Solar panels and EV chargers in Indio

Indio's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Indio Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Indio's code says

Indio code What Indio's code adds
EV charger permit
  • Expedited nondiscretionary permit, issued when the charger meets state and federal safety rules; apply in person, mail or electronically.
    Applies: Applies when the charger has no specific, adverse impact on public health or safety.
    § 151.065 · code text
    Anyone seeking to install an electric vehicle charging station system at any site within the City may apply to the Building Official for an expedited nondiscretionary building permit.
Solar permit process
  • Nondiscretionary permit for a complete application meeting the standard plan and checklist; 1 inspection, scheduled within 2 business days.
    Applies: Applies to small residential rooftop solar systems.
    § 151.060 · code text
    The Building Official shall issue a building permit, the issuance of which is nondiscretionary, on the same day for over the counter applications or within one to three business days for electronic applications or in either case as soon thereafter as may be practicable upon receipt of a complete application that meets the requirements of the approved checklist and standard plan.
Review time
  • The permit is issued the same day.
    Applies: Applies to a complete over-the-counter application that meets the approved checklist and standard plan.
    § 151.060 · code text
    The Building Official shall issue a building permit, the issuance of which is nondiscretionary, on the same day for over the counter applications or within one to three business days for electronic applications or in either case as soon thereafter as may be practicable upon receipt of a complete application that meets the requirements of the approved checklist and standard plan.
  • The permit is issued within 1 to 3 business days.
    Applies: Applies to a complete electronic application that meets the approved checklist and standard plan.
    § 151.060 · code text
    The Building Official shall issue a building permit, the issuance of which is nondiscretionary, on the same day for over the counter applications or within one to three business days for electronic applications or in either case as soon thereafter as may be practicable upon receipt of a complete application that meets the requirements of the approved checklist and standard plan.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Indio?

Indio's code: Nondiscretionary permit for a complete application meeting the standard plan and checklist; 1 inspection, scheduled within 2 business days. (Applies to small residential rooftop solar systems.) (§ 151.060); Expedited nondiscretionary permit, issued when the charger meets state and federal safety rules; apply in person, mail or electronically. (Applies when the charger has no specific, adverse impact on public health or safety.) (§ 151.065).

General information, not legal advice.