What Glendora's code says

Glendora code What Glendora's code adds
EV charger permit
  • Building or other nondiscretionary permit issued within 3 business days of a complete application meeting the checklist and standard plan.
    § 19.16.060 · code text
    The city of Glendora building department shall issue a building permit or other nondiscretionary permit within three business days upon receipt of a complete application that meets the requirements of the approved checklist and standard plan requirements.
  • Only one inspection; a separate fire inspection may also be required.
    Applies: EV charging systems eligible for expedited review.
    § 19.16.060 · code text
    Only one inspection shall be required and performed by the building division for EVC systems eligible for expedited review. A separate fire inspection may be required and performed by the Los Angeles County fire department for compliance with safety requirements.
Solar permit process
  • Only one inspection; a separate fire inspection may also be required.
    Applies: Small residential rooftop solar systems eligible for expedited review.
    § 19.21.060 · code text
    Only one inspection shall be required and performed by the building division for small residential rooftop solar energy systems eligible for expedited review. On some submittals a separate fire inspection may be required and performed by the Los Angeles County fire department for their safety requirements.
Review time
  • Permit issued within 3 days.
    Applies: Small residential rooftop solar with a complete application meeting the expedited checklist and standard plan.
    § 19.21.060 · code text
    The building division shall issue a building permit or other nondiscretionary permit within three days of receipt of a complete application that meets the requirements of the expedited approved checklist and standard plan.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Glendora?

Glendora's code: Only one inspection; a separate fire inspection may also be required. (Small residential rooftop solar systems eligible for expedited review.) (§ 19.21.060); Building or other nondiscretionary permit issued within 3 business days of a complete application meeting the checklist and standard plan. (§ 19.16.060).

General information, not legal advice.

Ask about a specific Glendora property

Ask GoCodebook how Glendora's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Glendora