Sec. 10-5.101. Title. ¶
Esta sección aún no está traducida y se muestra en inglés.
This chapter shall be known as the "The Surface Mining Reclamation Ordinance of Yolo County" or “Reclamation Ordinance”. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.102. Authority. ¶
Esta sección aún no está traducida y se muestra en inglés.
This chapter is enacted pursuant to the authority granted by the California Surface Mining and Reclamation Act of 1975, Chapter 9 of Division 2 of the Public Resources Code of the state, commencing with Section 2710; the State Mining and Geology Board Reclamation Regulations, Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, commencing with Section 3500; and pursuant to the powers of the County to protect the public health, safety, and welfare pursuant to Section 7 of Article XI of the Constitution of the State. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.103. Purposes. ¶
Esta sección aún no está traducida y se muestra en inglés.
The purposes of this chapter are as follows:
(a) The reclamation of mined lands is necessary to prevent or minimize the adverse effects of mining on the environment and to protect the public health and safety;
(b) The reclamation of mined lands shall provide for the protection and subsequent beneficial use of mined lands. However, mining takes place in diverse areas, with significantly different geologic, topographic, climatic, biological, and social conditions, so that the methods and operations of reclamation plans may vary accordingly to provide for the most beneficial reclamation of mined lands;
(c) In order to provide for reclamation plans that are specifically adapted to the requirements of particular mined lands; and to ensure that mined land is reclaimed to end uses such as agriculture, habitat, groundwater recharge, flood control, and channel stabilization in a consistent manner to maximize their overall management; this chapter imposes performance standards by which reclamation methods and operations shall be measured;
(d) The continued protection of agriculture and open-space uses is essential. As such, all off-channel, prime agricultural land and/or off-channel lands within a Williamson Act contract at the time that mining commences shall be reclaimed to an agriculturally productive state equal to or greater than that which existed before mining commenced. Prime agricultural land that is not within a Williamson Act contract shall be reclaimed to those uses which are declared by the County to be compatible with agricultural activities. Such uses include, but are not limited to, the following:
(1) Agriculture and range land;
(2) Groundwater storage and recharge areas;
(3) Native fish, wildlife, invertebrate, and plant habitat;
(4) Watercourses and flood control basins; and,
(5) Recreational or open space lands;
(e) Non-prime agricultural land shall be similarly reclaimed to one of the alternate uses described above; and
(f) Reclamation plans shall be designed to integrate with the long-term goals of encouraging agriculture and recreation while protecting habitat and the riparian corridor. Provisions shall be made to continue monitoring and maintenance activities after reclamation is completed, where appropriate, in order to ensure that reclaimed uses remain compatible with and enhance local resource management.
(§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 2.
Definitions
Sec. 10-5.201. Scope. ¶
Esta sección aún no está traducida y se muestra en inglés.
The definitions set forth in section 2725 et seq. of the Act and 3500 et seq. of the Regulations shall apply throughout this chapter. In addition, the definitions set forth in this article shall also govern the interpretation of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.202. Abandon: Abandonment. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Abandon" or "abandonment" shall mean to cease surface mining or reclamation with the intention of not resuming or reclaiming. Operations that have an approved interim management plan shall not be considered abandoned, unless the operator is financially incapable of performing reclamation or has failed to observe an order to comply. However, any surface mining operation that is idle for twelve (12) consecutive months or longer shall be considered abandoned. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.203. Act. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Act" shall mean the Surface Mining and Reclamation Act of 1975, specifically referring to Chapter 9 of Division 2 of the State Public Resources Code, Sections 2710 et seq. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.204. Agency. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Agency" shall mean the County Administrator. (§ 1, Ord. 1191, eff. September 5, 1996, as amended by § 2, Ord. 1407, eff. April 28, 2011; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.205. Board. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Board" shall mean the Board of Supervisors of the County. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.206. CEQA. ¶
Esta sección aún no está traducida y se muestra en inglés.
"CEQA" shall mean the California Environmental Quality Act set forth in Sections 21000 et seq. of Division 13 of the Public Resources Code of California. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.207. Commission. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Commission" shall mean the Planning Commission of the County, or its successor in function. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.208. County. ¶
Esta sección aún no está traducida y se muestra en inglés.
"County" shall mean the County of Yolo. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.209. Department. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Department" shall mean the State Department of Conservation, or its successor in function with regards to surface mining and reclamation regulation. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.210. Director. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Director" shall mean County Administrator, or a designee chosen by Administrator. (§ 1, Ord. 1191, eff. September 5, 1996, (as amended by § 2, Ord. 1407, eff. April 28, 2011; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.211. Financial assurances. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Financial assurances" shall mean monetary funds, securities, or other instruments provided by the operator to ensure that surface mining operations are reclaimed according to the approved reclamation plan, should the operator abandon the mine site. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.212. Haul road. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Haul road" or “route” shall mean: 1) a road along which material is transported from the area of excavation to the processing plant or stock pile area of the surface mining operation; and/or 2) the designated route aggregate trucks are authorized to take pursuant to Section 104.419. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.213. Idle. ¶
Esta sección aún no está traducida y se muestra en inglés.
“Idle” means that an operator of a surface mining operation has curtailed production at the surface mining operation, with the intent to resume the surface mining operation at a future date, for a period of one year or more by more than ninety (90%) percent of its maximum annual mineral production within any of the last five (5) years during which an interim management plan has not been approved. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.214. Interim management plan. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Interim management plan" shall mean an amendment to the approved reclamation plan to provide measures for maintaining an idle mine site until operations are resumed. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.215. Irrevocable letter of credit. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Irrevocable letter of credit" shall mean a form of financial assurance whereby a bank authorized to do business in the State submits a letter granting credit on behalf of the mine operator. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.216. Mined lands. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Mined lands" shall mean the surface, subsurface, and groundwater of an area in which surface mining operations will be, are being, or have been conducted, including private ways and roads appurtenant to any such area, land excavations, workings, mining waste, and areas in which structures, facilities, equipment, machines, tools, or other materials or property which result from, or are used in, surface mining operations are located. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.217. Mining waste. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Mining waste" shall mean the residual of soil, rock, mineral, liquid, vegetation, equipment, machines, tools, or other materials or property directly resulting from, or displaced by, surface mining operations. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.218. Minor modification. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Minor modification" shall mean a change in the approved reclamation plan that does not substantially alter the intent or the conditions of the reclamation plan. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.219. Operator. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Operator" shall mean any person who is engaged in surface mining operations, or who contracts with others to conduct operations on their behalf, except a person who is engaged in surface mining operations as an employee with wages as their sole compensation. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.220. Overburden. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Overburden" shall mean soil, rock, or other materials that lie above a natural mineral deposit or in between mineral deposits, before or after their removal by surface mining operations. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.221. Prime agricultural land. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Prime agricultural land" shall mean all land which meets the definition of prime agricultural land set forth in Section 51201 of the Government Code of the State as administered by the County in the administration of its agricultural preserve program. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.222. Reclamation. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Reclamation" shall mean the combined process of land treatment that minimizes water degradation, air pollution, damage to aquatic or wildlife habitat, flooding, erosion, threats to public health or safety, and other adverse effects
from surface mining operations, including adverse surface effects incidental to underground mines, so that mined lands are reclaimed to a usable condition which is readily adaptable for alternate land uses. The process may extend to affected lands surrounding mined lands, and may require backfilling, grading, resoiling, revegetation, soil compaction, stabilization, or other measures. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.223. Reclamation plan. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Reclamation plan" shall mean the operator's completed and approved plan for reclaiming lands affected by any surface mining operations conducted after January 1, 1976, as required by Section 2772 of the Public Resources Code of the State. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.224. Regulations. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Regulations" shall mean the State Mining and Geology Board Reclamation Regulations, specifically referring to Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.225. Responsible agency. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Responsible agency" shall mean all public agencies other than the County which have discretionary approval power over the project. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.226. Slope. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Slope" shall mean the angle of the groundsurface, expressed as a ratio of the horizontal distance to the vertical distance. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.227. State CEQA guidelines. ¶
Esta sección aún no está traducida y se muestra en inglés.
"State CEQA guidelines" shall mean those regulations set forth in Sections 15000 et seq. of Chapter 3 of Title 14 of the California Code of Regulations. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.228. Surety bond. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Surety bond" shall mean a form of financial assurance whereby an indemnity agreement is executed in a certain amount, either by the mine operator as principal and surety, or by a surety firm authorized to do business in the State. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.229. Surface mining operations. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Surface mining operations" shall mean all, or any part of, the process involved in the mining of minerals on mined lands by removing overburden and mining directly from the mineral deposits, open-pit mining of minerals naturally exposed, mining by the auger method, dredging and quarrying, or surface work incidental to an underground mine. Surface mining operations shall include, but are not limited to: in-place distillation or retorting or leaching; the production and disposal of mining waste; and prospecting and exploratory activities. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.230. Trustee agency. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Trustee agency" shall mean a State agency having jurisdiction by law over natural resources affected by a project which are held in trust for the people of the State. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.231. Trust fund. ¶
Esta sección aún no está traducida y se muestra en inglés.
"Trust fund" shall mean a form of financial assurance, including: cash deposited in a federally insured account; negotiable bonds "held in escrow" by a political subdivision and endorsed by the operator, and rated "A" or better by a nationally recognized bond rating organization; or negotiable certificates of deposit in a federally insured depository. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 3.
Scope and Exemptions
Sec. 10-5.301. Incorporation by reference. ¶
Esta sección aún no está traducida y se muestra en inglés.
The provisions of the Act and the Regulations, as those provisions and regulations may be amended from time to time, are made a part of this chapter by reference with the same force and effect as if the provisions therein were specifically and fully set out herein, excepting that when the provisions of this chapter are more restrictive than corresponding State provisions, this chapter shall prevail. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.302. Scope of regulations. ¶
Esta sección aún no está traducida y se muestra en inglés.
Unless otherwise provided in this article, no person shall conduct surface mining operations within the unincorporated area of the County unless a reclamation plan has been approved and adequate financial assurances have been submitted, in accordance with this chapter. Nothing in this chapter shall be interpreted as requiring the filing of a reclamation plan or financial assurances for, or the reclamation of, mined lands where surface mining operations were completed prior to January 1, 1976.
