Grading and erosion control in Danville

Danville's own rules on grading and erosion control, with the code text for every value.

Each rule below links to the section of the Danville Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Danville's code says

Danville code What Danville's code adds
Erosion control plan
  • All cut and fill slopes must be planted under an erosion-control plan approved by the Town Engineer.
    § 19-6.3 · code text
    All cut and fill slopes shall be planted in accordance with an erosion-control plan approved by the Town Engineer.
Grading without a permit
  • Excavation for basements and footings of a structure with a valid building permit (not the fill made from it, and not an excavation over five (5') feet unsupported height); fills not intended to support structures, under three (3') feet deep, not over one hundred (100) cubic yards, on natural slopes flatter than five (5') horizontal to one (1') vertical and at least three (3') feet from a property line; excavations under three (3') feet deep moving no more than one hundred (100) cubic yards, with no cut slope over five (5') feet high or steeper than three (3') horizontal to one (1') vertical, at least five (5') feet (or one-half the height of a nearby building, retaining structure or slope, if greater) from a property line
    Applies: The fill must not change the drainage pattern, as the Town Engineer determines
    § 19-3.2 · code text
    A grading permit is not required for the following:
Rainy-season limits
  • Grading from October 15 to April 15 may be banned unless the Town Engineer approves a written request.
    Applies: Applies to grading up to and including pad certification.
    § 19-4.1 · code text
    Grading activity, up to and including pad certification, is subject to periodic review and approval of the Town Engineer and may be prohibited between October 15 and April 15

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

What are the grading rules in Danville?

Danville's code: Excavation for basements and footings of a structure with a valid building permit (not the fill made from it, and not an excavation over five (5') feet unsupported height); fills not intended to support structures, under three (3') feet deep, not over one hundred (100) cubic yards, on natural slopes flatter than five (5') horizontal to one (1') vertical and at least three (3') feet from a property line; excavations under three (3') feet deep moving no more than one hundred (100) cubic yards, with no cut slope over five (5') feet high or steeper than three (3') horizontal to one (1') vertical, at least five (5') feet (or one-half the height of a nearby building, retaining structure or slope, if greater) from a property line (The fill must not change the drainage pattern, as the Town Engineer determines) (§ 19-3.2); All cut and fill slopes must be planted under an erosion-control plan approved by the Town Engineer. (§ 19-6.3).

General information, not legal advice.