Local zoning · Tehama County

Tehama County — Design Review

Design Review under the Tehama County local zoning and planning code, with the controlling citations.

Last reviewed: July 6, 2026

Overview

In unincorporated areas of Tehama County, “design review” isn’t a single stand‑alone chapter or board; it’s implemented through several parts of the county’s zoning code that control site and building design during discretionary review, plot plan approval, and specialized permits. Start with the county’s zoning & planning overview to confirm your site is in unincorporated Tehama County; incorporated cities have their own rules.

The most universal trigger: any commercial or industrial project that creates more than 10,000 sq ft of impervious surface must meet the County’s objective development design standards before plot plan approval for a building permit (§ 17.08.080 ).

Design-related review also appears in use permit findings that expressly evaluate “design and operating characteristics” (§ 17.70.040 ), objective development standards applied by district (e.g., M‑1), the Water Efficient Landscape rules when a project requires “plan check or design review” (§ 17.85.040 ), and specialized chapters like Communication Facilities (§ 17.71.060, § 17.71.090 ).

How design review is used in unincorporated Tehama County

  • Objective “development design standards” apply to large commercial/industrial site work at plot plan stage (§ 17.08.080 ).
  • Use permits require findings on compatibility of location, size, design, and operations (§ 17.70.040 ).
  • Landscape submittals may be required and can be filed “with a … design review application” for projects subject to the Water Efficient Landscape Ordinance (§ 17.85.040(B) ).
  • Certain districts bake in administrative design checks (e.g., M‑1 requires administrative review and conformance to development design standards before building permits for changes of use/occupancy, § 17.34.020(D) ).
  • Specialized chapters impose design/aesthetic submittals (e.g., color elevations, visual simulations for towers; §§ 17.71.060, 17.71.090 ).
  • Overlays can add review/notice steps tied to physical design (e.g., Military Operation Overlay; § 17.69.040 ).

Countywide, cross-cutting design requirements

  • Development Design Standards threshold. Any commercial or industrial building or complex that exceeds 10,000 sq ft of impervious area must meet minimum design standards before plot plan approval. Topics include building design (avoid blank walls along streets), pedestrian amenities, color, and materials (§ 17.08.080 ). Tie these to your base‑zone rules in Tehama County Zoning.
  • Water Efficient Landscape (when permit, plan check, or “design review” is required). New or rehabilitated landscapes meeting size thresholds (e.g., ≥2,500 sq ft in single‑lot commercial/industrial; ≥2,500 sq ft developer-installed in multi‑family; ≥5,000 sq ft homeowner‑provided) must submit a Landscape Documentation Package, which may be filed with a design review application (§ 17.85.040(A)–(B) ). See Landscaping and Screening.
  • Use permit design compatibility. If your project needs a use permit, the Planning Commission must find the “location, size, design and operating characteristics” are compatible, considering scale, bulk, coverage, traffic, and neighborhood character (§ 17.70.040 ).
  • Communication facilities. Applications must include dimensioned site plans, color elevations, visual impact assessments, and demonstrate aesthetic compatibility; conditions address height, siting, lighting, finishes, screening, and cumulative visual effects (§ 17.71.060; § 17.71.090 ).
  • Military Operation Overlay. New discretionary projects that could penetrate the defined floor elevation of the MOA are reviewed for light/glare, visibility, and physical obstructions; the County must notify the Armed Forces and apply overlay processing rules (§ 17.69.040 ). See Overlay Districts.

District-by-district: how design review shows up

The following districts commonly interface with design review or objective design checks in unincorporated Tehama County. Always pair these with base district development standards and any overlay requirements in the Land Use map.

M-1 Light Industrial

  • Purpose/typical uses. Light industrial, research and development, data centers, accessory offices, and clean manufacturing (§ 17.34.010; § 17.34.020(A) ).
  • Key dimensional standards. Front setback 20 ft; side/rear “none” except as required by other codes; max height 65 ft; no lot area/coverage minimums (§§ 17.34.040–.070 ).
  • Design review hook. Any change of use or occupancy requires administrative review by Planning and must meet the County’s development design standards before a building permit is issued (§ 17.34.020(D) ). Projects adding >10,000 sq ft of impervious area must satisfy § 17.08.080 at plot plan stage .

M-2 General Industrial

  • Purpose/typical uses. Heavy industrial uses like lumber mills, batching plants, and yards; all M‑1 uses allowed (§ 17.36.010; § 17.36.020 ).
  • Key dimensional standards. Yards minimal; side/rear may be “none”; height follows C‑2 limits; off‑street loading required (§§ 17.36.040–.080 ).
  • Design review hook. Same countywide design/landscape triggers apply (e.g., § 17.08.080; § 17.85.040 ). Expect robust screening and circulation design; coordinate with Parking.

