Grading and erosion control in Modesto
Modesto's own rules on grading and erosion control, with the code text for every value.
Each rule below links to the section of the Modesto Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.
What Modesto's code says
| When a grading permit is needed |
|
|---|---|
| Grading without a permit |
|
Who this affects
Frequently asked questions
What are the grading rules in Modesto?
Modesto's code: A permit is needed for 350 cubic yards or more of soil, or clearing and grubbing more than one-half acre. (Applies to grading, filling, digging, storing or disposing of soil or earth material.) (§ 5-10.301); Less than 350 cubic yards of soil, or clearing and grubbing less than one-half acre. (Exempt work must still meet the chapter's standards.) (§ 5-10.302).
General information, not legal advice.
Ask about a specific Modesto property
Ask GoCodebook how Modesto's grading and erosion control rules apply to your situation and get an answer that cites the section.
Ask your questionMore on building on your lot in Modesto
All building on your lot rules in Modesto
Sheds, garages and other accessory structures in Modesto
Solar panels and EV chargers in Modesto
Parking spaces required for homes in Modesto
Home alarm permits and false alarms in Modesto
Trash and recycling carts in Modesto
Historic homes in Modesto
Modesto Municipal Code — full text