No reclamation plan application is required if the operator can provide evidence of a reclamation plan for the site approved by the County prior to January 1, 1976, and if the operator has accepted responsibility for reclaiming the mined lands in accordance with the approved reclamation plan. (as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.303. Scope: Area defined. ¶
Esta sección aún no está traducida y se muestra en inglés.
This chapter shall apply only to the area located within the boundaries of the Cache Creek Area Plan of the Yolo County General Plan. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.304. Exemptions: Defined. ¶
Esta sección aún no está traducida y se muestra en inglés.
The provisions of this chapter shall not apply to those activities and operations which are exempted by Sections 2714 and 2776 of the Act. Any exemption granted from the provisions of this chapter shall not, in and of itself, exempt a project or activity from the application of other applicable regulations and requirements. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.305. Exemptions: Applications. ¶
Esta sección aún no está traducida y se muestra en inglés.
Applications for exemptions shall be submitted to the Director for review and determination as to completeness. If the application is determined incomplete, the Director shall notify the applicant in writing within thirty (30) days, specifically describing the information necessary to complete the application. Upon receipt of a completed application, the Director shall determine whether the operation is exempt or is subject to the provisions of this chapter. Any person with standing may appeal the Director's decision to the Commission, pursuant to Article 11 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 4.
Minimum Reclamation Standards: In-Channel Operations.
(Not Used)
Article 5.
Minimum, Reclamation Performance Standards: Off-Channel Operations
Sec. 10-5.501. Reclamation standards: Scope. ¶
Esta sección aún no está traducida y se muestra en inglés.
The general standard for the reclamation of mined lands is to restore the site to a usable condition which is readily adaptable for alternate land uses consistent with the policies of the County expressed in Article 1 of this chapter and in the General Plan, specific plans, and zoning laws.
This article sets forth minimum acceptable practices to be followed in reclamation operations to implement this general standard. These minimum acceptable standards shall be considered and discussed in every reclamation plan approved pursuant to this chapter. In addition, the minimum statewide reclamation practices and standards set forth in the Regulations shall also be considered and discussed in every reclamation plan approved pursuant to this chapter. These standards shall be followed in addition to any other conditions of approval or regulations imposed on the surface mining permit. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.502. Aesthetics. ¶
Esta sección aún no está traducida y se muestra en inglés.
Means of improving the appearance of the landscape after mining has been completed shall be assessed based on site-specific visual characteristics, site lines, and view corridors. The use and placement of berms, vegetative screens, special plant materials, grading. slopes, and contouring the sides and top surfaces of modified landforms to mimic surrounding landforms, or other measures, shall be incorporated into the mine reclamation plan as appropriate. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.503. Backfilled excavations: Groundwater flow impacts. ¶
Esta sección aún no está traducida y se muestra en inglés.
The area of backfilled off-channel excavations extending below the groundwater table shall be minimized in order to reduce changes to groundwater levels and flow. Backfilled pits shall be oriented with regard to the direction of groundwater flow to prevent localized obstructions. If a backfilled off-channel excavation is proposed to penetrate either fifty (50') feet or one-half (½) into the saturated thickness of the shallow aquifer, then at least six (6) months prior to the commencement of excavation below the average high groundwater level, the applicant shall demonstrate in a manner consistent with the Technical Studies that the pit design will not adversely affect active off-site wells
within one thousand (1,000) feet of the proposed pit boundary. If the application includes a series of backfilled pits, then the applicant shall also demonstrate that the cumulative effects of the multiple backfilled pits will not adversely affect groundwater flow, if there are any active off-site wells within one thousand (1,000) feet of the pit boundaries. The applicant shall demonstrate, using MODFLOW (or a similar model of equal capability and proven reliability, as approved by the Director), that the proposed pit design would not adversely impact active off-site wells within one thousand (1,000) feet of the proposed pit boundary or result in well failure.
Average, historic low groundwater levels, which represent the condition of maximum threat to water levels in the subject well, shall be used for this simulation. If an adverse impact is identified by the MODFLOW (or other approved model) simulation, the mining and reclamation plan shall be modified or the applicant shall submit a written agreement that the well owner has agreed to relocate or redesign the well, or accept the potential impact (at no expense to the County).
Site-specific aquifer testing shall be conducted, if needed, to determine aquifer properties for the required modeling. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.504. Backfilled excavations: Improvements. ¶
Esta sección aún no está traducida y se muestra en inglés.
Improvements, including the construction of buildings, roadways, or other public facilities proposed for construction in reclaimed mining pits shall require a geotechnical investigation of the stability of fills conducted by a Licensed Geotechnical Engineer or a Registered Civil Engineer. A report on the results and recommendations of the investigation shall be submitted to the Director prior to the issuance of building permits. The recommendations of the geotechnical investigations shall be fully implemented by the applicant. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.505. Backfilled excavations: Inspections. ¶
Esta sección aún no está traducida y se muestra en inglés.
Backfilled mining areas and slopes shall be inspected by the Director following strong seismic shaking events. Observable damage shall be reported to the landowner. If the Director determines that the damage requires repair to meet the intended use of the reclaimed land, the landowner shall perform the required repairs. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.506. Bank stabilization maintenance. ¶
Esta sección aún no está traducida y se muestra en inglés.
Financial assurances for off-channel mining operations which include mining within seven hundred (700) feet of the active channel of Cache Creek shall include adequate funding for maintenance during the mining and reclamation period of any bank stabilization features approved for the mining permit. Maintenance of the bank stabilization features following the completion of reclamation shall be the responsibility of the property owners under the Cache Creek Resource Management Plan.
The condition of flood protection structures, bank stabilization measures, and the integrity of the land within the approved setback zone separating the mining areas and the creek channel shall be inspected annually by a Registered Civil Engineer and reported to the Director. The annual report shall include recommendations for remedial action for identified erosion problems. Following reclamation, the Director shall inspect the land separating the mining areas and creek channel every five (5) years. Observable damage shall be reported to the property owner. If the Director determines that damage requires repair to meet the intended performance of the separator, the property owner shall perform the required repairs. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.507. Drainage. ¶
Esta sección aún no está traducida y se muestra en inglés.
Upon the completion of operations, grading and revegetation shall minimize erosion and convey storm water runoff from reclaimed mining areas to natural outlets or interior basins. The condition of the land shall allow sufficient drainage to prevent water pockets or undue erosion. Stormwater drainage shall be designed so as to prevent flooding on surrounding properties and County rights-of-way.
Drainage and detention facilities within the proposed mining areas and vicinity shall be designed to prevent discharges to the wet pits and surface water conveyances (i.e., creeks and sloughs) from the twenty (20) year/one-hour storm or less. For events greater than the twenty (20) year/one-hour storm, runoff from around the perimeter of the mining areas shall be directed into surface water conveyances. Runoff from within the lowered mining area shall be directed away from wet pits to detention/infiltration areas. Drainage plans shall not rely solely on ditches and berms to direct runoff away from the wet pit. Without proper maintenance, berms and ditches may deteriorate with time and become ineffective. Drainage plans shall emphasize grading of disturbed areas that results in broad gentle slopes that drain away from the pits. Grading plans shall be reviewed by the County to evaluate compliance with drainage plan objectives prior to project approval.
In addition, a restriction shall be recorded on the deed that requires berms and ditches to be permanently maintained in a condition consistent with the final approval. The deed restriction shall require an inspection easement which allows County staff or other authorized personnel access for the inspection of berms and ditches. If the County determines that evidence of damage to those facilities exists, the County shall require that the owner have an inspection report for the property prepared by a Registered Geologist or Registered Civil Engineer. The inspection report including recommendations for corrective action, if needed, shall be submitted to the Director. The property owner shall be required to implement recommended corrective actions, if any. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.508. Erosion control. ¶
Esta sección aún no está traducida y se muestra en inglés.
The grading of final slopes, the replacement of soil, and associated erosion control measures shall take place prior to November 1 in areas where mining has been completed. To minimize erosion, the finish grading of mining pit slopes above the average seasonal high groundwater level, with the exception of the location of designated haul roads, shall be performed as soon as practical after the mining of overburden and unsaturated aggregate resources has been completed. A drought-tolerant, weed-free mix of native grass species shall be established on slopes prior to November 1 or alternate erosion control (mulch or netting) shall be placed on exposed soil on the slopes prior to this date. Phasing of mining to minimize the length of exposed mining slopes during the rainy season is encouraged. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.509. Fence row habitat. ¶
Esta sección aún no está traducida y se muestra en inglés.
Where fence row or field margin habitat previously existed, reestablish similar habitat as part of reclamation to agricultural use to replace and improve the wildlife habitat value of agricultural lands, allowing for the reestablishment of scattered native trees, shrubs, and ground covers along the margins of reclaimed fields. Reestablished habitat can be located in areas other than where it occurred originally. Restoration plans shall specify ultimate fence row or field margin locations, identify planting densities for trees and shrubs, and include provisions for monitoring and maintenance to ensure establishment. Restoration plans should be reviewed and approved by the TAC. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.510. Fencing. ¶
Esta sección aún no está traducida y se muestra en inglés.
Open wet pits shall be fenced with a forty-two (42") inch minimum, four (4) strand barbed wire fence or the equivalent (e.g., welded square "hog" fencing), prior to the commencement of excavation, during excavation, and during reclamation. Fencing may enclose the property of which mining is a part, the mining site, or both. In addition, signs shall be installed at the project site boundaries and access road, indicating that the excavation area is restricted. Additional security (e.g., gates with protected locks and wing fences to prevent drive-arounds) shall be provided at all vehicular routes. The fencing and gates shall be maintained throughout the mining and reclamation period after completion of reclamation. A requirement shall be recorded on the deed of the property which requires the landowner to maintain fences. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.511. Field drainage. ¶
Esta sección aún no está traducida y se muestra en inglés.
Reclaimed agricultural surfaces shall be graded to provide adequate field gradients to allow surface/furrow irrigation of crops and allow for adequate storm water drainage. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.512. Field releveling. ¶
Esta sección aún no está traducida y se muestra en inglés.
The operator shall retain a Licensed Land Surveyor or Registered Civil Engineer to resurvey any areas reclaimed to agricultural usage after the first two (2) crop seasons have been completed. Any areas where settling has occurred shall be releveled to the field grade specified in the approved reclamation plan. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.513. Floodplain development. ¶
Esta sección aún no está traducida y se muestra en inglés.
