Lincoln's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Lincoln Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Lincoln's code says

Lincoln code What Lincoln's code adds
Solar permit process
  • Administrative, nondiscretionary building permit review, limited to health and safety requirements.
    Applies: Small residential rooftop solar applications that meet the approved checklist and standard plan.
    § 15.05.060 · code text
    The building department shall either approve or deny the issuance of a building permit, the issuance of which is nondiscretionary, on the same day for over-the-counter applications that meet the requirements of the approved checklist and standard plan and one to three days for applications submitted by e-mail or facsimile.
  • You may submit the application by email or online.
    Applies: Applies to small residential rooftop solar permit applicants.
    § 15.05.050 · code text
    Electronic submittal of the required permit application and documents by email, or the Internet will be made available to all small residential rooftop solar energy system permit applicants.
Review time
  • Approved or denied the same day.
    Applies: Small residential rooftop solar; over-the-counter applications that meet the approved checklist and standard plan.
    § 15.05.060 · code text
    The building department shall either approve or deny the issuance of a building permit, the issuance of which is nondiscretionary, on the same day for over-the-counter applications that meet the requirements of the approved checklist and standard plan
  • Approved or denied in 1 to 3 days.
    Applies: Small residential rooftop solar; applications sent by email or fax.
    § 15.05.060 · code text
    and one to three days for applications submitted by e-mail or facsimile.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Lincoln?

Lincoln's code: Administrative, nondiscretionary building permit review, limited to health and safety requirements. (Small residential rooftop solar applications that meet the approved checklist and standard plan.) (§ 15.05.060); You may submit the application by email or online. (Applies to small residential rooftop solar permit applicants.) (§ 15.05.050).

General information, not legal advice.