California ADU rules · Alameda County

Can I Build an ADU in Livermore?

Yes — you can build an ADU in Livermore. California's statewide ADU law requires every city, including Livermore, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Livermore's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

CA state law

1 ADU + 1 JADU

At least one ADU and one JADU per single-family lot (a conversion ADU may also be possible).

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Units on a multifamily lot

CA state law

Conversion ADUs (≥1, up to 25% of units) + up to 8 detached

Conversions of non-livable space (at least 1, or up to 25% of existing units) plus up to 8 detached ADUs on a lot with existing multifamily — never exceeding the number of existing units. JADUs are single-family only.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Junior ADU (JADU)

CA state law

Allowed

Up to 500 sq ft, within the walls of an existing single-family home (single-family lots only).

Cal. Gov. Code § 66333 (junior ADUs)

Size & height

Max detached ADU size

CA state law

1,200 sq ft

Statewide default cap for detached new-construction ADUs in the absence of a compliant local ADU ordinance. The unconditional by-right floor a city must always allow is 800 sq ft (see Guaranteed minimum size); a city with a compliant ordinance may set its own ceiling.

Max attached ADU size

CA state law

50% of the primary dwelling, but ≥850 sq ft (≥1,000 sq ft for 2+ bedrooms) is always allowed

Cal. Gov. Code § 66321 (size minimums & height)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

Local rule

16 ft

16 ft for a detached ADU on a lot with an existing/proposed single-family home; up to 25 ft for an ADU attached to the primary dwelling. State transit/two-story 18-ft (and 20-ft multistory-MF) allowances still apply.

Livermore Dev. Code, Part 11 (ADU Standards)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

CA state law

None required

No statewide separation requirement between the ADU and the primary dwelling.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Parking

Parking required

CA state law

Up to 1 space

At most 1 space per ADU (or per bedroom, whichever is less) — and waived in the common cases below.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

CA state law

Not required

When a garage/carport is demolished or converted to build an ADU, replacement parking cannot be required.

Cal. Gov. Code § 66314 (local ordinance standards)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

CA state law

Only for a JADU

No owner-occupancy requirement for ADUs (the prior sunset was removed). A JADU may require owner-occupancy, principally where it shares sanitation with the main house.

Cal. Gov. Code § 66315 (owner-occupancy)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

CA state law

Building permit

Only a ministerial building permit — no conditional use permit or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Livermore-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Citywide Objective Design Standards (ADU historic & design)

Livermore's Part 11 update adopted objective historic and design standards for ADUs — regulating features such as color, materials, and landscaping — exercising the local discretion state law allows, provided they never preclude a detached ADU of at least 800 sq ft with 4-ft side/rear setbacks.

Livermore re-codified its ADU rules in the Development Code's new Part 11 (Housing) chapter, adopted July 2025 and effective Aug. 28, 2025, bringing them into full compliance with current state ADU Law (HCD's Oct. 2025 letter had flagged the prior 2018 ordinance as outdated). The substantive numbers track the state floor — detached ADUs up to 1,200 sq ft, 4-ft side/rear setbacks, 16 ft detached / 25 ft attached height, one space per bedroom waived within ½ mi of transit, impact-fee exemption under 750 sq ft. The genuine local layer is a set of Citywide Objective Design Standards for ADUs (color, materials, landscaping, historic compatibility) that cannot block a 800 sq ft / 4-ft-setback ADU. Pre-approved ADU plans get a 7-business-day review. Verify the current objective design standards with Livermore Community Development before designing.

Frequently asked questions

Can I build an ADU in Livermore?

Yes. California's statewide ADU law requires Livermore to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Livermore?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Livermore?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Livermore?

Up to 1 space. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Livermore?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Livermore?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

Last updated 2026-06-28. This is an AI-assisted summary of Livermore's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Livermore Planning before relying on it.

Will an ADU work on your Livermore lot?

Ask GoCodebook about your address and get the size, setback, parking and permit rules that actually apply to your parcel — with the exact citation.

Check my parcel free