(a) Applicable Projects. The Central SoMa Infrastructure Impact Fee is applicable to any development project in the Central SoMa Special Use District that:
(1) Is in any Central SoMa Tier, pursuant to Section 423; and
(2) Includes new construction or an addition of space in excess of 800 gross square feet.
(b) Fee Calculation. For applicable projects, the Fee is as follows:
(1) For Residential uses in Central SoMa Fee Tier B:
(A) For Owned Units, as defined in Section 415.2, $20.00 per gross square foot of net additional gross square feet, net replacement of gross square feet from PDR uses, or net change of use of gross square feet from PDR uses.
(B) For Rental Units, defined as units that are not Owned Units as defined in Section 415.2, $10.00 per gross square foot of net additional gross square feet, net replacement of gross square feet from PDR uses, or net change of use of gross square feet from PDR uses.
(2) For Non-residential uses in Central SoMa Fee Tier A that are seeking an Office Allocation of 50,000 gross square feet or more pursuant to the requirements of Planning Code Section 321, $21.50 per gross square foot of net additional gross square feet, net replacement of gross square feet from PDR uses, or net change of use of gross square feet from PDR uses.
(3) For Non-residential uses in Central SoMa Fee Tier A that are not seeking an Office Allocation of 50,000 gross square feet or more pursuant to the requirements of Planning Code Section 321:
- (A) $41.50 per gross square foot of net additional gross square feet, net replacement of gross square feet from PDR uses, or net change of use of gross square feet from PDR uses;
(B) $21.50 per gross square foot of net replacement of gross square feet from Residential uses or net change of use of gross square feet from Residential uses.
(4) For Non-residential uses in Central SoMa Fee Tier C that are not seeking an Office Allocation of 50,000 gross square feet or more pursuant to the requirements of Planning Code Section 321, $20.00 per gross square foot of net additional gross square feet, net replacement of gross square feet from PDR uses, or net change of use of gross square feet from PDR uses.
(c) Option for In-Kind Provision of Community Improvements and Fee Credits. Project sponsors may propose to directly provide community improvements to the City. In such a case, the City may enter into an In-Kind Improvements Agreement with the sponsor and issue a fee waiver for the Central SoMa Infrastructure Impact Fee from the Planning Commission, subject to the following rules and requirements:
(1) Approval Criteria. The City shall not enter into an In-Kind Agreement unless the proposed in-kind improvements meet an identified community need as analyzed in the Central SoMa Community Improvements Program and substitute for improvements that could be provided by the Central SoMa Infrastructure Public Benefits
Fund (as described in Section 433.4). The City may reject in-kind improvements if they are not consistent with the priorities identified in the Central SoMa Plan, by the Interagency Plan Implementation Committee (see Section 36 of the Administrative Code), the Eastern Neighborhoods Citizens Advisory Committee, or other prioritization processes related to Eastern Neighborhoods Citizens community improvements programming. No physical improvement or provision of space otherwise required by the Planning Code or any other City Code shall be eligible for consideration as part of this In-Kind Improvements Agreement.
(2) Valuation, Content, Approval Process, and Administrative Costs. The valuation, content, approval process, and administrative costs shall be undertaken pursuant to the requirements of Sections 423.3(d)(2) through 423.3(d)(5).
(d) Timing of Fee Payments. The Fee shall be paid to DBI for deposit into the Central SoMa Infrastructure Impact Fund at the time required by Section 402(d).
(e) Waiver or Reduction of Fees. Development projects may be eligible for a waiver or reduction of impact fees, pursuant to Section 406.
(Added by Ord. 296-18, File No. 180184, App. 12/12/2018, Eff. 1/12/2019; amended by Ord. 63-20 ,, File No. 200077, App. 4/24/2020, Eff. 5/25/2020; Ord. 47-21, File No. 201175, App. 4/16/2021, Eff. 5/17/2021) AMENDMENT HISTORY
Division (d) amended; Ord. 63-20 ,; Eff. 5/25/2020. Divisions (b)(1)(A) and (b)(1)(B) amended; Ord. 47-21, Eff. 5/17/2021.
Obtén una respuesta en español sencillo con una cita a este texto.
