California ADU rules · Stanislaus County

Can I Build an ADU in Riverbank?

Yes — you can build an ADU in Riverbank. California's statewide ADU law requires every city, including Riverbank, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Riverbank's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

Local rule

conversions (>=1 or 25% of units) + up to 2 detached

Riverbank limits detached ADUs on multifamily lots to 2 per lot, less than the state default of 8.

§ 153.326(F)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,200 sq ft

Local maximum matches state cap; included for explicit local confirmation.

§ 153.327(A)(1)(b)

Max attached ADU size

Local rule

50% of primary dwelling

No local minimums stated; follows state for minimums.

§ 153.327(A)(1)(a)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

Local rule

16 ft

16 ft and 1 story for detached ADUs; up to 35 ft if above a garage.

§ 153.327(A)(4)

Setbacks

Side setback

Local rule

4 ft

Street side setback is 10 ft; standard side/rear is 4 ft.

§ 153.327(A)(3)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

Local rule

ADUs not allowed in front yard setback

ADUs prohibited in front yard setback, which is more restrictive than state default.

§ 153.327(A)(5)

Separation from main house

Local rule

None required

No specific minimum separation in zoning code; must comply with building code.

§ 153.327(A)(3)(c)

Parking

Parking required

Local rule

Up to 1 space

1 off-street space per ADU or per bedroom, whichever is less; exemptions per state law.

§ 153.327(D), (E)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

Local rule

Not required

No replacement required for parking lost due to ADU conversion.

§ 153.327(D)(3)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

Local rule

Only for a JADU

No owner-occupancy for ADUs approved Jan 2020–Jan 2025; required for JADUs.

§ 153.329(A)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

Local rule

Building permit, JADU deed restriction

JADUs require a deed restriction in addition to building permit.

§ 153.327(A)(2)(e)

Riverbank-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Fire code compliance

Must meet city-adopted building/fire code; sprinklers not required if not required for primary dwelling.

Historic district parking exemption

No parking required for ADUs in historic districts.

Riverbank limits detached ADUs on multifamily lots to 2 per lot and prohibits ADUs in the front yard setback. JADUs require a deed restriction and owner-occupancy, while ADUs do not (through Jan 2025).

Frequently asked questions

Can I build an ADU in Riverbank?

Yes. California's statewide ADU law requires Riverbank to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Riverbank?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Riverbank?

Side and rear setbacks are limited to 4 ft. ADUs not allowed in front yard setback.

Is parking required for an ADU in Riverbank?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Riverbank?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Riverbank?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Riverbank Municipal Code, Chapter 153, Sections 153.325–153.330 (Ord. 2021-007, passed 12-14-21)
  • § 153.326(F)
  • § 153.327(A)(1)(b)
  • § 153.327(A)(1)(a)
  • § 153.327(A)(4)
  • § 153.327(A)(3)
  • § 153.327(A)(5)
  • § 153.327(A)(3)(c)
  • § 153.327(D), (E)
  • § 153.327(D)(3)
  • § 153.329(A)
  • § 153.327(A)(2)(e)
  • § 153.327(A)(1)(d)
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
  • Cal. Gov. Code § 66333 (junior ADUs)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated 2026-06-25. This is an AI-assisted summary of Riverbank's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Riverbank Planning before relying on it.

Will an ADU work on your Riverbank lot?

Ask GoCodebook about your address and get the size, setback, parking and permit rules that actually apply to your parcel — with the exact citation.

Check my parcel free