C-2 General Commercial

  • Purpose/typical uses. General commercial retail and services; several uses require a use permit (§ 17.26.030 ).
  • Key dimensional standards. Front: 50 ft from centerline or 20 ft from property line (greater controls); sides: none (subject to other codes); rear: 15 ft where accessible; height: up to 65 ft; no lot coverage minimum (§§ 17.26.040, 17.26.060 ).
  • Design review hook. Parking/loading must follow general provisions in § 17.08.080—plan early for driveways, aisles, and screening (§ 17.26.070 ). Projects over the 10,000‑sq‑ft impervious threshold trigger the county’s objective design standards (§ 17.08.080 ).

PD Planned Development

  • Purpose/typical uses. Intended for larger, master‑planned sites; any R, C, M, or S district use may be permitted, subject to a use permit (§ 17.38.010; § 17.38.030 ).
  • Key dimensional standards. Yards, lot area, building height, and site coverage are set by the use permit for the PD (§§ 17.38.040–.060 ).
  • Design review hook. The chapter expressly allows varying standards “when such variance will result in improved design” of the development—expect design conditions integrated into the PD’s use permit (§ 17.38.080 ). Countywide design/landscape triggers still apply (§§ 17.08.080; 17.85.040 ).

Overlay with design implications: Military Operation Overlay (MOA)

  • What it does. Adds review for hazards to aircraft (glare, emissions, vertical obstructions) and requires notice to the Armed Forces for qualifying discretionary projects (§ 17.69.040 ). Coordinate early if your building height, lighting, or emissions could affect aviators. See Overlay Districts.

Design review triggers and what to expect (quick table)

Trigger/Topic What’s reviewed or required Applies where Code Reference
>10,000 sq ft impervious (commercial/industrial) Objective development design standards before plot plan approval (building design, color, materials, pedestrian amenities) Countywide in unincorporated areas § 17.08.080
M-1 change of use/occupancy Administrative review; must meet development design standards prior to building permit M‑1 Light Industrial § 17.34.020(D)
Landscape subject to WEL Ordinance and “design review” Landscape Documentation Package (may submit with design review app) Projects meeting size thresholds and needing building permit/plan check/design review § 17.85.040(A)–(B)
Use permit (any district) Findings on compatibility of location, size, design, operations; conditions possible Countywide in unincorporated areas § 17.70.040
Communication facilities Site plan, color elevations, simulations; height/finish/siting/lighting/screening standards Countywide; any zoning with applicable permit §§ 17.71.060, 17.71.090
MOA Overlay Review of light/glare/obstruction; notice to Armed Forces Within/under MOA or near installations § 17.69.040

Checklist

  • Confirm your parcel is in unincorporated Tehama County and identify its base zone and any overlays via Tehama County Zoning.
  • If commercial/industrial, calculate new impervious area; if >10,000 sq ft, prepare materials to show compliance with § 17.08.080 (building design, color, materials, pedestrian features) before plot plan approval .
  • Screen for landscape thresholds; if the Water Efficient Landscape Ordinance applies, assemble the Landscape Documentation Package (MAWA/ETWU, plans) and be ready to submit it with any design review filing (§ 17.85.040(B) ).
  • If a use permit is required, address compatibility/“design and operating characteristics” in your narrative and plans (§ 17.70.040 ).
  • In M‑1, include administrative review materials and show conformance to County development design standards for any change of use/occupancy (§ 17.34.020(D) ).
  • If proposing a communication facility, provide color elevations, visual simulations, and demonstrate aesthetic compatibility (§§ 17.71.060, 17.71.090 ).
  • If in the MOA overlay, coordinate early for the hazard review/notice step (§ 17.69.040 ).
  • Cross‑check any parking, signage, or screening details with applicable chapters (Parking, Signage, Landscaping and Screening).

Risks & Ambiguities

Issue Why it matters What to verify
Section cross‑reference numbering (17.08.080 vs. 17.08.090) M‑1 points to § 17.08.090 for design standards, while current codification shows standards in § 17.08.080 Verify the current section number with Planning before submittal (§ 17.34.020(D); § 17.08.080)
Whether your project needs a use permit Use permit findings include “design and operating characteristics,” which can add conditions Check your use list in the base zone and confirm permit type in Tehama County Zoning and § 17.70.040
What counts as “impervious surface” Triggers objective design standards at 10,000 sq ft Confirm with staff how your paving/roof areas are counted under § 17.08.080
Landscape submittal timing WEL package can ride with a “design review application” Coordinate timing/format with Planning per § 17.85.040(B)
MOA overlay applicability Extra review/notice may affect height, lighting, plume, or schedule Map your site against MOA and confirm review path under § 17.69.040

Information Gaps

  • Formal “Design Review Board” or a chapter titled “Design Review”: Not found in retrieved materials.
  • A comprehensive, countywide “site plan review” procedure outside specific use chapters (e.g., bed & breakfast): Not found in retrieved materials.
  • Detailed submittal checklist for general (non‑communications) design review beyond the WEL Package: Not found in retrieved materials.
  • Historic resource‑specific design standards: Not found in retrieved materials; see Historic Preservation for related policy context.