New development proposed within the reclamation plan (such as buildings, levees, or dikes) located within the floodplain shall conform to all applicable requirements of the Yolo County Flood Protection Ordinance, and the Federal Emergency Management Agency (FEMA). (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.514. Habitat conservation plan compliance. ¶
Esta sección aún no está traducida y se muestra en inglés.
All reclamation plans shall be consistent with applicable components of the Yolo Habitat Conservation Plan/Natural Community Conservation Plan (HCP/NCCP). (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.515. Habitat plan referral. ¶
Esta sección aún no está traducida y se muestra en inglés.
Proposed habitat restoration or mitigation plans for lands within the OCMP area shall be sent to the California Department of Fish and Wildlife, U.S. Fish and Wildlife Service, the U.S. Army Corps of Engineers, and other interested parties for review and comment through the CEQA process as applicable, to ensure that the projects do not conflict with other existing habitat enhancement efforts. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.516. Lowered elevations for reclaimed agricultural fields. ¶
Esta sección aún no está traducida y se muestra en inglés.
The final distance between lowered surfaces reclaimed to agriculture and the average high groundwater shall not be less than five (5') feet. The average high groundwater level shall be established for each proposed mining area. The degree of groundwater level fluctuation varies with location throughout the basin and within relatively small areas (proposed mining sites). The determination of the average high groundwater level shall be conducted by a Registered Civil Engineer or Certified Hydrogeologist and shall be based on wet season water level elevation data collected at the proposed site or adjacent areas with similar hydrogeological conditions. Water level records prior to 1977 shall not be used since they would reflect conditions prior to the installation of the Indian Valley Dam. The dam caused a significant change in hydrology of the basin and data collected before its installation shall not be used in estimating current average high groundwater levels. The wells shall be adequately distributed throughout the proposed mining site to reflect spatial variation in groundwater levels and fluctuations. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.517. Mercury bioaccumulation in fish. ¶
Esta sección aún no está traducida y se muestra en inglés.
As part of each approved long-term mining plan involving wet pit mining to be reclaimed to a permanent pond, lake, or water feature, the operator shall maintain, monitor, and report to the Director according to the standards given in this section. Requirements and restrictions are distinguished by phase of operation as described below.
(a) Mercury Protocols. The Director shall issue and update as needed “Lower Cache Creek Off-Channel Pits Mercury Monitoring Protocols” (Protocols), which shall provide detailed requirements for mercury monitoring activities. The Protocols shall include procedures for monitoring conditions in each pit lake, and for monitoring ambient mercury level in the lower Cache Creek channel within the CCAP planning area, as described below. The Protocols shall be developed and implemented by a qualified aquatic scientist or equivalent professional acceptable to the Director. The protocols shall identify minimum laboratory analytical reporting limits, which may not exceed the applicable response threshold identified in subsection (e) below. Data produced from implementing the Protocols shall meet or exceed applicable standards in the industry.
(b) Ambient Mercury Level. The determination of the ambient or “baseline” fish mercury level shall be undertaken by the County every ten (10) years in years ending in 0. This analysis shall be undertaken by the County for use as a baseline of comparison for fish mercury testing conducted in individual wet mining pits. The work to establish this baseline every ten (10) years shall be conducted by a qualified aquatic systems scientist acceptable to the Director and provided in the form of a report to the Director. It shall be paid for by the mining permit operators on a fairshare basis. The results of monitoring and evaluation of available data shall be provided in the report to substantiate the conclusions regarding ambient concentrations of mercury in fish within the lower Cache Creek channel within the CCAP planning area.
(c) Pit Monitoring.
(1) Mining Phase (including during idle periods as defined in SMARA). The operator shall monitor fish and water column profiles in each pit lake once every year during the period generally between September and November for the first five (5) years after a pit lake is created. Fish monitoring should include sport fish where possible, together with other representative species that have comparison samples from the creek and/or other monitored ponds. Sport fish are defined as predatory, trophic level four fish such as bass, which are likely to be primary angling targets and have the highest relative mercury levels. The requirements of this subsection apply to any pit lake that is permanently wet and navigable by a monitoring vessel. If, in the initial five (5) years after the pit lake is created, the applicable response threshold identified in subsection (e) is exceeded in any three (3) of five (5) monitoring years, the operator shall, solely at their own expense, undertake expanded analysis pursuant to subsection (f) and preparation of a lake management plan pursuant to subsection (g).
(2) Reclamation Phase. No monitoring is required after mining has concluded, during the period that an approved reclamation plan is being implemented, provided reclamation is completed within the time specified by SMARA or the project approval, whichever is sooner.
(3) Post-Reclamation Phase. After reclamation is completed, the operator shall monitor fish and water column profiles in each pit lake at least once every two (2) years during the period of September-November for ten (10) years following reclamation. Monitoring shall commence in the first calendar year following completion of reclamation activities. If fish monitoring results from the post-reclamation period exceed the applicable response threshold described in subsection (e) or, for ponds that have implemented mitigation management, results do not exhibit a general decline in mercury levels, the operator shall, solely at their own expense, undertake expanded analysis pursuant to subsection (f) and preparation of a lake management plan pursuant to subsection (g).
(4) Other Monitoring Obligation. If monitoring conducted during both the mining and post- reclamation phase did not identify any exceedances of the ambient mercury level for a particular pit lake, and at the sole discretion of the Director no other relevant factors substantially support that continued monitoring is merited, the operator shall have no further obligations.
(d) Reporting.
(1) Pit Monitoring Results. Reporting and evaluating of subsection (c) pit monitoring results shall be conducted by a qualified aquatic scientist or equivalent professional acceptable to the Director. Monitoring activities and results shall be summarized in a single report (addressing all wet pit lakes) and submitted to the Director within six (6) months following each annual monitoring event. The report shall include, at a minimum: (1) results from subsection (b) (pit monitoring), in relation to subsection (a) (ambient mercury levels).
st or equivalent professional acceptable to the Director. Monitoring activities and results shall be summarized in a single report (addressing all wet pit lakes) and submitted to the Director within six (6) months following each annual monitoring event. The report shall include, at a minimum: (1) results from subsection (b) (pit monitoring), in relation to subsection (a) (ambient mercury levels).
(2) Expanded Analysis Results. Reporting and evaluation of subsection (f) expanded analysis shall be conducted by a qualified aquatic scientist or equivalent professional acceptable to the Director. Results shall be summarized in a single report (addressing all affected wet pit lakes) and submitted to the Director within six (6) months following each annual monitoring event. The report shall include, at a minimum, the results of the expanded analysis undertaken pursuant subsection (f).
(3) Data Sharing. For pit lakes open to the public, the Director may submit the data on mercury concentrations in pit lake fish to the state Office of Environmental Health Hazard Assessment (or its successor) for developing sitespecific fish consumption advisories.
(e) Response Thresholds.
(1) Fish Consumption Advisory. If at any time during any phase of monitoring the pit lake’s average sport fish tissue mercury concentration exceeds the Sport Fish Water Quality Objective, as it may be modified by the state over time (as of 2019, the level was 0.2 mg/kg), the operator shall post fish consumption advisory signs at access points around the lake and around the lake perimeter. Catch-and-release fishing may still be allowed. Unless site-specific guidance has been developed by the state’s Office of Health Hazard Assessment or the County, statewide fish consumption guidance shall be provided.
(2) Mining Phase Results. If, during the mining phase of monitoring, the pit lake’s average fish tissue mercury concentration exceeds the ambient mercury level for any three (3) of five (5) monitoring years, annual monitoring shall continue for an additional five (5) years, and the operator shall undertake expanded analysis pursuant to subsection (f) and preparation of a lake management plan pursuant to subsection (g).
(3) Post-Reclamation Phase Results. If during the first ten (10) years of the post-reclamation phase of monitoring, the pit lake’s average fish tissue mercury concentration exceeds the ambient mercury level for any three (3) of five (5) monitoring years, biennial monitoring shall continue for an additional ten (10) years, and the operator shall undertake expanded analysis pursuant to subsection (f) and preparation of a lake management plan pursuant to subsection(g). (f) Expanded Analysis.
hase of monitoring, the pit lake’s average fish tissue mercury concentration exceeds the ambient mercury level for any three (3) of five (5) monitoring years, biennial monitoring shall continue for an additional ten (10) years, and the operator shall undertake expanded analysis pursuant to subsection (f) and preparation of a lake management plan pursuant to subsection(g). (f) Expanded Analysis.
(1) General. If during the mining or post-reclamation phase, any pit lake’s average fish tissue mercury concentration exceeds the ambient mercury level for any three (3) years, the operator shall undertake expanded analyses. The analysis shall include expanded lake water column profiling (a minimum of five (5) profiles per affected wet pit lake plus one or more nonaffected lakes for control purposes) conducted during the warm season (generally May through October) in an appropriate deep profiling location for each pit lake. The following water quality parameters shall be collected at regular depth intervals, from surface to bottom of each lake, following protocols identified in subsection (a): temperature, dissolved oxygen, conductivity, pH and oxidation-reduction potential (ORP), turbidity or total suspended solids, dissolved organic matter, and algal density by Chlorophyll or Phycocyanin. The initial analysis shall also include one-time collections of fine grained (clay/silt) bottom sediments from a minimum of six (6) well distributed locations for each affected lake, and from one or more nonaffected lakes for control purposes, to be analyzed for mercury and organic content.
(2) Scope of Analysis. The purpose of the expanded analyses is to identify and assess potential factors linked to elevated methylmercury production and/or bioaccumulation in each pit lake. The scope of the expanded analyses shall include monitoring and analysis appropriate to fulfill this purpose, invoking best practices in the industry. In addition to the analyses described in subsection (f)(1) above, the analysis should also consider such factors as: electrical conductivity, bathymetry (maximum and average depths, depth-to-surface area ratios, etc.), and trophic status indicators (concentrations, Secchi depth, chlorophyll a, fish assemblages, etc.). Additional types of testing may be indicated and appropriate if initial results are inconclusive.
(3) Use of Results. The results of the expanded analyses undertaken pursuant to this subsection shall be used to inform the preparation of a lake management plan described below under subsection (g).
