Skip to content

DIVISION 17. TOLL FACILITIES AND RELATED MATTERS 30000-31490›CHAPTER 4.3. Metropolitan Transportation Commission 30950-30963

§ 30952.2

California Streets and Highways Code · 2018-11 edition · updated 2026-10-04 · California

(a) The department shall provide monthly reports to the Toll Bridge Program Oversight Committee, including, but not limited to, the construction status, actual expenditures, and forecasted costs and schedules for the Benicia-Martinez Bridge construction project and the state toll bridge seismic retrofit program projects.

(b) (1) Commencing August 15, 2005, and quarterly thereafter until completion of all applicable projects, the Toll Bridge Program Oversight Committee shall provide quarterly reports within 45 days of the end of each quarter to the transportation and fiscal committees of both houses of the Legislature and the California Transportation Commission for the toll bridge seismic retrofit program in subdivision (a) of Section 188.5.

(2) The report shall include details of each toll bridge seismic retrofit project and all information necessary to clearly describe the status of the project, including, but not limited to, all of the following:

(A) A progress report.

(B) The baseline budget for capital and capital outlay support costs for the revised program cost estimate, as described in Section 188.6.

(C) The current or projected budget for capital and capital outlay support costs.

(D) Expenditures to date for capital and capital outlay support costs.

(E) A comparison of the current or projected schedule and the baseline schedule that was assumed.

(F) A summary of milestones achieved during the quarterly period and any issues identified and actions taken to address those issues.

(G) A summary of the expenses incurred by the Toll Bridge Program Oversight Committee to perform the duties required by Sections 30952.05 and 30952.1.

(H) A summary of the incentives, disincentives, and criteria for each utilized by the department, and the expenses incurred by the department, pursuant to Section 30952.3.

(3) The report described in paragraph (1) shall also include a programwide summary of the program’s budget status for capital and capital outlay support costs.

(Added by Stats. 2005, Ch. 375, Sec. 3. Effective September 29, 2005.)

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — California Streets and Highways Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.