Pregúntale a la IA sobre este código▸ Contenido — San Francisco County Planning Code
- Chapter 10E — PLANNING MONITORING
- Chapter 10E — PLANNING MONITORING
- Chapter 24 — REDEVELOPMENT AGENCY
- Chapter 24 — REDEVELOPMENT AGENCY
- Chapter 29A — APPROVAL OF POWER PLANT; PLANNING CODE SEC. 303
- Chapter 29A — APPROVAL OF POWER PLANT; PLANNING CODE SEC. 303
- Chapter 31 — CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCEDURES
- Chapter 31 — CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCEDURES
- Chapter 44 — ADULT DAY HEALTH CARE PLANNING COUNCIL
- Chapter 44 — ADULT DAY HEALTH CARE PLANNING COUNCIL
- Chapter 56 — DEVELOPMENT AGREEMENTS
- Chapter 56 — DEVELOPMENT AGREEMENTS
- Chapter 61 — WATERFRONT LAND USE
- Chapter 61 — WATERFRONT LAND USE
- Chapter 2 — ENVIRONMENTALLY PREFERABLE PURCHASING ORDINANCE
- Chapter 2 — ENVIRONMENTALLY PREFERABLE PURCHASING ORDINANCE
- Chapter 4 — EMERGENCY PLANNING AND PREPAREDNESS.
- Chapter 4 — EMERGENCY PLANNING AND PREPAREDNESS.
- Division I
- Division II
- Division III
- Division IV
- Division V
- Division VI
- Division VII
- Division VIII
- Division IX
- Division X
-
▸ Division XI
Overview- Article 4 — DEVELOPMENT IMPACT FEES AND PROJECT REQUIREMENTS
-
▸ Article 4 — DEVELOPMENT IMPACT FEES AND PROJECT REQUIREMENTS
Overview- SEC. 411. TRANSIT IMPACT DEVELOPMENT FEE.
- SEC. 412. DOWNTOWN PARK FEE.
- SEC. 413. JOBS-HOUSING LINKAGE PROGRAM; HOUSING REQUIREMENTS F…
- SEC. 414. CHILD-CARE REQUIREMENTS FOR OFFICE AND HOTEL DEVELOP…
- SEC. 415. HOUSING REQUIREMENTS FOR RESIDENTIAL AND LIVE/WORK D…
- SEC. 416. MARKET AND OCTAVIA AREA PLAN AND UPPER MARKET NEIGHB…
- SEC. 417. EASTERN NEIGHBORHOODS AREA PLAN AFFORDABLE HOUSING R…
- SEC. 418. RINCON HILL COMMUNITY IMPROVEMENTS FUND AND SOMA COM…
- SEC. 419. HOUSING REQUIREMENTS FOR RESIDENTIAL DEVELOPMENT PRO…
- SEC. 420. VISITACION VALLEY COMMUNITY FACILITIES AND INFRASTRU…
- SEC. 421. MARKET AND OCTAVIA COMMUNITY IMPROVEMENTS FUND.
- SEC. 422. BALBOA PARK COMMUNITY IMPROVEMENTS FUND.
- SEC. 423. EASTERN NEIGHBORHOODS IMPACT FEES AND PUBLIC BENEFIT…
- SEC. 424. VAN NESS & MARKET AFFORDABLE HOUSING AND NEIGHBORHOO…
- SEC. 425. VAN NESS & MARKET COMMUNITY FACILITIES FEE AND FUND.
- SEC. 428. DIVISADERO STREET NCT AFFORDABLE HOUSING FEE AND REQ…
- SEC. 429. ARTWORKS, OPTIONS TO MEET PUBLIC ART FEE REQUIREMENT…
- SEC. 430. BICYCLE PARKING IN LIEU FEE.
- SEC. 432. CENTRAL SOMA COMMUNITY SERVICES FACILITIES FEE AND F…
-
▸ SEC. 433. CENTRAL SOMA INFRASTRUCTURE IMPACT FEE AND FUND.
- SEC. 435. UNION SQUARE PARK, RECREATION, AND OPEN SPACE FEE.
- Article 7 — REDEVELOPMENT AGENCY AUTHORITY
- Article 7 — REDEVELOPMENT AGENCY AUTHORITY
- Division 1 — SUBDIVISION CODE
- Division 11 — LIMITED EQUITY HOUSING COOPERATIVE CONVERSIONS
- Division 2 — MISSION BAY SUBDIVISION CODE
- Division 2 — MISSION BAY SUBDIVISION CODE
- Division 3 — CANDLESTICK POINT/HUNTERS POINT SHIPYARD SUBDIVI
- Division 3 — CANDLESTICK POINT/HUNTERS POINT SHIPYARD SUBDIVI
- Division 4 — TREASURE ISLAND AND YERBA BUENA ISLAND SUBDIVISI