(g) Lake Management Activities.
(1) General. If monitoring conducted during the mining or post-reclamation phases triggers the requirement to undertake expanded analysis and prepare and implement a lake management plan, the operator shall implement lake management activities designed by a qualified aquatic scientist or equivalent professional acceptable to the Director, informed by the results of subsection (f). Options for addressing elevated mercury levels may include (A) and/or (B) below at the Director’s sole discretion and at the operator’s sole expense.
sis and prepare and implement a lake management plan, the operator shall implement lake management activities designed by a qualified aquatic scientist or equivalent professional acceptable to the Director, informed by the results of subsection (f). Options for addressing elevated mercury levels may include (A) and/or (B) below at the Director’s sole discretion and at the operator’s sole expense.
(A) Lake Management Plan. Prepare a lake management plan that provides a feasible, adaptive management approach to reducing fish tissue mercury concentrations to at or below the ambient mercury level. Potential mercury control methods could include, for example: addition of oxygen to or physical mixing of anoxic bottom waters; alteration of water chemistry (modify pH or organic carbon concentration); and/or removal or replacement of affected fish populations. The lake management plan may be subject to external peer review at the discretion of the Director. Lake management activities shall be appropriate to the phase of the operation (e.g., during mining or postreclamation). The Lake Management Plan shall include a recommendation for continued monitoring and reporting. All costs associated with preparation and implementation of the lake management plan shall be solely those of the operator. Upon acceptance by the Director, the operator shall immediately implement the plan. The lake management plan shall generally be implemented within three (3) years of reported results from the expanded analyses resulting from subsection (f). If lake management does not achieve acceptable results and/or demonstrate declining mercury levels after a maximum of three (3) years of implementation, at the sole discretion of the Director, the operator may prepare an alternate management plan with reasonable likelihood of mitigating the conditions.
(B) Revised Reclamation Plan. As an alternative to (A), or if (A) does not achieve acceptable results and/or demonstrate declining mercury levels after a maximum of three (3) years of implementation, at the sole discretion of the Director, the operator shall prepare and submit revisions to the reclamation plan (including appropriate applications and information for permit amendment) to fill the pit lake with suitable fill material to a level no less than five (5) feet above the average seasonal high groundwater level, and modify the end use to agriculture, habitat, or open
space at the discretion of the Director, subject to Article 6 of the Mining Ordinance and/or Article 8 of the Reclamation Ordinance as may be applicable.
(2) Implementation Obligations.
(A) If a lake management plan is triggered during the mining or post- reclamation phase and the subsequent lake management activities do not achieve acceptable results and/or demonstrate declining mercury levels, the operator may propose different or additional measures for consideration by the Director and implementation by the operator, or the Director may direct the operator to proceed to modify the reclamation plan as described in subsection (g)(1)(B). (B) Notwithstanding the results of monitoring and/or lake management activities during the mining phase, the operator shall, during the post-reclamation phase, conduct the required ten (10) years of biennial monitoring.
(C) If monitoring conducted during the post-reclamation phase identifies three (3) monitoring years of mercury concentrations exceeding the ambient mercury level, the operator shall implement expanded analyses as in subsection (f), to help prepare and implement a lake management plan and associated monitoring.
(D) If subsequent monitoring after implementation of lake management activities, during the post-reclamation phase, demonstrates levels of fish tissue mercury at or below the ambient mercury level for any three (3) monitoring years (i.e., the management plan is effective), the operator shall be obligated to continue implementation of the plan and continue monitoring, or provide adequate funding for the County to do both, in perpetuity. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.518. Mining in reclaimed lands. ¶
Esta sección aún no está traducida y se muestra en inglés.
Once the reclamation plan or any portion thereof has been completed, no further surface mining operations shall be allowed within reclaimed lands, without approval of an amendment to the surface mining permit and reclamation plan. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.519. Motorized watercraft prohibition. ¶
Esta sección aún no está traducida y se muestra en inglés.
The use of motorized watercraft on any pond, lake or other body of water created as a part of the approved reclamation plan is prohibited. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.520. Operational areas. ¶
Esta sección aún no está traducida y se muestra en inglés.
Operational areas and haul roads that are not required for future use of the site shall be ripped, resoiled, and prepared accordingly, to allow for replanting. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.520.1. Parkway Plan consistency. ¶
Esta sección aún no está traducida y se muestra en inglés.
Reclamation plans shall be developed to be consistent with, avoid conflict with, and further the goals of the Cache Creek Parkway Plan. (Ord. 1518, eff. February 13, 2020)
Sec. 10-5.520.2. Permanent easements. ¶
Esta sección aún no está traducida y se muestra en inglés.
Upon completion of reclamation within each phase of the project, for land that will not be dedicated or deeded to the County, the operator shall enroll each parcel reclaimed to agriculture in Williamson Act contract, or other equivalent long-term easement or deed restriction satisfactory to the County, for the purpose of protecting the agricultural use of the reclaimed land in perpetuity. (Ord. 1518, eff. February 13, 2020)
Sec. 10-5.521. Permanent stockpiles. ¶
Esta sección aún no está traducida y se muestra en inglés.
There shall be no permanent piles of mine waste and/or overburden. Berms established for visual screening and noise abatement shall be contoured to conform visually with the surrounding topography. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.522. Phasing plans. ¶
Esta sección aún no está traducida y se muestra en inglés.
All proposed mining and reclamation plans shall present a phasing plan for mining and reclamation activities. The phasing plan shall be structured to minimize the area of disturbed agricultural lands during each mining phase, and encourage the early completion of the reclamation of agricultural land. (§ 1, Ord. 1191, eff. September 5,1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.523. Planting plans. ¶
Esta sección aún no está traducida y se muestra en inglés.
Site-specific planting plans shall be developed by a qualified biologist for proposed habitat reclamation projects. Restoration components of reclamation plans shall include provisions to enhance habitat for special-status species, where feasible.
Native-planted hedgerows and other vegetated buffers shall be included between restored habitat areas and adjoining farmland, in order to minimize the potential for riparian areas to serve as harbors for predators and insect pests. These buffers will also reduce the noise, dust, and spraying generated by agricultural operations, in addition to providing valuable pollinator resources that in turn could enhance agricultural production. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.524. Post-reclamation groundwater monitoring. ¶
Esta sección aún no está traducida y se muestra en inglés.
Monitoring during the mining and reclamation period shall be a condition of the permit. The applicant shall ensure that the groundwater monitoring of wet-pit mining continues for (10) years after the completion of reclamation. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.525. Farmland conversion. ¶
Esta sección aún no está traducida y se muestra en inglés.
All mining permit applications shall identify the location and acreage of prime farmlands, unique farmland, and farmland of statewide significance, as shown on the State Farmland Mapping and Monitoring Program (FMMP) which, as a result of reclamation, would be permanently converted to non- agricultural uses. For each acre of farmland in these categories that would be converted to non-agricultural use, the reclamation plan shall present provisions to offset the conversion of these lands, at a ratio consistent with Section 8-2.404 (Agricultural Conservation and Mitigation Program) of the County Code. This mitigation requirement may be satisfied using a variety of flexible options identified below so long as the total acreage of benefit is found to be equivalent to the applicable ratio and acreage required under Section 8-2.404 of the County Code, by type and amount of farmland being impacted, and so long as a minimum ratio of 1:1 of permanently protected agriculture land of equivalent or better quality/capability is achieved.
(a) Implementation of improvements, identified by a qualified soil scientist, to the agricultural capability of nonprime lands within the project site or outside the project site but within the OCMP area, that convert non-prime to prime agricultural conditions. These improvements can include permanent improvement of soil capability through soil amendments, reduction of soil limitations (such as excessive levels of toxins), or improvements in drainage for areas limited by flooding or low permeability soils.
(b) Placement of permanent conservation easements on land of equal or better quality/capability. The operator shall be encouraged to target property "at risk" of conversion to non-agricultural uses in selecting areas for permanent protection. Prior to approval of the conservation easement, the operator shall consult with the County and/or an appropriate non-profit agency to determine the relative risk of conversion, to which the proposed property might otherwise be subject. A minimum ratio of 1:1 is required in this category.
(c) Dedication of land, funding, or equivalent improvements, consistent with the County’s net gains goals, above and beyond the net gains benefits otherwise required under the CCAP program.
(d) Dedication of land, funding, or equivalent improvements, consistent with the Parkway Plan, above and beyond net gains benefits otherwise required under the CCAP program. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.526. Repair of damage due to natural disaster. ¶
Esta sección aún no está traducida y se muestra en inglés.
The cost of implementing recommendations for repair of reclaimed land caused during earthquakes or other natural events shall be met through application of contingency costs provided for by the project's financial assurances as required by SMARA. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.527. Recreational and habitat uses of permanent wet pits. ¶
Esta sección aún no está traducida y se muestra en inglés.
If any permanent wet pit is proposed to be reclaimed for recreational uses and/or riparian habitat, the design shall account for fluctuations in the groundwater table. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.528. Sewage storage prohibition. ¶
Esta sección aún no está traducida y se muestra en inglés.
The use of off-channel wet pits for the storage and treatment of sewage effluent, or for landfill purposes, is prohibited. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.529. Shallow depths. ¶
Esta sección aún no está traducida y se muestra en inglés.
All permanent wet pits shall be reclaimed to include valuable wildlife habitat as a beneficial use of the water lost from wet pits due to evaporation. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.530. Slopes. ¶
Esta sección aún no está traducida y se muestra en inglés.
All final reclaimed slopes shall have a minimum safety factor equal to or greater than the critical gradient as determined by an engineering analysis of the slope stability. Final slopes less than five (5') feet below the average summer low groundwater level shall be designed in accordance with the reclaimed use and shall not be steeper than 2:1 (horizontal:vertical). Reclaimed wet pit slopes located five (5') feet or more below the average summer low groundwater level shall not be steeper than 1:1 (horizontal:vertical), in order to minimize the effects of sedimentation and biological clogging on groundwater flow, to prevent stagnation, and to protect the public health.
