California ADU rules · Monterey County

Can I Build an ADU in Monterey?

Yes — you can build an ADU in Monterey. California's statewide ADU law requires every city, including Monterey, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Monterey's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

CA state law

Conversion ADUs (≥1, up to 25% of units) + up to 8 detached

Conversions of non-livable space (at least 1, or up to 25% of existing units) plus up to 8 detached ADUs on a lot with existing multifamily — never exceeding the number of existing units. JADUs are single-family only.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

Local rule

1,000 sq ft

Monterey caps an attached OR detached ADU at 850 sq ft for a studio/1-bedroom and 1,000 sq ft for 2+ bedrooms — below the 1,200 sq ft statewide default. State law still guarantees an 800 sq ft ADU by right regardless. So a 2-bedroom detached ADU maxes at 1,000 sq ft here, not 1,200.

Max attached ADU size

Local rule

850 sq ft (studio/1 bedroom) or 1,000 sq ft (2+ bedrooms); a separate entrance is required

Monterey applies the same 850/1,000 sq ft size cap to attached and detached ADUs, and requires the ADU to have a separate entrance.

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

CA state law

16 ft

16 ft baseline; cities must allow 18 ft within ½ mi of a major transit stop or where the primary dwelling is two-story, and 20 ft on a lot with a multistory multifamily building.

Cal. Gov. Code § 66321 (size minimums & height)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

CA state law

None required

No statewide separation requirement between the ADU and the primary dwelling.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Parking

Parking required

Local rule

Up to 1 space

One space per unit or per bedroom, whichever is less, which may be tandem on an existing driveway or in setback areas — subject to the state exemptions (½ mi of transit, within an existing structure, historic district, etc.).

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

CA state law

Not required

When a garage/carport is demolished or converted to build an ADU, replacement parking cannot be required.

Cal. Gov. Code § 66314 (local ordinance standards)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

CA state law

Only for a JADU

No owner-occupancy requirement for ADUs (the prior sunset was removed). A JADU may require owner-occupancy, principally where it shares sanitation with the main house.

Cal. Gov. Code § 66315 (owner-occupancy)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

CA state law

Building permit

Only a ministerial building permit — no conditional use permit or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Monterey-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Coastal Zone / Local Coastal Program

Parcels in Monterey's Coastal Zone may need a coastal development permit and must conform to the city's certified Local Coastal Program, but ADU approval remains ministerial.

Water-credit verification (MPWMD)

An ADU is not permitted where water or sewer service is inadequate. Water adequacy is determined by the Monterey Peninsula Water Management District; verification of MPWMD water credits is required at building-permit application. This is the most common real-world blocker in Monterey.

The City of Monterey's ADU standards are in Monterey City Code § 38-112.6 (Ord. 3641, 2021). The distinctive local rule is size: ADUs are capped at 850 sq ft (studio/1-BR) or 1,000 sq ft (2+ BR) rather than the 1,200 sq ft state default — though an 800 sq ft ADU is always allowed by right. The binding constraint in practice is water: no ADU is permitted without verified MPWMD water credits. Coastal-zone parcels may also need a coastal development permit. (Do not confuse with Monterey County's separate coastal ADU ordinance.) Confirm water credits and coastal status with Monterey Planning.

Frequently asked questions

Can I build an ADU in Monterey?

Yes. California's statewide ADU law requires Monterey to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Monterey?

A detached ADU of at least 1,000 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Monterey?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Monterey?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Monterey?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Monterey?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

Last updated 2026-06-28. This is an AI-assisted summary of Monterey's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Monterey Planning before relying on it.