What Hawthorne's code says

Hawthorne code What Hawthorne's code adds
EV charger permit
  • The building official approves an application meeting the city checklist and issues all needed permits.
    Applies: Electric vehicle charging stations; the station may not be energized until the city approves it.
    § 15.71.050 · code text
    A permit application that satisfies the information requirements in the city's adopted checklist shall be deemed complete and be promptly processed.
  • Electronic submittal and electronic signatures are accepted.
    Applies: Electric vehicle charging station permit applications.
    § 15.71.050 · code text
    In accepting such permit applications, the building official shall also accept electronic signatures on all forms, applications, and other documentations in lieu of a wet signature by applicant.
Solar permit process
  • Administrative, nondiscretionary review; only one inspection, scheduled within 2 business days of a request.
    Applies: Small residential rooftop solar systems.
    § 15.70.070 · code text
    The city of Hawthorne building department shall adopt an administrative, nondiscretionary review process to expedite approval of small residential rooftop solar energy systems within thirty days of the adoption of the ordinance codified in this chapter.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Hawthorne?

Hawthorne's code: Administrative, nondiscretionary review; only one inspection, scheduled within 2 business days of a request. (Small residential rooftop solar systems.) (§ 15.70.070); The building official approves an application meeting the city checklist and issues all needed permits. (Electric vehicle charging stations; the station may not be energized until the city approves it.) (§ 15.71.050).

General information, not legal advice.

Ask about a specific Hawthorne property

Ask GoCodebook how Hawthorne's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Hawthorne