The maximum slope angle for all final reclaimed slopes shall be determined by slope stability analysis performed by a Licensed Geotechnical Engineer or Registered Civil Engineer and submitted with any mining and reclamation application for review by the Director. The slope stability analysis shall conform with industry standard methodologies regarding rotational slope failures under static and pseudostatic (seismic) conditions. The minimum factor of safety for
all design reclamation slopes located adjacent to levees or below existing structures shall not be less than 1.5 for static and 1.1 for pseudostatic (seismic) conditions. Other reclamation slopes shall meet a minimum factor of safety that is consistent with the post-reclamation use proposed for the mining area. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.531. Soil ripping. ¶
Esta sección aún no está traducida y se muestra en inglés.
Where areas are to be reclaimed to agricultural usage, all A and B horizon soil shall be ripped to a depth of three (3') feet after every two (2') foot layer of soil is laid down, in order to minimize compaction. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.532. Use of overburden and fine sediments in reclamation. ¶
Esta sección aún no está traducida y se muestra en inglés.
Sediment fines associated with processed in-channel aggregate deposits (excavated as a result of maintenance activities performed in compliance with the CCIP) may be used in the backfill or reclamation of off-channel permanent lakes, for in-channel reshaping or habitat restoration, and/or as a soil amendment in agricultural fields provided the operator can demonstrate that no detrimental sediment toxicity exists (consistent with the state’s Stream Pollution Trends Monitoring Program protocols) and fine-grained soil (<63 micron) do not exceed 0.4 mg/kg total mercury.
The operator shall use overburden and processing fines whenever possible to support reclamation activities for pit lakes. If topsoil (A-horizon soil), formerly in agricultural production, is proposed for use within a pit lake or its drainage area, the operator must sample the soils prior to placement and analyze them for pesticides and herbicides (EPA Methods 8141B and 8151A, or equivalent) as well as for total mercury (EPA Method 7471B, or equivalent). The operator shall collect and analyze samples in accordance with EPA Test Methods for Evaluating Solid Waste Physical/Chemical Methods, SW-846 (as updated). Topsoil that contains pesticides or herbicides above the Maximum Contaminant Levels for primary drinking water (California Code of Regulations), or that contains fine-grained soils exceeding on average 0.4 mg/kg total mercury shall not be placed in areas that drain to the pit lakes.
Land reclaimed to a subsequent use that includes planting of vegetation (e.g., agriculture, habitat) shall be provided an adequate soil profile (i.e., depth and texture of soil) to ensure successful reclamation. At the discretion of the Director and at the operator’s sole expense, the proposed reclamation plan for the project may be peer reviewed by an appropriate expert/professional, and recommendations, if any, shall be incorporated into the project as conditions of approval. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.533. Wetland habitat. ¶
Esta sección aún no está traducida y se muestra en inglés.
Off-channel excavations that are proposed to be reclaimed to permanent lakes shall include riparian and/or wetland habitat. The creation of riparian and/or wetland habitat along the perimeter of permanent lakes shall include appropriate features such as: scalloped basin perimeters with extended peninsulas, islands, and stepped benches of various widths at approximately three (3') foot vertical intervals both above and below the groundwater level. Where wetlands are not proposed, either grassland and/or woodland habitat, or agricultural fields separated from the lake by a berm, shall be established using only native species in order to provide continuous habitat value around the permanent lakes. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.534. Exceptions. ¶
Esta sección aún no está traducida y se muestra en inglés.
Where an operator demonstrates to the lead agency that an exception to the standards specified in this article is necessary, the Commission may approve an alternative standard for inclusion in the approved reclamation plan.
Exceptions shall only be approved where the strict application of the off-channel reclamation standards would deprive the operator of privileges enjoyed by other mining operators in the vicinity, due to special circumstances associated with the subject site, including size, shape, topography, location, or surroundings. Although the Commission may set alternative standards, in no case may the Commission set any standard which does not meet or exceed the policy objectives set forth in the OCMP. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 6.
Reclamation Plan Approval Process
Sec. 10-5.601. Applications: Contents. ¶
Esta sección aún no está traducida y se muestra en inglés.
Except as provided for in Section 10-5.602 of this article, all documentation for the reclamation plan shall be submitted to the Director at one time. Ten (10) complete hard copies of the application, and one electronic version, shall be provided to the County. An executive summary and a table of contents for the reclamation plan shall be submitted with each application. Applications for proposed reclamation plan shall include, but shall not be limited to, the following:
(a) A narrative description of the proposed use of mined lands after reclamation has been completed and the manner in which reclamation will be accomplished, including the following information:
(1) The consistency of the proposed reclaimed use with this chapter, the General Plan, zoning, and applicable specific plans;
(2) The manner by which contamination will be controlled in the reclaimed use;
(3) The manner in which affected streambed channels and streambanks will be rehabilitated to a condition minimizing erosion;
(4) The effect that proposed reclamation will have on future mining, both on-site and in the surrounding area; (5) A time schedule of reclamation activities, showing the beginning date, completion dates for each proposed phase, and the final completion date, supported by a statement indicating that reclamation will be initiated at the earliest possible time on those portions of the site that will not be subject to further disturbance by mining;
(6) Separate sections demonstrating compliance of the proposal with each minimum performance standard set forth in the Regulations and Article 5 of this chapter;
(7) A signed statement that the person submitting the application accepts responsibility for implementing the approved reclamation plan;
(8) The acreages of proposed reclaimed uses, such as agriculture, wetlands, groundwater recharge, etc.;
(9) The methods to be used for on-site and off-site surface water drainage and erosion control after reclamation has been completed, including provisions for ensuring flood protection of the site for the 100-year event;
(10) A discussion of the maximum amount of mined lands to be disturbed at any one time;
(11) A description of whether any portion of the project site is currently under a Land Conservation Contract
(Williamson Act) and/or Agricultural Preserve, including any lands for which a Notice of Nonrenewal has been filed and the date of expiration. Proposed mined lands that meet the definition of "prime farmlands" as defined under the Williamson Act shall also be identified;
(b) A narrative description of the type of surface mining proposed to be employed, including the following information:
(1) The name and address of the proposed surface mine operator and the names and addresses of any persons designated by the operator to act as an agent for the applicant through the permit process;
(2) The anticipated quantity and type of minerals for which the proposed surface mining operation will be conducted, including the estimated maximum annual production with calculations presented in both tons mined and in tons sold;
(3) The proposed dates for the initiation and termination of the proposed surface mining operation;
(4) The maximum anticipated depth of the proposed surface mining operation;
(5) Evidence that all owners of a possessory interest in the lands included in the application have given authority to the applicant to conduct surface mining as proposed and to implement the reclamation plan as proposed;
(6) The acreage of the lands that will be affected by the surface mining operations (separately identifying buffer and setback areas), as well as acreages and legal descriptions of the original parcels;
(7) A description of the general geology of the region, including a detailed description of the geology of the area in which surface mining is to be conducted;
(8) The names and addresses of the owners of all surface interests and mineral interest in the lands to be mined;
(c) Site-specific technical studies, performed by qualified professionals in the appropriate area of expertise, shall provide specific proposals for inclusion in the reclamation plan to address the following potential environmental impacts:
(1) A biological analysis to evaluate the feasibility of proposed revegetation efforts, including detailed plans describing planting methods, appropriate planting times, species to be used, irrigation requirements, erosion control, weed control, and proposed success rates for plant cover and density. The analysis shall also include cross-sections for those areas proposed to be revegetated, including slopes, visual screens, and wildlife habitat. Plant materials should be collected in the vicinity of the project site in order to control the origin of the genetic stock and provide the most siteadapted ecotypes. Native seeds, plants and cuttings used for reclamation and restoration activities shall be ecotypes of Cache Creek Watershed genetic origin including areas outside of Yolo County and of Yolo County genetic origin when materials are used that originate from outside of the Cache Creek Watershed.
(2) If the proposed reclamation plan includes agriculture as an end use, then a soil analysis shaft be submitted to evaluate the methods and feasibility of restoring those portions of the mined site to agricultural productivity, including discussions of current and reclaimed soil conditions and classifications, the types of crops grown on the lands proposed for reclamation and their historic yields for a minimum of five (5) years, and projected production of reclaimed agricultural lands. The analysis shall also include detailed plans for the removal and replacement of topsoil and overburden, including cross-sections of the areas to be reclaimed to agriculture, the depth of soils replaced, field irrigation slope grades, detention basins, and the relationship between finished field elevations and the groundwater level for the site; and
ed production of reclaimed agricultural lands. The analysis shall also include detailed plans for the removal and replacement of topsoil and overburden, including cross-sections of the areas to be reclaimed to agriculture, the depth of soils replaced, field irrigation slope grades, detention basins, and the relationship between finished field elevations and the groundwater level for the site; and
(3) A geotechnical study to evaluate the proposed final slopes to ensure that they will be stable once mining has been completed and that the slopes possess an adequate factor of safety. Measures shall be included within the study to ensure slope stability and maintenance.
(d) A site plan submitted in the form prescribed by the Planning Director, including all property proposed to be included in the reclamation plan, drawn to a scale of one inch equals one-hundred feet (1" = 100'), or other scale acceptable to the Director for larger holdings. Small-scale, reproducible copies shall be provided along with all site plans submitted. Site plans shall show the following information:
(1) All property lines, including the boundaries of all parcels proposed for mining and reclamation; the boundaries of any ownerships, leases, and/or other entitlements vested in the surface mining operator which allow surface mining and reclamation to be conducted on-site; and all Assessor parcel numbers for properties included in the application;
(2) The location of all streams, roads, railroads, and utility facilities within, or adjacent to, the lands to be reclaimed;
(3) The location and condition of any previously mined areas within the site, specifically designating those portions of the site, if any, where mining was completed prior to January 1, 1976, and which is claimed to be exempt from the requirements of this chapter;
(4) The existing and proposed topography of all reclaimed lands, including the location of the control crosssections submitted pursuant to subsection (e) of this section;
(5) The location of all development proposed as a part of the reclaimed end use, including settling basins, drainage conveyances, equipment, fences, and other man-made structures;
(6) The depiction of separate reclamation phases;
(7) The locations for the permanent storage of overburden and waste material in any proposed berms;
(8) The proposed points of ingress and egress, access roads, driveways, and parking areas proposed as a part of the reclaimed end use; and
(9) The extent of any borrow areas, where topsoil and overburden material are excavated to be used in the reclamation of mined lands.
