California ADU rules · Colusa County

Can I Build an ADU in Colusa?

Yes — you can build an ADU in Colusa. California's statewide ADU law requires every city, including Colusa, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Colusa's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

CA state law

Conversion ADUs (≥1, up to 25% of units) + up to 8 detached

Conversions of non-livable space (at least 1, or up to 25% of existing units) plus up to 8 detached ADUs on a lot with existing multifamily — never exceeding the number of existing units. JADUs are single-family only.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,200 sq ft

Local maximum for detached ADUs is 1,200 sq ft of habitable space.

Sec. 49.07(a)

Max attached ADU size

Local rule

50% of primary, >=850 (>=1,000 for 2+ bedrooms)

Attached ADUs capped at 50% of primary, but not less than 850 sq ft (studio/1-bed) or 1,000 sq ft (2+ bedrooms).

Sec. 49.07(b)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

CA state law

16 ft

16 ft baseline; cities must allow 18 ft within ½ mi of a major transit stop or where the primary dwelling is two-story, and 20 ft on a lot with a multistory multifamily building.

Cal. Gov. Code § 66321 (size minimums & height)

Setbacks

Side setback

Local rule

4 ft

4 ft minimum for new attached/detached ADUs; 5 ft if above a garage.

Sec. 49.06(b)

Rear setback

Local rule

4 ft

4 ft minimum for new attached/detached ADUs; 5 ft if above a garage.

Sec. 49.06(b)

Front setback

Local rule

Same as primary dwelling; 800 sq ft ADU may be in front yard if no feasible alternative.

Front setback matches primary dwelling; 800 sq ft ADU allowed in front yard if no other feasible location.

Sec. 49.06(b)

Separation from main house

CA state law

None required

No statewide separation requirement between the ADU and the primary dwelling.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Parking

Parking required

Local rule

Up to 1 space

1 off-street space per ADU, with multiple exemptions.

Sec. 49.12(a)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

Local rule

Not required

No replacement parking required when garage/carport is converted.

Sec. 49.12(a)(d)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

Local rule

Only for a JADU

Owner-occupancy required only for JADUs (either primary or JADU must be owner-occupied).

Sec. 49.20(b)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

Local rule

Building permit, ADU/JADU permit

Both a building permit and an ADU/JADU permit are required.

Sec. 49.05(b)

Colusa-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Sprinkler requirements

Sprinklers required only if primary dwelling is required to have them or if substantial remodel/addition increases floor area by >50%.

Colusa sets a 1,200 sq ft cap for detached ADUs, allows attached ADUs up to 50% of the primary (with state minimums), and permits 2-story ADUs up to 27 ft. No replacement parking is required for garage conversions, and owner-occupancy is required only for JADUs.

Frequently asked questions

Can I build an ADU in Colusa?

Yes. California's statewide ADU law requires Colusa to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Colusa?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Colusa?

Side and rear setbacks are limited to 4 ft. Same as primary dwelling; 800 sq ft ADU may be in front yard if no feasible alternative..

Is parking required for an ADU in Colusa?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Colusa?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Colusa?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Colusa Municipal Code, Article 49 (Ord. No. 568, 5-20-2025)
  • Sec. 49.07(a)
  • Sec. 49.07(b)
  • Sec. 49.06(b)
  • Sec. 49.12(a)
  • Sec. 49.12(a)(d)
  • Sec. 49.20(b)
  • Sec. 49.05(b)
  • Sec. 49.07(b), Sec. 49.03(d)
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
  • Cal. Gov. Code § 66333 (junior ADUs)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated May 20, 2025. This is an AI-assisted summary of Colusa's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Colusa Planning before relying on it.

Will an ADU work on your Colusa lot?