What Elk Grove's code says

Elk Grove code What Elk Grove's code adds
How the park fee is set
  • Acres of land required times fair market value per acre equals the fee.
    Applies: When the approving authority requires a fee instead of land.
    § 22.28.040 · code text
    A x V = M
  • Fair market value set by appraisal.
    Applies: City park and recreation land dedications.
    § 22.28.040 · code text
    the subdivider shall pay the in-lieu fee based upon the fair market value established by the appraisal consistent with the standards set forth herein.
  • Units in each land use category times the cost per unit set in the fee resolution.
    Applies: Residential development in the Laguna Ridge Specific Plan.
    § 16.82.080 · code text
    the Laguna Ridge supplemental park fee shall be calculated by multiplying the number of units per land use category by a cost per unit factor as identified in the fee resolution.
Parkland per 1,000 residents
  • At least 5 acres per 1,000 residents.
    Applies: All new residential subdivisions or projects, unless an adopted community or specific plan sets another ratio.
    § 22.28.030 · code text
    All new residential subdivisions or development projects shall provide real property for recreation and park purposes at a ratio of no less than five (5) acres of property for each one thousand (1,000) members of the population of the City
  • 2 acres per 1,000 residents.
    Applies: Local and neighborhood parks.
    § 22.28.030 · code text
    A standard of two (2) acres per each one thousand (1,000) persons for local parks
  • 3 acres per 1,000 residents.
    Applies: Community and regional parks.
    § 22.28.030 · code text
    A standard of three (3) acres per each one thousand (1,000) persons for community parks
When the fee applies
  • Tentative maps of 50 lots or less may pay a fee instead of dedicating land.
    § 22.28.040 · code text
    The proposed tentative map contains fifty (50) lots or less.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

What park or impact fees apply to a new home in Elk Grove?

Elk Grove's code: Acres of land required times fair market value per acre equals the fee. (When the approving authority requires a fee instead of land.) (§ 22.28.040); At least 5 acres per 1,000 residents. (All new residential subdivisions or projects, unless an adopted community or specific plan sets another ratio.) (§ 22.28.030).

General information, not legal advice.

Ask about a specific Elk Grove property

Ask GoCodebook how Elk Grove's park and impact fees for new homes rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Elk Grove