What Redwood City's code says

Redwood City code What Redwood City's code adds
How the park fee is set
  • The fee is the parkland required minus land dedicated, times the land cost per acre.
    Applies: Park fee for subdivisions.
    § 30.70 · code text
    The fee required with respect to a subdivision shall bear a reasonable relationship to the use of the park and recreational facilities by the future inhabitants of the subdivision, and shall be calculated by first subtracting the acreage dedicated pursuant to Section 30.70 from the parkland requirement for that subdivision and then multiplying the result of that calculation by a per acre land cost calculated pursuant to subsection B, below.
  • Land cost is $3,865,382.00 per acre.
    Applies: Used for the subdivision park fee; adjusted each July 1 by the construction cost index.
    § 30.70 · code text
    The cost per acre of land for purposes of subsection A, above, shall be three million eight hundred sixty-five thousand three hundred eighty-two dollars ($3,865,382.00).
Parkland per 1,000 residents
  • 2.75 acres of park land per 1,000 residents.
    Applies: Used to set the parkland a subdivision must provide.
    § 30.68 · code text
    2.75 acres of property for each one thousand (1,000) persons residing within this City be devoted to park and recreational purposes.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

What park or impact fees apply to a new home in Redwood City?

Redwood City's code: The fee is the parkland required minus land dedicated, times the land cost per acre. (Park fee for subdivisions.) (§ 30.70); 2.75 acres of park land per 1,000 residents. (Used to set the parkland a subdivision must provide.) (§ 30.68).

General information, not legal advice.

Ask about a specific Redwood City property

Ask GoCodebook how Redwood City's park and impact fees for new homes rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Redwood City