What Alameda County's code says

Alameda County code What Alameda County's code adds
Parkland per 1,000 residents
  • 5 acres of park land per 1,000 people.
    § 12.20.120 · code text
    The park dedication requirement shall be based on a figure of five acres of land per one thousand (1,000) persons or two hundred eighteen (218) square feet per person except as may be indicated below.
Fee per home
  • $11,550.00 total per unit, including a $2,175.00 development increment.
    Applies: Single-family units, after July 1, 2006.
    § 12.20.120 · code text
    Single-family | 628 | $11,550.00 | $2,175.00
  • $10,200.00 total per unit, including a $1,900.00 development increment.
    Applies: Multiple units, after July 1, 2006.
    § 12.20.120 · code text
    Multiple | 555 | 10,200.00 | 1,900.00
  • $5,775.00 total per unit, including a $1,075.00 development increment.
    Applies: Secondary units, after July 1, 2006.
    § 12.20.120 · code text
    Secondary unit | 314 | 5,775.00 | 1,075.00
  • $5,775.00 total per unit, including a $1,075.00 development increment.
    Applies: Agricultural caretaker's units, after July 1, 2006.
    § 12.20.120 · code text
    Agricultural caretaker's unit | 314 | 5,775.00 | 1,075.00
  • $7,975.00 total per unit, including a $1,500.00 development increment.
    Applies: Mobilehomes, after July 1, 2006.
    § 12.20.120 · code text
    Mobilehome | 434 | 7,975.00 | 1,500.00

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

What park or impact fees apply to a new home in Alameda County?

Alameda County's code: $11,550.00 total per unit, including a $2,175.00 development increment. (Single-family units, after July 1, 2006.) (§ 12.20.120); 5 acres of park land per 1,000 people. (§ 12.20.120).

General information, not legal advice.

Ask about a specific Alameda County property

Ask GoCodebook how Alameda County's park and impact fees for new homes rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Alameda County