Solar height and setbacks
  • Panels cannot be taller than the maximum legal building height for the system to qualify.
    Applies: To qualify as a small residential rooftop solar energy system.
    § 15.04.040 · code text
    A solar panel or module array that does not exceed the maximum legal building height as defined by the authority having jurisdiction.
Solar permit process
  • Permits are issued administratively for a complete application meeting the checklist. Apply in person or electronically if available, with fees.
    Applies: Small residential rooftop solar systems eligible for expedited review; fees are the required permit processing and inspection fees.
    § 15.04.040 · code text
    The applicant shall submit the permit application and associated documentation to the City's building division either by personal or, if available, electronic submittal together with any required permit processing and inspection fees.
  • Only 1 inspection is required.
    Applies: Small residential rooftop solar systems eligible for expedited review.
    § 15.04.040 · code text
    For a small residential rooftop solar energy system eligible for expedited review, only one inspection shall be required, which shall be done in a timely manner and may include a consolidated inspection by the Building Inspector and Fire Department designee.
Review time
  • Permits are issued within 1 to 3 working days.
    Applies: A complete application that meets the checklist for a small residential rooftop solar energy system.
    § 15.04.040 · code text
    Upon confirmation by the building official of the application and supporting documentation being complete and meeting the requirements of the checklist, the building official shall administratively approve the application and issue all required permits or authorizations within one to three working days in which the permit application is submitted.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Ceres?

Ceres's code: Permits are issued administratively for a complete application meeting the checklist. Apply in person or electronically if available, with fees. (Small residential rooftop solar systems eligible for expedited review; fees are the required permit processing and inspection fees.) (§ 15.04.040); Only 1 inspection is required. (Small residential rooftop solar systems eligible for expedited review.) (§ 15.04.040).

General information, not legal advice.

Ask about a specific Ceres property

Ask GoCodebook how Ceres's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Ceres