California ADU rules · Del Norte County

Can I Build an ADU in Crescent City?

Yes — you can build an ADU in Crescent City. California's statewide ADU law requires every city, including Crescent City, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Crescent City's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

Local rule

1 JADU + 1 non-exempt ADU OR 1 statewide exemption ADU (Type 1) + 1 Type 2 (detached) OR 1 Type 1 + 1 Type 2 + 1 non-exempt ADU if non-exempt ADU was built first

Allows more than state baseline if sequencing is met; see code for details.

§ 17.35.090

Units on a multifamily lot

Local rule

Conversions (>=1 or 25% of units) + up to 2 detached ADUs (each max 800 sqft)

Detached ADUs on multifamily lots capped at 2, each max 800 sqft.

§ 17.35.090

Junior ADU (JADU)

Local rule

Allowed

JADUs allowed, 1 per single-family lot.

§ 17.35.080(B)

Size & height

Max detached ADU size

Local rule

1,200 sq ft

Local maximum for detached ADUs is 1,200 sqft.

§ 17.35.060(B)

Max attached ADU size

Local rule

50% of primary, up to 1,200 sqft; >=850 (0–1 bed), >=1,000 (2+ bed)

Local cap of 1,200 sqft for attached ADUs.

§ 17.35.050(B)

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

Local rule

500 sq ft

JADU max size 500 sqft; min 150 sqft.

§ 17.35.080(B)

Max height

CA state law

16 ft

16 ft baseline; cities must allow 18 ft within ½ mi of a major transit stop or where the primary dwelling is two-story, and 20 ft on a lot with a multistory multifamily building.

Cal. Gov. Code § 66321 (size minimums & height)

Setbacks

Side setback

CA state law

4 ft

A city cannot require more than 4 ft side or rear setback; conversions of existing structures are exempt.

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Rear setback

CA state law

4 ft

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Front setback

CA state law

No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone

Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)

Separation from main house

Local rule

5 ft

Detached ADUs must be at least 5 ft from any other building.

§ 17.35.060(C)

Parking

Parking required

Local rule

None

No off-street parking required for ADUs or JADUs.

§ 17.35.040(I), § 17.35.080(G)

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

Local rule

Not required

No replacement parking required for garage/carport conversions.

§ 17.35.040(I)

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

Local rule

Only for a JADU

Owner-occupancy required for JADU or primary dwelling (one must be owner-occupied).

§ 17.35.080(F)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

Local rule

Planning permit, Building permit

Both planning and building permits required.

§ 17.35.100(A)

Crescent City-specific factors that can change the answer

State law sets the floor, but these local conditions often decide whether a specific parcel works.

Coastal Zone Exclusion

ADU ordinance applies only to noncoastal zoning districts; coastal zone ADUs subject to different rules.

Crescent City allows up to 1,200 sqft detached ADUs and requires no off-street parking for ADUs or JADUs. Only two detached ADUs are allowed on multifamily lots, each max 800 sqft. The ordinance applies only outside the coastal zone.

Frequently asked questions

Can I build an ADU in Crescent City?

Yes. California's statewide ADU law requires Crescent City to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Crescent City?

A detached ADU of at least 1,200 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Crescent City?

Side and rear setbacks are limited to 4 ft. No front setback may block the mandatory 800 sq ft / 16-ft / 4-ft-setback ADU; otherwise per base zone.

Is parking required for an ADU in Crescent City?

None. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Crescent City?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Crescent City?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Crescent City Municipal Code Chapter 17.35, Ord. 837 § 2, 2023
  • § 17.35.090
  • § 17.35.080(B)
  • § 17.35.060(B)
  • § 17.35.050(B)
  • § 17.35.060(C)
  • § 17.35.040(I), § 17.35.080(G)
  • § 17.35.040(I)
  • § 17.35.080(F)
  • § 17.35.100(A)
  • § 17.35.010
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66323 (by-right ADU/JADU, 800 sq ft, 4-ft setbacks)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated 2026-06-25. This is an AI-assisted summary of Crescent City's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Crescent City Planning before relying on it.

Will an ADU work on your Crescent City lot?