(e) Graphic depictions of control cross-sections located as follows and including the following information:
(1) At least three (3) control cross-sections within the area to be reclaimed, with two (2) of the cross-sections perpendicular to one another;
(2) In no event may the interval between the control cross-sections exceed twelve hundred (1200) feet; and
(3) The cross-sections shall identify both the existing and proposed reclaimed elevations, and shall identify the angle of reclaimed slopes.
(f) All maps, diagrams, or calculations that require preparation in accordance with the Professional Engineers Act (Chapter 7 (commencing with Section 6700) of Division 3 of the Business and Professions Code), the Geologist and Geophysicist Act (Chapter 12.5 (commencing with Section 7800) of Division 3 of the Business and Professions Code), or the Professional Land Surveyors’ Act (Chapter 15 (commencing with Section 8700) of Division 3 of the Business and Professions Code) shall be prepared by a California-licensed professional, shall include his or her license number and name, and shall bear the signature and seal of the licensee;
- (g) An estimate of the financial assurances necessary to implement the proposed reclamation plan, or phases thereof, prepared in accordance with Article 7 of this title and including the following information:
(1) An estimate of the equipment usage and manhours necessary to complete reclamation. Estimates for equipment usage shall be substantiated (e.g. the Caterpillar Performance Handbook or similar reference document) and labor requirements explained;
(2) An estimate of indirect costs, such as supervision, contingency, mobilization, profit, and overhead;
(3) The acreages of each type of area proposed in the reclamation plan (e.g., agriculture, slopes, roads, habitat, etc.), referenced to a site plan; and,
(4) An estimate of the amounts of soil, subsoil, wash sediments, and overburden to be used in reclamation, including the average distance from the soil stockpiles to the areas being reclaimed.
(h) A Land Survey or Record of Survey for all parcels included in the application which has a basis of bearing in the California Coordinate System (NAD 27 or NAD 83);
- (i) An initial environmental assessment describing the potential impacts of approving the proposed reclamation plan; and,
(j) A list of all other applicable discretionary permits required by other public agencies.
In addition to the foregoing, the Director may require such other and further information relevant to the project as needed to determine whether the proposal may affect the public health and safety.
- (k) A chart identifying the page number, chapter, appendix, or other specific location in the reclamation plan application where content meeting the requirements, as applicable, of Sections 2772, 2773, and 2773.3 and Article 1
(commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, is located. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.602. Applications: Waiver of information. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Director may temporarily waive any of the items of information required in Section 10-5.601 of this article, if the following conditions apply:
(a) The gathering of such information is precluded by physical conditions existing on the site on the date of the application; and
(b) The operator has provided a statement describing the reasons for the delay, including the date by which the information required in the application will be submitted. If granted, the Director shall notify the operator in writing, specifically describing the information which is being waived and specifying the date by which the operator shall provide the necessary information. If all other information required pursuant to this chapter has been submitted and the appropriate fees have been paid, then the Director shall receive the application for filing. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.603. Applications: Confidentiality. ¶
Esta sección aún no está traducida y se muestra en inglés.
Any information in the reclamation plan application which is considered by the applicant to be confidential, as provided in Article 9 of Chapter 4 of this title, shall be submitted under separate cover and shall be so marked by the Director. The proposed confidential information shall be accompanied by a statement citing the legal authority supporting the applicant's claim of confidentiality. The request for confidentiality shall be reviewed by the Director and either approved or denied.
The decision of the Director to reject or accept the claim of confidentiality shall be mailed and posted in accordance with Section 10-5.607 of this chapter. Any request for confidentiality approved by the Director shall become final within fifteen (15) days, unless appealed to the Commission, as provided in Article 11 of this chapter. The appellate hearing shall be conducted such that the information remains confidential until a decision is reached.
If the request is approved, then the confidential information shall be filed under separate cover. The contents of the confidential file shall be made available only to the Director and those persons authorized in writing by the operator and by the property owner. If the request is denied, the applicant may withdraw the information and include it with the application as a public document. Failure to submit any necessary information may result in an incomplete application. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.604. Applications: Filing. ¶
Esta sección aún no está traducida y se muestra en inglés.
Applications for reclamation plans shall be submitted to the Director for review and determination as to completeness. If the application is determined to be incomplete, the Director shall notify the applicant in writing within thirty (30) days of receipt of the application. The written notice shall specifically describe the information necessary to complete the application. The application shall not be processed until the Director has determined it to be complete and the appropriate fees have been paid, as required under Article 10 of this chapter.
Once the application has been determined to be complete and the appropriate fees have been paid, the application shall be processed by the Director, who shall set it for a hearing pursuant to Section 10-5.606 of this article. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.605. Applications: Review. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Director shall notify the Department in writing of any application for a reclamation plan within thirty (30) days of its being filed. The application shall also be circulated to all other agencies of jurisdiction for their review and comments in accordance with CEQA, or other applicable regulatory requirements. In addition, a notice of the filing of a reclamation plan shall be mailed to any other person with an interest in the application, who has deposited a selfaddressed, stamped envelope with the Agency for the purpose of receiving a notice of the filing. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.606. Applications: Public hearing. ¶
Esta sección aún no está traducida y se muestra en inglés.
Once the application has been processed, the Director shall set a public hearing before the Commission to consider the proposed reclamation plan. Said hearing shall be held within six (6) months after the completion of the final EIR or within three (3) months after the completion of the negative declaration. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.607. Public hearing: Notice. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Director shall mail notices of the public hearing to the applicant and to all property owners and property occupants located within three hundred (300) feet of the exterior boundaries of the property containing the proposed site. Notices shall be mailed to said property owners at the addresses shown on the latest equalized County assessment roll, as well as the occupants at the situs addresses, as well as the County website. In addition, the Director shall publish a notice of the public hearing at least once in a newspaper of general circulation, published and circulated in the area of the proposal. All notices shall be mailed and published at least ten (10) days prior to the public hearing. The Director shall also provide such other notice as may be appropriate in the circumstances of the project.
Notices of public hearing shall state the date, time, and place set for the commencement of the hearing; shall identify the property included within the proposal; and shall generally describe the subject matter of the hearing. A metes and bounds legal description of the subject property shall not be required. Notices required by this chapter may describe the subject property using landmarks, Assessor parcel numbers, and/or similar identifying information.
Failure to mail or to receive such notice, as a result of mistake or inadvertence, shall not affect the validity of the hearing or the decision rendered. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.608. Public hearing: Review. ¶
Esta sección aún no está traducida y se muestra en inglés.
Prior to the hearing, the Director shall submit copies of the following to the Department for a thirty (30)- day review period:
(a) A copy of the proposed reclamation plan;
(b) A copy of the environmental document for the reclamation plan, prepared in accordance with CEQA; and
(c) Other related documentation, as appropriate.
No reclamation plan may be approved until the Department has completed its review, or the thirty (30)- day period has expired. The Director shall prepare a written response to any written comments received from the Department regarding the reclamation plan submitted. If applicable, the Director's response shall specifically address, in detail, why any comments or suggestions submitted by the Department were not accepted. The Director shall forward copies of both the Department's comments and the Director's response to the applicant. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.609. Public hearing: Conflict of comments. ¶
Esta sección aún no está traducida y se muestra en inglés.
If there is a conflict between comments submitted by a trustee or responsible agency and the comments of other reviewing agencies received during circulation of the reclamation plan, as required by CEQA, the Commission or Board shall only consider the comments of the trustee or responsible agency. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.610. Public hearing: Findings for approval. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Commission or, on appeal, the Board may approve a reclamation plan pursuant to this chapter only if all of the following findings can be made:
(a) That the proposed reclamation plan and financial assurances comply with the Act, the Regulations, and this chapter;
(b) That the proposed mining shall be conducted pursuant to a surface mining permit granted in accordance with this title, or that the operator has vested rights to conduct surface mining pursuant to Section 2776 of the Act;
(c) That the site, during and after reclamation, will not be detrimental to the public health and safety, giving consideration to the degree and type of present and probable future exposure of the public to the site;
(d) That the proposed reclaimed use is consistent with the General Plan, any applicable specific plans, and the zoning of the site;
(e) That the proposed reclaimed use is compatible with the existing and probable future uses of surrounding lands, as designated in the General Plan;
(f) That the site is physically suitable for the proposed use of the land in its reclaimed condition, giving consideration, but not limited to, such factors as on-site soil conditions, local groundwater conditions, surface water flow, surrounding habitat areas, and public access to the proposed site;
(g) That the estimated financial assurances reasonably approximate the probable costs of carrying out the proposed reclamation plan; and,
(h) That a written response to the State Department of Conservation has been prepared and considered, describing the disposition of major issues raised by the Department. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.611. Public hearing: Decision. ¶
Esta sección aún no está traducida y se muestra en inglés.
After considering the evidence in the public hearing, the Commission or Board shall approve, conditionally approve, or deny the application by a written decision setting forth the findings supporting the action. Approval may be granted subject to any relevant condition which the Commission may deem necessary to effectuate the purposes of the Act, the Regulations, and this chapter. Such conditions may address any or all of the findings required by Section 10-5.610 of this article. If the application is conditionally approved, the conditions shall be specified in writing.
Within ten (10) days after the decision of the Commission or Board, the Director shall mail a copy of the decision to the applicant. Copies of the decision shall also be mailed to any other person with an interest in the application, who has deposited a self-addressed, stamped envelope with the Agency for the purpose of receiving a copy of the decision. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 7.
Financial Assurances
Sec. 10-5.701. Financial assurances: Scope. ¶
Esta sección aún no está traducida y se muestra en inglés.
Prior to the commencement of any mining activities, all new and existing surface mining operations conducted within the unincorporated territory of the County shall submit sufficient financial assurances to ensure the faithful performance of the reclamation plan approved pursuant to this chapter. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.702. Financial assurances: Form. ¶
Esta sección aún no está traducida y se muestra en inglés.
Surface mining operations that are not undertaken by governmental agencies shall provide financial assurances in any one or a combination of the following forms:
(a) Surety bonds;
(b) Trust funds;
(c) Irrevocable letters of credit; and/or,
(d) Such other forms of financial assurances as the State Mining and Geology Board may adopt.
