Yes — you can build an ADU in Corte Madera. California's statewide ADU law requires every city, including Corte Madera, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Corte Madera's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

Local rule

conversions (>=1 or 25% of units) + up to 2 detached (proposed multifamily) or up to 8 detached (existing multifamily), not to exceed number of existing units

Local cap of 2 detached ADUs for proposed multifamily and 8 for existing multifamily, not to exceed number of existing units.

CMMC § 18.31.030(d)-(e), (1)-(2)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,000 sq ft

Detached ADUs: 850 sq ft (studio/1-bed), 1,000 sq ft (2-bed); up to 1,200 sq ft with discretionary review.

CMMC § 18.31.080(f)(1)-(2), (k)

Max attached ADU size

Local rule

lesser of 50% of primary or 850/1,000 sq ft local max; must allow at least 800 sq ft

Attached ADUs capped at 850/1,000 sq ft unless discretionary review; must allow at least 800 sq ft.

CMMC § 18.31.080(f)(3)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

Local rule

25 ft

Detached: 16 ft standard, 18 ft near transit/multifamily, up to 20 ft in floodplain; attached/above garage: up to 25 ft or primary dwelling height, whichever is less.

CMMC § 18.31.080(e)(1)-(6)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

Local rule

3 ft

Detached ADUs must be at least 3 ft from primary dwelling and other accessory structures.

CMMC § 18.31.080(c)

Parking

Parking required

Local rule

Up to 1 space

1 space per ADU unless exempt; exemptions include proximity to transit, historic district, conversions, etc.

CMMC § 18.31.110(a)-(c)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

Local rule

Not required

No replacement required for parking lost to ADU conversion or demolition.

CMMC § 18.31.110(d)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

CA state law

Only for a JADU

No owner-occupancy requirement for ADUs (the prior sunset was removed). A JADU may require owner-occupancy, principally where it shares sanitation with the main house.

Cal. Gov. Code § 66315 (owner-occupancy)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

Local rule

ADU permit, Building permit

Both ADU permit (ministerial) and building permit required.

CMMC § 18.31.035, § 18.31.040(a)

Corte Madera-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Christmas Tree Hill Overlay District

Cap on ADUs/JADUs at 10% of primary units in capacity districts due to fire/evacuation constraints.

Historic Districts

No parking required for ADUs in historic districts.

Corte Madera sets a local detached ADU max of 1,000 sq ft (2-bed) and requires 3 ft separation from the primary dwelling. The Christmas Tree Hill Overlay District imposes a strict ADU/JADU cap due to fire evacuation concerns.

Frequently asked questions

Can I build an ADU in Corte Madera?

Yes. California's statewide ADU law requires Corte Madera to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Corte Madera?

A detached ADU of at least 1,000 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Corte Madera?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Corte Madera?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Corte Madera?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Corte Madera?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Corte Madera Municipal Code Chapter 18.31 (Ord. No. 1043, § 5, 12-17-2024)
  • CMMC § 18.31.030(d)-(e), (1)-(2)
  • CMMC § 18.31.080(f)(1)-(2), (k)
  • CMMC § 18.31.080(f)(3)
  • CMMC § 18.31.080(e)(1)-(6)
  • CMMC § 18.31.080(c)
  • CMMC § 18.31.110(a)-(c)
  • CMMC § 18.31.110(d)
  • CMMC § 18.31.035, § 18.31.040(a)
  • CMMC § 18.31.120
  • CMMC § 18.31.110(b)(2)
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
  • Cal. Gov. Code § 66333 (junior ADUs)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66315 (owner-occupancy)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated 2026-06-25. This is an AI-assisted summary of Corte Madera's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Corte Madera Planning before relying on it.

Will an ADU work on your Corte Madera lot?

Ask GoCodebook about your address and get the size, setback, parking and permit rules that actually apply to your parcel — with the exact citation.

Check my parcel free

Related