What Fullerton's code says

Fullerton code What Fullerton's code adds
EV charger permit
  • Must be approved if it meets the checklist and standards and has no specific, adverse public health or safety impact.
    § 14.30.060 · code text
    If the application meets the requirements of the approved checklist and standards, and the proposed electric vehicle charging station and/or hydrogen fueling station does not pose any specific, adverse impact upon public health or safety, the Building Official must approve the application.
  • Decision (approved, or a use permit is needed) within 30 days after a complete application.
    § 14.30.060 · code text
    The Building Official must notify an applicant whether the application has been approved, or, alternatively, whether the applicant must obtain an “electric vehicle charging station use permit” or a “hydrogen fueling station use permit,” within 30 days after the submission of a complete application.
Review time
  • Within 3 business days.
    Applies: Applies to over-the-counter applications for small rooftop home solar that meet the checklist and standard plan.
    § 14.18.060 · code text
    For an application for a small residential rooftop solar energy system that meets the requirements of the approved checklist and standard plan, the Building Division shall issue a building permit or other non-discretionary permit within three business days for over-the-counter applications or within five business days for electronically filed applications.
  • Within 5 business days.
    Applies: Applies to electronically filed applications for small rooftop home solar that meet the checklist and standard plan.
    § 14.18.060 · code text
    For an application for a small residential rooftop solar energy system that meets the requirements of the approved checklist and standard plan, the Building Division shall issue a building permit or other non-discretionary permit within three business days for over-the-counter applications or within five business days for electronically filed applications.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Fullerton?

Fullerton's code: Within 3 business days. (Applies to over-the-counter applications for small rooftop home solar that meet the checklist and standard plan.) (§ 14.18.060); Must be approved if it meets the checklist and standards and has no specific, adverse public health or safety impact. (§ 14.30.060).

General information, not legal advice.

Ask about a specific Fullerton property

Ask GoCodebook how Fullerton's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Fullerton