In addition those listed above, governmental agencies undertaking surface mining operations may provide financial assurances in the following forms:
- (e) Pledges of revenue; and/or,
(f) Budget set asides. Financial assurances shall be issued by a corporate surety authorized to do conduct surety business in the State and shall be made payable to the “County of Yolo or the Department of Conservation.” Financial assurances that were approved by the County prior to January 1, 1993, and were made payable to the State Geologist shall be considered payable to the Department for the purposes of this chapter.
The form of such financial assurance instruments shall be subject to the approval of the County Counsel who may require such additional provisions as are necessary to ensure the performance of the obligations. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.703. Financial assurances: Pledges of revenue. ¶
Esta sección aún no está traducida y se muestra en inglés.
The action approving a pledge of revenue shall take the form of a resolution or other appropriate document from the governing body of the agency responsible for reclamation. The resolution or document shall remain in effect continuously until the approved reclamation plan has been determined to be completed by the Director, pursuant to this chapter. The pledge of revenue shall consist of the following items:
(a) The resolution or document establishing the pledge of revenue;
(b) The types and sources of pledged revenue;
(c) The period of time that each source of revenue is pledged to be available;
(d) The estimated amount of financial assurances necessary to complete the approved reclamation plan; and,
(e) An authorization for the County or the Department to use the proceeds of the pledge to complete reclamation, if the operator is incapable of performing reclamation, as determined in Article 9 of this chapter.
The government agency may pledge the following types of revenue that it controls, as long as the revenue is available in a timely manner to perform the necessary reclamation work:
(f) Fees, rents, or other charges;
(g) Tax revenues within statutory limitations; and/or
(h) Other guaranteed revenues that are acceptable to the lead agency and the State Mining and Geology Board. If the government agency ceases at any time to retain control of its ability to allocate pledged revenue to complete reclamation, the governing body of the agency shall notify both the lead agency and the Department within sixty (60) days after control lapses. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.704. Financial assurances: Budget set asides. ¶
Esta sección aún no está traducida y se muestra en inglés.
Government agencies may also submit financial assurances in the form of a specific fund or line item set aside to provide funds for reclamation. The budget set aside shall remain in effect continuously until the approved reclamation plan has been determined to be completed by the Director, pursuant to this chapter. The budget set aside shall consist of the following items:
(a) A resolution or other appropriate document establishing the set aside or line item including proof of approval by the governing body or appropriate official of the government agency;
(b) The types and sources of specific funds;
(c) The period of time that each funding source is to be available;
(d) The estimated amount of financial assurances necessary to complete the approved reclamation plan; and,
(e) The authorization for the County or the Department to use the funds to complete reclamation, if the operator is incapable of performing reclamation, as determined in Article 9 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.705. Financial assurances: Term. ¶
Esta sección aún no está traducida y se muestra en inglés.
Financial assurances shall remain in effect until the County has determined that the reclamation plan has been completed as approved. Financial assurances may be made renewable for periods of at least one year. However, the failure of an operator to renew any financial assurance before its expiration date shall be considered a violation of this chapter. New or renewed financial assurances shall be submitted to the County prior to the expiration date of the existing financial assurances. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.706. Financial assurances: Calculations. ¶
Esta sección aún no está traducida y se muestra en inglés.
The amount of the financial assurances shall be equal to one-hundred (100%) percent of the estimated cost of implementing the approved reclamation plan. The estimated cost of reclamation shall be calculated by the operator and shall be based on the following factors:
(a) An analysis of the physical activities and materials necessary to implement the approved reclamation plan;
(b) The lead agency’s unit costs for each of the specified activities, or the unit costs for a third party contract, if applicable. When calculating the unit costs of reclamation activities, prevailing wage rates shall not be used,
(c) The number of units for each of the specified activities; and,
(d) An amount to cover contingency costs, not to exceed ten (10%) percent of the reclamation costs estimated above.
The costs associated with the completion of permitted mining shall not be used in the calculation of financial assurances.
The salvage value of buildings and equipment left on-site as a result of abandonment by the operator may be included to offset the costs of reclamation in the calculation of financial assurances. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.707. Financial assurances: Phasing. ¶
Esta sección aún no está traducida y se muestra en inglés.
If a phased reclamation plan is approved, the initial amount of the financial assurances shall be no less than onehundred (100%) percent of the total cost of all reclamation work to be done in the first approved phase. Before mining commences in the subsequent phase, additional financial assurances shall be submitted in an amount equal to onehundred (100%) percent of the total cost of reclamation for that phase. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.708. Financial assurances: Annual adjustments. ¶
Esta sección aún no está traducida y se muestra en inglés.
As a part of the annual report, each operator shall submit a revised estimate of financial assurances for the following year. Financial assurances may be adjusted annually by the Director to account for any of the following factors:
(a) The addition of new permitted lands to be mined in the following year;
(b) Previously mined lands which have been completely reclaimed in accordance with the approved reclamation plan; and,
(c) The increased labor and/or material costs of reclamation. Any decision to either increase or decrease financial assurances shall become final within fifteen (15) days, unless appealed to the Planning Commission within that fifteen (15)- day period, as provided in Article 11 of this chapter. The review of existing financial assurances shall not be considered a project within the meaning of CEQA, pursuant to the exemption granted under Section 2770(c) of the Act. (§ 1, Ord. 1191, eff. September 5, 1996, as amended by § 2, Ord. 1407, eff. April 28, 2011)
Sec. 10-5.709. Financial assurances: Review. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Director shall submit a copy of all new and revised financial assurance estimates and any supporting documentation to the Department for a forty-five (45)-day review period. No financial assurances may be approved until the Department has completed its review. The Director shall prepare a written response to any written comments received from the Department regarding the financial assurances submitted. If applicable, the Director’s response shall specifically address, in detail, why any comments or suggestions submitted by the Department were not accepted. The Director shall forward copies of both the Department’s comments and the Director’s response to the operator. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.710. Financial assurances: Transfer. ¶
Esta sección aún no está traducida y se muestra en inglés.
If a surface mining operation is sold or ownership is transferred to another person, the existing financial assurances shall remain in full force and effect and shall not be released until new financial assurances are secured by the new owner and approved by the County. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.711. Financial assurances: Release. ¶
Esta sección aún no está traducida y se muestra en inglés.
The mining operator shall notify the Director in writing when all or any portion of the required reclamation work is completed. Within sixty (60) days after notification to the County by the operator, the Director shall inspect the site in order to determine whether the site or the portion thereof complies with the approved reclamation plan. If it is determined that reclamation has not been completed pursuant to the approved reclamation plan, then the Director shall notify the operator in writing, specifically describing the remedial steps required for compliance. If it is determined that reclamation has been completed as approved, then the Director shall place the matter on the agenda of the Planning Commission for action within thirty (30) days. The Planning Commission may release all or a portion of the financial assurances, as appropriate. The Director shall send written notification of the proposed release of financial assurances to both the operator and the Department prior to the Planning Commission action. (§ 1, Ord. 1191, eff. September 5, 1996)
Sec. 10-5.712. Financial assurances: Disasters. ¶
Esta sección aún no está traducida y se muestra en inglés.
Prior to final approval of reclamation by the County and the release of financial assurances, if a reclaimed site or any reclaimed phases thereof have been adversely affected by a disaster, such as flood, earthquake, or other natural occurrence beyond the operator’s control, then the Director shall take the following factors into account in determining the operator’s responsibility:
(a) The extent to which the operator had completed reclamation prior to the natural occurrence;
(b) The extent to which the reclamation work has been destroyed by the natural occurrence;
(c) The effect of the natural occurrence on the public health and safety;
(d) The degree to which the site can be reclaimed naturally without human intervention;
(e) The specific reasons a particular monitoring period was established for reclamation; and,
(f) The site characteristics, reclamation program, and the proposed end use.
The operator may not be held responsible for the adverse impacts caused by a natural occurrence if the reclamation has been approved and the financial assurances released by the County. (§ 1, Ord. 1191, eff. September 5, 1996)
Article 8.
Amendments and Modifications to Approved Reclamation Plans
Sec. 10-5.801. Amendments and modifications: Purpose. ¶
Esta sección aún no está traducida y se muestra en inglés.
The purpose of this article is to provide procedures for changing the conditions of approval or project description (as described in the application and accompanying analyses) to account for unanticipated changes in the reclamation, site characteristics, regulations, or other aspects of the approved reclamation plan. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.802. Amendments: Applications. ¶
Esta sección aún no está traducida y se muestra en inglés.
Applications for amendments to previously approved reclamation plans shall be submitted to the Director, on forms provided by the Agency, and shall be accompanied by the appropriate fees, as determined in Article 10 of this chapter. Such applications shall be processed pursuant to the procedures set forth in Article 6 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.803. Amendments: Exceptions and changes. ¶
Esta sección aún no está traducida y se muestra en inglés.
Proposed exceptions to the reclamation standards may not be included as part of any application for a minor modification. Any changes in the conditions of approval or the amount of surface area and/or depth to be disturbed shall also be treated as a substantial deviation from the approved plan. Such changes and exceptions shall be processed as an amendment to the reclamation plan. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.804. Minor modifications. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Director may approve minor modifications of reclamation plans approved by the Commission pursuant to this chapter. Minor modifications may only be approved if it is found that such changes would be consistent with the conclusions of the EIR or other applicable environmental document, and that such changes will not have a significantly adverse effect on the successful achievement of the approved reclamation plan. Such modifications shall be noted on the approved plans and shall be initialed by the Director.
The decision of the Director shall be mailed and posted in accordance with Section 10-5.607 of this chapter. Any minor modification approved by the Director shall become final within fifteen (15) days, unless appealed to the Board, as provided in Article 11 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.805. Interim management plans: Scope. ¶
Esta sección aún no está traducida y se muestra en inglés.
Anytime that the annual production of a surface mining operation is reduced for a period of one year or more by more than ninety percent (90%) of its maximum annual mineral production within any of the last five (5) years during which an interim management plan has not been approved, then the operator shall submit an interim management plan to provide measures for maintaining the site until normal production is resumed. The interim management plan shall be considered an amendment to the approved reclamation plan, but not just cause to re-examine an approved reclamation plan and/or cause the plan to be subsequently amended. An interim management plan shall not be considered a project within the meaning of CEQA, pursuant to the exemption granted under Section 2770 of the Act. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.806. Interim management plans: Application. ¶
Esta sección aún no está traducida y se muestra en inglés.
