Solar panels and EV chargers in Palm Springs

Small residential rooftop solar permits get administrative, nondiscretionary review and are issued within 3 business days when the application meets the city checklist.

Key points

  • Solar permits: Small residential rooftop solar permits get administrative, nondiscretionary review and are issued within 3 business days when the application meets the city checklist.

Each rule below links to the section of the Palm Springs Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Palm Springs's code says

Palm Springs code What Palm Springs's code adds
EV charger permit
  • You may apply electronically with electronic signatures; the charger stays off until the city grants approval and all permits.
    § 8.105.060 · code text
    The Building Official shall allow for electronic submittal of permit applications covered by this chapter and associated supporting documentations.
Solar permit process
  • Administrative, nondiscretionary review: a building permit is issued when the application meets the city checklist.
    Applies: Applies to small residential rooftop solar systems.
    § 8.100.060 · code text
    The Building Department shall implement the following administrative, nondiscretionary review process to expedite the approval of small residential rooftop solar energy system applications:
Review time
  • The permit is issued within 3 business days.
    Applies: Applies when a rooftop solar application meets the city checklist.
    § 8.100.060 · code text
    For an application for a small residential rooftop solar energy system that meets the requirements of the City's checklist, the Building Department shall issue a building permit or other non-discretionary permit or authorization within three business days.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Palm Springs?

Small residential rooftop solar permits get administrative, nondiscretionary review and are issued within 3 business days when the application meets the city checklist.

General information, not legal advice.