Solar panels and EV chargers in Kingsburg

Kingsburg's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Kingsburg Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Kingsburg's code says

Kingsburg code What Kingsburg's code adds
EV charger permit
  • A permit application is required, with the completed city checklist attached.
    § 15.10.040 · code text
    Any person wishing to install an electric vehicle charging station shall file an application, in the form provided by the city, for a permit to install an electric vehicle charging station. A completed city checklist for permitting electric vehicle service equipment ("checklist") shall accompany the application.
  • The city must accept electronic applications and electronic signatures.
    Applies: Applies to permit applications under this ordinance.
    § 15.10.040 · code text
    the City shall allow electronic submittal of permit applications covered by this ordinance and associated supporting documentations for installation of electric vehicle charging stations. In accepting such applications, the city shall also accept electronic signatures
  • Approved, with all needed permits issued, when the application meets the city checklist and health and safety requirements.
    Applies: Applies to EV charging stations.
    § 15.10.040 · code text
    Upon confirmation by the building official that the permit application and supporting documents meets the requirements of the city adopted checklist and is consistent with all applicable laws and health and safety standards, the building official shall, in accordance with Government Code Section 65850.7, approve the application and issue all necessary permits
Review time
  • The permit is issued 3 business days after a complete application.
    Applies: Over the counter or electronic applications that meet the approved checklist and standard plan.
    § 15.09.060 · code text
    The building division shall issue a permit or other nondiscretionary approval three (3) business days after an over-the-counter application is deemed complete and meets the requirements of the approved checklist and standard plan
Solar permit process
  • Small residential rooftop solar: administrative review; permit within 3 business days of a complete application meeting checklist and standard plan.
    Applies: The building official may require a use permit if substantial evidence shows a specific, adverse impact on public health and safety.
    § 8.26.060 · code text
    within three (3) business days after the date of receipt of an application sent by electronic submittal is deemed complete and meets the requirements of the approved checklist and standard plan

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Kingsburg?

Kingsburg's code: Small residential rooftop solar: administrative review; permit within 3 business days of a complete application meeting checklist and standard plan. (The building official may require a use permit if substantial evidence shows a specific, adverse impact on public health and safety.) (§ 8.26.060); A permit application is required, with the completed city checklist attached. (§ 15.10.040).

General information, not legal advice.