Plain-English Summary

If you’re building in unincorporated Tehama County, there isn’t a single “Design Review” chapter—but your project’s look, site layout, and landscaping will be checked through objective design standards (especially if you add more than 10,000 sq ft of hardscape), use‑permit findings, required landscape packages, and any overlay/specialty standards. Plan early for setbacks, heights, circulation, landscape water budgets, and screening, and be ready to submit clear site plans and elevations that demonstrate compatibility with surrounding areas.

Source References

  • § 17.08.080 Development design standards (impervious >10,000 sq ft; plot plan approval)
  • § 17.70.040 Use permit findings; design and operating characteristics
  • § 17.85.040 Water Efficient Landscape—applicability; Landscape Documentation Package; “design review application” filing path
  • §§ 17.71.060, 17.71.090 Communication facilities—submittals; aesthetic/height/siting standards
  • § 17.69.040 Military Operation Overlay—review and notice
  • §§ 17.34.010–.070 M‑1 Light Industrial—purpose, uses, yards, height; admin review and design standards cross‑reference (§ 17.34.020(D))
  • §§ 17.36.010–.080 M‑2 General Industrial—purpose, uses, yards/height/loading
  • §§ 17.26.030–.070 C‑2 General Commercial—use permit list; yards; height; parking linkage to § 17.08.080
  • §§ 17.38.010–.080 PD Planned Development—PD entitlement standards and design flexibility

Sources

Retrieved passages

  • Tehama County Zoning Code (chapter and) High relevance
  • Tehama County Zoning Code (Section 17.85.050) Medium relevance
  • Tehama County Zoning Code Medium relevance
  • Tehama County Zoning Code (§2) Medium relevance
  • Tehama County Zoning Code (§4) Medium relevance
  • Tehama County Zoning Code (§ 6) Medium relevance
  • Tehama County Zoning Code Medium relevance
  • CFC § 20 (Chapter 4.24.) Medium relevance
  • Tehama County Zoning Code (Section 17.70.040) Medium relevance
  • Tehama County Zoning Code (§2) Medium relevance
  • Tehama County Zoning Code Medium relevance
  • Tehama County Zoning Code (§1) Medium relevance
  • CBC § 1 (section are) Medium relevance
  • Tehama County Zoning Code (§ 1) Medium relevance
  • Tehama County Zoning Code (§ 1) Medium relevance
  • Tehama County Zoning Code (§2) Medium relevance
  • CFC § 2 (chapter and) Medium relevance
  • Tehama County Zoning Code (§ 1) Medium relevance
  • CBC § 2 (§2) Medium relevance
  • Tehama County Zoning Code (§3) Medium relevance
  • CBC § 1 (Title 17) Medium relevance

Cited sections

Frequently asked questions

Do I need “design review” for a commercial project in unincorporated Tehama County?

Likely yes if your project adds more than 10,000 sq ft of impervious surface; you must show compliance with the County’s development design standards before plot plan approval (§ 17.08.080 ). If a use permit is also needed, the Planning Commission will evaluate your design and operating characteristics for compatibility (§ 17.70.040 ).

What design materials should I submit for a wireless tower?

Expect a dimensioned site plan, color elevations, and visual simulations; you must also address height, finishes, lighting, and screening per the communications chapter (§ 17.71.060; § 17.71.090 ).

How do landscaping rules connect to design review?

If your landscape area meets Water Efficient Landscape thresholds and the project requires a building permit, plan check, or “design review,” you must submit a Landscape Documentation Package; it may be filed with the design review application (§ 17.85.040(A)–(B) ).

In the M-1 district, what extra design steps apply when changing a use?

Any change of use/occupancy requires administrative review by Planning and must meet the County’s development design standards prior to building permit issuance (§ 17.34.020(D) ). Projects over 10,000 sq ft impervious also trigger § 17.08.080 .

Will the Military Operation Overlay affect my building design?

If your project could penetrate the overlay’s defined floor elevation or is near specified military areas, the County reviews for hazards (glare, emissions, obstructions) and must notify the Armed Forces (§ 17.69.040 ). Height, lighting, and plume controls can affect design.

Do commercial districts have their own design standards?

Yes—base zones set setbacks, heights, and site layout controls (e.g., C‑2 up to 65 ft height, specified yards; parking/loading per § 17.08.080; §§ 17.26.040–.070 ). These work in tandem with countywide development design standards (§ 17.08.080 ).

Does Tehama County have a Design Review Board?

Not found in retrieved materials. Design review functions are carried out through plot plan approval, use permits, and specialized chapters like Communications Facilities (§§ 17.08.080; 17.70.040; 17.71.060, 17.71.090 ).

Do ADUs go through design review?

The ADU section references conformance with “site plan review” and other standard residential requirements (§ 17.08.050(A)(7) ). State ADU law limits what local design standards can apply; see California ADU law for the objective‑standards rule.

Are there special design standards for historic properties?

Not found in retrieved materials. Coordinate early with Planning and see Historic Preservation for applicable processes or constraints.

More in Tehama County code

Ask about any Tehama County property

Get a cited, plain-English answer on Tehama County zoning, setbacks, FAR, ADUs and permits — for any address.

Start Free Trial

More Tehama County zoning topics