TITLE 7. PLANNING AND LAND USE [65000 - 66499.58]›DIVISION 1. PLANNING AND ZONING [65000 - 66345.4]›CHAPTER 4.5. Review and Approval of Development Projects [65920 - 65964.5]›ARTICLE 5. Approval of Development Permits [65950 - 65957.5]›§ 65950
§ 65950.1
Government Code §§ 65920–65964.5 — Permit Streamlining Act · 2026 edition · updated 2026-07-29 · California
65950.1. Notwithstanding Section 65950, if there has been an extension of time pursuant to Section 21100.2 or 21151.5 of the Public Resources Code to complete and certify the environmental impact report, the lead agency shall approve or disapprove the project within 90 days after certification of the environmental impact report.
(Added by Stats. 1983, Ch. 1240, Sec. 1.)
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — Government Code §§ 65920–65964.5 — Permit Streamlining Act
- Government Code §§ 65920–65964.5 — Permit Streamlining Act
-
▸ TITLE 7. PLANNING AND LAND USE [65000 - 66499.58]
Overview-
▸ DIVISION 1. PLANNING AND ZONING [65000 - 66345.4]
Overview-
▸ CHAPTER 4.5. Review and Approval of Development Projects [6592…
Overview- ARTICLE 1. General Provisions [65920 - 65923.8]
- ARTICLE 2. Definitions [65925 - 65934]
- ARTICLE 3. Applications for Development Projects [65940 - 6594…
- ARTICLE 4. Expedited Review [65946 - 65946.1]
- ARTICLE 5.6. Environmental Permits [65959 - 65959.3]
- ARTICLE 6. Development Permits for Classes of Projects [65960 …
-
-