Within ninety (90) days of a surface mining operation becoming idle, the operator shall submit an application for an interim management plan to the County. A proposed interim management plan shall be reviewed by the Director within thirty (30) days of receipt to determine whether the application complies with the requirements of this article. If the application is complete, then within ninety (90) days of the receipt of the application, a public hearing shall be held before the Commission to approve or deny the interim management plan in accordance with the procedures set forth in Article 6 of this chapter.
The interim management plan application shall include, at a minimum, the following:
(a) A statement describing why the mining operation is idle, including a description of those conditions necessary to reactivate the operation;
(b) The requested duration of the interim management plan (not to exceed five (5) years);
(c) A description of the measures to be taken to maintain site security;
(d) An analysis prepared by a Registered Civil Engineer describing interim slope angles, slope stability, and erosion control measures to be implemented during the interim period;
(e) A description of the equipment to be retained on the site;
(f) A plan prepared by a qualified biologist describing how revegetation efforts would be maintained in the interim period; and
(g) A plan showing the extent of mined areas, areas where reclamation has not yet been completed, internal haul roads and parking areas, stockpile locations, and equipment storage.
In addition to the foregoing, the Director may require such other and further information relevant to the project as needed to determine whether the proposal may affect the public health and safety. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.807. Interim management plans: Incomplete. ¶
Esta sección aún no está traducida y se muestra en inglés.
If the application does not comply with the requirements of this article, then the Director shall notify the applicant in writing, describing any deficiencies in the plan. The applicant shall have thirty (30) days to submit a revised plan correcting the deficiencies noted by the Director. If the revised application is complete, then within sixty (60) days of the receipt of the revised application, a public hearing shall be held before the Commission to approve or deny the interim management plan in accordance with the procedures set forth in Article 6 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.808. Interim management plans: Review. ¶
Esta sección aún no está traducida y se muestra en inglés.
The Director shall submit a copy of the interim management plan to the Department for a forty-five (45) day review period. No interim management plan may be approved until the Department has completed its review. The Director shall prepare a written response to any written comments received from the Department regarding the interim management plan. If applicable, the Director's response shall specifically address, in detail, why any comments or suggestions submitted by the Department were not accepted. The Director shall forward copies of both the Department's comments and the Director's response to the operator. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.809. Interim management plans: Appeal. ¶
Esta sección aún no está traducida y se muestra en inglés.
The decision of the Commission may be appealed to the Board of Supervisors within fifteen (15) days of the date of the decision, pursuant to Article 11 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.810. Interim management plans: Term. ¶
Esta sección aún no está traducida y se muestra en inglés.
Approved interim management plans shall remain in effect for a period not to exceed five (5) years. Prior to the expiration of the interim management plan, the Commission shall take one of the following actions:
(a) Renew the interim management plan for an additional period not to exceed five (5) years, which may be renewed for one additional five (5) year renewal period at the expiration of the first five (5) year renewal period, if the Commission finds that the surface mining operator has complied fully with the interim management plan; or
(b) Require the operator to commence reclamation in accordance with its approved reclamation plan. The operator shall notify the Director in writing prior to the reactivation of the surface mining operation. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.811. Interim management plans: Financial assurances. ¶
Esta sección aún no está traducida y se muestra en inglés.
Financial assurances shall remain in effect during the term of the interim management plan and any extensions granted thereto. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.812. Interim management plans: Abandonment. ¶
Esta sección aún no está traducida y se muestra en inglés.
Unless the operation has a pending or approved interim management plan, or an appeal of the interim management plan is pending before the Board of Supervisors, any surface mining operation which remains idle for more than one year shall be considered abandoned. All abandoned mining operations shall commence and complete reclamation in accordance with the approved reclamation plan, pursuant to Article 9 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.813. Interim management plans: Conditions. ¶
Esta sección aún no está traducida y se muestra en inglés.
All applicable conditions of approval shall remain in effect during the interim period. The Commission may impose additional conditions of approval necessary to safeguard the environment and the public health and safety. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.814. Interim permit review. ¶
Esta sección aún no está traducida y se muestra en inglés.
Every ten (10) years after a reclamation plan has been approved, the Commission shall hold a public hearing in accordance with Article 5 of this chapter, for the purpose of amending the plan to bring it into conformance with
applicable future environmental regulations and statutory changes. The Commission shall evaluate the plan to determine if there have been any subsequently adopted environmental regulations or statutory provisions which should be made applicable to the reclamation plan, even if such laws themselves are not made retroactive to affect the plan. For the purposes of this article, an environmental regulation or statutory provision is one that is promulgated by a responsible or trustee agency that has authority for a particular natural resource (e.g., Yolo-Solano Air Quality Management District, California Department of Fish and Wildlife, California Department of Conservation, Regional Water Quality Control Board, State Lands Commission, State Reclamation Board, etc.), including the County of Yolo. As a part of this review, the Commission shall also consider whether per-ton fees to which the permit is subject, reasonably reflect actual costs. The fees shall be adjusted up or down accordingly.
Should the Commission decide to incorporate into the reclamation plan new regulatory or statutory provisions that were not available at the time of project approval, said provisions shall be applied as an amendment to the plan and processed in accordance with Article 6 of this chapter. The decision of the Commission may be appealed, in accordance with Article 10 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 9.
Abandonment
Sec. 10-5.901. Abandonment: Hearing. ¶
Esta sección aún no está traducida y se muestra en inglés.
If, at any time, the Director determines that the operator is financially incapable of performing the required reclamation, or has abandoned the surface mining operation without completing the approved reclamation plan, or has failed to observe an order to comply, then a public hearing shall be held before the Commission as provided for in Article 6 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.902. Abandonment: Notice. ¶
Esta sección aún no está traducida y se muestra en inglés.
If the Commission determines that the operator is financially incapable of performing the required reclamation, or has abandoned the surface mining operation without completing the approved reclamation plan, or has failed to observe an order to comply, then the Director shall provide written notification to the operator by personal service or certified mail that the County intends to forfeit the financial assurances. The written notification shall include the specific reasons for the forfeiture. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.903. Abandonment: Forfeit of financial assurances. ¶
Esta sección aún no está traducida y se muestra en inglés.
The operator shall be allowed sixty (60) days to commence reclamation in accordance with the approved reclamation plan. Reclamation shall be completed within the time specified in the approved reclamation plan, or at a time mutually agreed to by the Director and the operator.
If the operator fails to begin reclamation within the sixty (60) days after notification, or otherwise fails to complete the approved reclamation plan within the time specified, then the Director may demand performance of any surety company issuing the financial assurances and commence reclamation of the site. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.904. Abandonment: Reclamation. ¶
Esta sección aún no está traducida y se muestra en inglés.
The following persons may enter the mine site and any adjacent property of the operators to plan or conduct all or any of the work described in the approved reclamation plan:
(a) Officers, employees, and agents of the County;
(b) Contractors hired by the County, as well as their subcontractors and agents; and
(c) Surveyors, engineers, and other consultants retained by the County.
These persons may bring onto the site and use thereon any and all equipment and machines necessary for completing the reclamation plan, and may use any equipment, supplies, earth, or other materials abandoned by the operator to perform required reclamation work.
The County shall follow the approved reclamation plan and all applicable permit conditions of approval in completing reclamation work. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.905. Abandonment: Use of financial assurances. ¶
Esta sección aún no está traducida y se muestra en inglés.
All or any portion of the financial assurances shall be deposited into a separate fund held by the County for the costs and reasonable expenses and fees associated with completing the approved reclamation plan. In no event shall the financial assurances be used for any other purpose.
If, after the Director has determined that the approved reclamation plan has been completed and all costs incurred by the County in performing such work have been accounted for, then any remaining monies from the financial assurances shall be refunded to the operator or the surety company, as their interests may appear, in accordance with Section 10-5.711 of this chapter. The operator shall be held responsible for all costs incurred by the County in completing the reclamation plan which exceed the amount of the forfeited financial assurances. Costs accrued by the County which exceed the amount of financial assurances shall be paid according to a schedule agreed to by the operator and the Director. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Article 10.
Fees
Sec. 10-5.1001. Fees: Applications. ¶
Esta sección aún no está traducida y se muestra en inglés.
Each application for a reclamation plan and/or approval of financial assurances or any amendments and modifications thereto shall be accompanied by the appropriate fee as determined by the Master Fee Resolution adopted by the Board. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Sec. 10-5.1002. Annual reviews. ¶
Esta sección aún no está traducida y se muestra en inglés.
Each operator individually shall be responsible for the payment of fees to cover the costs incurred by the County in annually inspecting the facilities of that operator, pursuant to Section 10-5.1203 of this chapter, as determined by the Master Fee Resolution adopted by the Board and any and all costs associated with the administration of Article 12. Said fee shall be due within thirty (30) days of written notification by the Director.
Failure to pay the above fees in a timely manner shall be considered a violation and may be enforced under the provisions of Article 12 of this chapter. (§ 1, Ord. 1191, eff. September 5, 1996; as amended by Ord. 1518, eff. February 13, 2020)
Obtén una respuesta en español sencillo con una cita a este texto.
Pregúntale a la IA sobre este código▸ Contenido — Yolo County Planning Code
- Chapter 1 — ENVIRONMENTAL IMPACT ASSESSMENTS
- Chapter 2 — ELM TREES
- Chapter 3 — CACHE CREEK AREA PLAN IN-CHANNEL ORDINANCE
- Chapter 4 — OFF-CHANNEL SURFACE MINING
-
▸ Chapter 5 — SURFACE MINING RECLAMATION
- Chapter 6 — AGRICULTURE
- Chapter 7 — GROUNDWATER
- Chapter 8 — AGRICULTURAL SURFACE MINING AND RECLAMATION ORDINA…
- Chapter 9 — STORMWATER MANAGEMENT AND DISCHARGE CONTROL
- Chapter 10 — HABITAT MITIGATION ORDINANCE
- Chapter 11 — GRAVEL MINING FEE ORDINANCE
- Chapter 12 — OFF-HIGHWAY VEHICLE USE AND OPERATION
- Chapter 14 — INDUSTRIAL HEMP CULTIVATION, MANUFACTURING, PROCE…