.
"Expansion to an existing manufactured home park or subdivision"
means the preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads).
"Flood" or "flooding"
means a general and temporary condition of partial or complete inundation of normally dry land areas from:
(a)
The overflow of inland or tidal waters; and/or
(b)
The unusual and rapid accumulation of runoff of surface waters from any source.
"Flood Boundary Floodway Map"
means the office map on which the Federal Insurance Administration has delineated both the areas of flood hazard and the floodway.
"Flood Insurance Rate Map (FIRM)"
means the official map on which the Federal Insurance Administration has delineated both the areas of special flood hazards and the risk premium zones applicable to the community.
"Flood Insurance Study"
means the official report provided by the Federal Emergency Management Agency that includes flood profiles, the FIRM, the Flood Boundary Floodway Map, and the water surface elevation of the base flood.
"Floodproofing"
means any combination of structural and nonstructural additions, changes or adjustments to nonresidential structures which reduce or eliminate flood damage to real estate or improved property. "Flood related erosion" is a condition that exists in conjunction with a flooding event that alters the composition of the shoreline or bank of a watercourse, or a condition that increases the possibility of loss due to the erosion of the land area adjacent to the shoreline or watercourse.
"Floodway"
means the channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than one (1) foot. The floodway is delineated on the Flood Boundary Floodway Map.
"Freeboard"
means a factor of safety above a flood level for purposes of flood plain management. Freeboard tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of watershed urbanization.
"Historic structure"
means any structure that is:
(a)
Listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;
(b)
Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district;
(c)
Individually listed on a state inventory of historic places in states with historic preservation programs which have been approved by the Secretary of Interior; or
(d)
Individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either by an approved state program as determined by the Secretary of the Interior or directly by the Secretary of the Interior in states without approved programs.
"Lowest Floor"
means the lowest floor of the lowest enclosed area (including basement). An unfinished or flood resistant enclosure, usable solely for parking of vehicles, building access or storage, in an area other than a basement area, is not considered a building’s lowest floor, provided that such enclosure is not built so as to render the structure in violation of the applicable non elevation design requirements of this ordinance.
"Hazard Mitigation Plan"
A plan that incorporates a process whereby the potential of future loss due to flooding can be minimized by planning and implementing alternatives to flood plain development community wide.
"Highest Adjacent Grade"
means the highest natural elevation of the ground surface prior to construction next to the proposed walls of a structure.
"Manufactured home"
means a structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when connected to the required utilities. The term "manufactured home" does not include a "recreational vehicle".
"Manufactured home park or subdivision"
means a parcel or contiguous parcels of land divided into two or more manufactured home lots for rent or sale.
"New construction"
means structures for which the "start of construction" commenced on or after July 5, 1984, which is the original adoption date of this chapter, and includes any subsequent improvements to such structures.
"New manufactured home park or subdivision"
means a manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after July 5, 1984, which is the original adoption date of floodplain management regulations adopted by the City of Fairfield.
"Recreational Vehicle"
means a vehicle which is:
(a)
Built on a single chassis;
(b)
400 square feet or less when measured at the largest horizontal projection;
(c)
Designed to be self-propelled or permanently towable by a light duty truck; and
(d)
Designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
"Start of Construction"
(for other than new construction or substantial improvements under the coastal barrier resources act (Pub. L. 97-348), includes substantial improvement and other proposed new development and means the date the building permit was issued, provided the actual start of construction, repair, reconstruction, placement, or other improvement was within 180 days of the permit date. The actual start means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
"Structure"
means a walled and roofed building, manufactured home, or gas or liquid storage tank that is principally above ground.
"Substantial damage"
means damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.
"Substantial improvement"
means any repair, reconstruction, or improvement of a structure, the cost of which equals or exceeds 50 percent of the market value of the structure either:
(a)
Before the improvement or repair is started, or
(b)
If the structure has been damaged and is being restored, before the damage occurred.
For the purposes of this definition, "substantial improvement" is considered to occur when the first alteration of any wall, ceiling, floor, or other structural part of the building commences, whether or not that alteration affects the external dimensions of the structure. This term includes structures that have incurred "substantial damage", regardless of the actual repair work performed. This term does not, however, include either:
| (a) | Any project for improvement of a structure to comply with existing state or local health, sanitary, or safety code specifications which have been identified by the local code enforcement official, and which are solely necessary to assure safe living conditions, or |
|---|---|
| (b) | Any alteration of a "historic structure", a structure listed on the national register of historic places, or a state inventory of historic places provided that the alteration will not preclude the structure’s continued designation as a "historic structure". |
"Violation"
means the failure of a structure or other development to fully comply with the community’s flood plain management regulations that are contained in this code. A structure or other development without an elevation certificate and other evidence of compliance required by the City is presumed to be in violation until such time as that documentation is provided.
(Ord. No. 98-28, § 2; Ord. No. 2002-17, § 1; Ord. No. 2012-14, § 2; Ord. No. 2016-05, § 1)