What South San Francisco's code says

South San Francisco code What South San Francisco's code adds
Deadline to comply
  • Defects must be repaired or replaced within 120 days of the city finding them.
    Applies: Applies when the lateral fails the inspection required for projects remodeling, altering or enlarging over 25% of the building area.
    § 14.14.140 · code text
    Any defects in the building sanitary sewer lateral that cause the sewer lateral to fail the inspection must be repaired or replaced within one hundred twenty days of the date the city determines that a defect exists.
Fee or permit
  • A city certificate of compliance before the building permit, after a licensed video inspection with city staff present.
    Applies: Applies to projects needing a building permit that remodel, alter or enlarge more than 25% of the building area.
    § 14.14.140 · code text
    Proof of the repair or replacement as directed by the city must be provided to the city before a certificate of compliance and/or building permit will be issued.
When an inspection is required
  • All building sewer laterals must be inspected and get a certificate of compliance before a building permit.
    Applies: Applies to any project needing a building permit that remodels, alters or enlarges more than 25% of the building area.
    § 14.14.140 · code text
    For any project requiring a building permit where more than twenty-five percent of the building area is being remodeled, altered or enlarged, the project applicant or property owner shall inspect all building sanitary sewer laterals on the property for defects and obtain a certificate of compliance before a building permit is issued.

Who this affects

BuyersSellersReal estate agents

Frequently asked questions

Does South San Francisco require a sewer lateral inspection when you sell a home?

South San Francisco's code: All building sewer laterals must be inspected and get a certificate of compliance before a building permit. (Applies to any project needing a building permit that remodels, alters or enlarges more than 25% of the building area.) (§ 14.14.140); Defects must be repaired or replaced within 120 days of the city finding them. (Applies when the lateral fails the inspection required for projects remodeling, altering or enlarging over 25% of the building area.) (§ 14.14.140).

General information, not legal advice.

Ask about a specific South San Francisco property

Ask GoCodebook how South San Francisco's sewer lateral inspection rules apply to your situation and get an answer that cites the section.

Ask your question

More on buying & selling in South San Francisco