California ADU rules · Kings County
Can I Build an ADU in Avenal?
Yes — you can build an ADU in Avenal. California's statewide ADU law requires every city, including Avenal, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.
Can you build one?
ADUs allowed
CA state lawYes — by right
ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.
Units on a single-family lot
CA state law1 ADU + 1 JADU
At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).
Units on a multifamily lot
CA state lawConversion ADUs (≥1, up to 25% of units) + up to 8 detached
Conversions of non-livable space (at least 1, or up to 25% of existing units) plus up to 8 detached ADUs on a lot with existing multifamily — never exceeding the number of existing units. JADUs are single-family only.
Junior ADU (JADU)
CA state lawAllowed
Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).
Size & height
Max detached ADU size
Local rule1,000 sq ft
Avenal caps the floor area of ALL accessory dwelling units (attached or detached) at 850 sq ft, or 1,000 sq ft for a unit with more than one bedroom (§ 9.60.030(D)) — below the 1,200 sq ft statewide default but above the 800 sq ft by-right floor the state protects regardless of any local cap.
Max attached ADU size
Local rule≤850 sq ft (≤1,000 sq ft for 2+ bedrooms)
Avenal's § 9.60.030(D) size cap applies uniformly to attached and detached ADUs. State law still guarantees an 850 sq ft attached ADU (1,000 sq ft for 2+ bedrooms) cannot be denied on size, so the local cap and the state floor coincide here.
Guaranteed minimum size
CA state law800 sq ft
An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).
Max JADU size
CA state law500 sq ft
Max height
Local rule16 ft
Detached ADU: 16 ft, rising to 18 ft (plus 2 ft for a matching roof pitch, i.e. 20 ft) within ½ mi of a major transit stop or on a multistory multifamily lot. An attached ADU may match the primary dwelling height up to 25 ft (§ 9.60.030(J)(2)). Tracks the state floor.
Setbacks
Side setback
CA state law4 ft
A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.
Rear setback
CA state law4 ft
Front setback
CA state lawNo front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone
Separation from main house
CA state lawNone required
No statewide separation requirement between the ADU and the primary dwelling.
Parking
Parking required
Local ruleNone
Avenal requires NO off-street parking for any ADU, and parking spaces removed to create an ADU need not be replaced (§ 9.60.030(C)) — more permissive than the state cap of 1 space.
Transit parking exemption
CA state lawYes — no parking required near transit & for conversions
No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.
Garage-conversion replacement parking
CA state lawNot required
When a garage/carport is demolished or converted to build an ADU, replacement parking cannot be required.
Approval, timeline & cost
Approval path
CA state lawMinisterial (by right)
No public hearing or discretionary design review for a qualifying ADU.
Approval timeline
CA state law60 days
The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.
Owner-occupancy
Local ruleOnly for a JADU
No owner-occupancy for ADUs (§ 9.60.030(F); the ordinance's 2025 sunset reference is superseded by permanent state law). A JADU is allowed only where the owner occupies the property as their primary residence (§ 9.60.040(A)).
Impact-fee waiver
CA state lawWaived under 750 sq ft
An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.
Permits required
CA state lawBuilding permit
Only a ministerial building permit — no conditional use permit or discretionary design review for a qualifying ADU.
Avenal adopted a current local ADU ordinance in its 2024 Zoning Ordinance (Title 9, §§ 9.60.030–9.60.040). Two specifics matter locally: ALL ADUs are capped at 850 sq ft (1,000 sq ft for 2+ bedrooms) — smaller than the 1,200 sq ft state default, though the 800 sq ft by-right floor still cannot be denied — and NO off-street parking is required. Detached ADUs use 4-ft side/rear setbacks and 16-ft height (18–20 ft near transit), and design rules require the ADU to match the primary dwelling's exterior finish and roof form. JADUs (≤500 sq ft) require owner-occupancy. Confirm setbacks and design review with Avenal Community Development.
Frequently asked questions
Can I build an ADU in Avenal?
Yes. California's statewide ADU law requires Avenal to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.
How big can an ADU be in Avenal?
A detached ADU of at least 1,000 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.
What are the setback requirements for an ADU in Avenal?
Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.
Is parking required for an ADU in Avenal?
None. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.
How long does ADU approval take in Avenal?
A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.
Do I have to live on the property to build an ADU in Avenal?
Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.
Sources
- Avenal Zoning Ordinance §§ 9.60.030–9.60.040 (Title 9 Zoning)
- Avenal Zoning Ord. § 9.60.030(D)
- Avenal Zoning Ord. § 9.60.030(J)(2)
- Avenal Zoning Ord. § 9.60.030(C)
- Avenal Zoning Ord. §§ 9.60.030(F), 9.60.040(A)
- Cal. Gov. Code §§ 66310–66342 (ADU Law)
- HCD 2025 Accessory Dwelling Unit Handbook
- Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
- Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
- Cal. Gov. Code § 66333 (junior ADUs)
- Cal. Gov. Code § 66321 (size minimums & height)
- Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
- Cal. Gov. Code § 66314 (local ordinance standards)
- Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)
Last updated 2026-06-28. This is an AI-assisted summary of Avenal's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Avenal Planning before relying on it.