Solar panels and EV chargers in Chowchilla

Chowchilla's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Chowchilla Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Chowchilla's code says

Chowchilla code What Chowchilla's code adds
EV charger permit
  • Applications are reviewed and approved ministerially.
    Applies: Applies to EV charging station applications that meet the chapter rules and the city's standard permit checklist.
    § 15.61.040 · code text
    Applications for electric vehicle charging stations that comply with the requirements of this chapter and the city's standardized permit checklist shall be reviewed and approved ministerially.
Solar permit process
  • Only 1 inspection, scheduled within 2 business days of request, with a 2-hour inspection window.
    Applies: Applies to small residential rooftop solar systems eligible for expedited review.
    § 15.50.060 · code text
    Only one inspection shall be required and performed by the city for small residential rooftop solar energy systems eligible for expedited review. The inspection shall be done in a timely manner and should include consolidated inspections. An inspection will be scheduled within two business days of a request and provide a two-hour inspection window.
Review time
  • The permit is issued within 3 business days.
    Applies: Applies to a complete small residential rooftop solar application that meets the approved checklist and standard plan.
    § 15.50.060 · code text
    The city's building department shall issue a building permit or other nondiscretionary permit within three business days of receipt of a complete application that meets the requirements of the approved checklist and standard plan.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Chowchilla?

Chowchilla's code: Only 1 inspection, scheduled within 2 business days of request, with a 2-hour inspection window. (Applies to small residential rooftop solar systems eligible for expedited review.) (§ 15.50.060); Applications are reviewed and approved ministerially. (Applies to EV charging station applications that meet the chapter rules and the city's standard permit checklist.) (§ 15.61.040).

General information, not legal advice.