California ADU rules · Alameda County

Can I Build an ADU in Albany?

Yes — you can build an ADU in Albany. California's statewide ADU law requires every city, including Albany, to approve a qualifying accessory dwelling unit by right, plus a junior ADU (JADU) on a single-family lot. What varies city to city are the local specifics below.

Figures below reflect Albany's adopted ADU ordinance layered on California state law.

Can you build one?

ADUs allowed

CA state law

Yes — by right

ADUs and JADUs are allowed by right in all residential and mixed-use zones; ministerial approval, no hearing.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Units on a single-family lot

Local rule

Option 1: 1 JADU + 1 attached/new detached/converted ADU; Option 2: 1 JADU + 1 new detached ADU (max 800 sqft) + 1 converted ADU

Allows up to 3 units (1 JADU, 1 new detached ADU, 1 converted ADU) on single-family lots under certain conditions.

Albany Municipal Code § 20.20.080(D)

Units on a multifamily lot

Local rule

1 attached, detached, or converted ADU OR 2 detached ADUs; AND at least 1 converted ADU per building (up to 25% of units, rounded); JADUs not permitted

Local rule allows up to 2 detached ADUs and at least 1 converted ADU per multifamily building.

Albany Municipal Code § 20.20.080(D)

Junior ADU (JADU)

Local rule

Allowed

JADUs allowed only on single-family lots; not permitted on multifamily lots.

Albany Municipal Code § 20.20.080(B), (D), (G)

Size & height

Max detached ADU size

Local rule

1,000 sq ft

Detached ADU max: 850 sqft (1 bedroom), 1,000 sqft (2+ bedrooms); must allow at least 800 sqft by state law.

Albany Municipal Code § 20.20.080(E) Table E

Max attached ADU size

Local rule

850 (1 bedroom) or 1,000 (2+ bedrooms); must allow at least 800 sqft regardless of percentage of primary dwelling

Local cap is 850/1,000 sqft; state minimum of 800 sqft always applies.

Albany Municipal Code § 20.20.080(E) Table E

Guaranteed minimum size

CA state law

800 sq ft

An 800 sq ft ADU must be allowed regardless of FAR/lot-coverage caps; a city also cannot cap an attached ADU below 850 sq ft (1,000 for 2+ bedrooms).

Cal. Gov. Code § 66321 (size minimums & height)

Max JADU size

CA state law

500 sq ft

Cal. Gov. Code § 66333 (junior ADUs)

Max height

Local rule

20 ft

Detached ADU max height 20 ft; attached ADU up to 25 ft or 28 ft if matching roofline/daylight plane.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Setbacks

Side setback

Local rule

3 ft

Local side/rear setback is 3 ft, but must allow 4 ft for 800 sqft ADUs per state law.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Rear setback

Local rule

3 ft

Local side/rear setback is 3 ft, but must allow 4 ft for 800 sqft ADUs per state law.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Front setback

Local rule

15 feet (not required for detached ADUs up to 800 sqft per state law)

Local front setback is 15 ft, but state law preempts for 800 sqft ADUs.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Separation from main house

Local rule

6 ft

6 ft separation required for detached ADUs on single-family lots; 10 ft on multifamily.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Parking

Parking required

Local rule

None

No parking required for ADUs or JADUs.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Transit parking exemption

CA state law

Yes — no parking required near transit & for conversions

No parking may be required within ½ mi walking distance of transit, in a historic district, for an ADU within an existing structure, within one block of car-share, or in certain permit-parking areas.

Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)

Garage-conversion replacement parking

Local rule

Not required

No replacement parking required for garage/carport conversions.

Albany Municipal Code § 20.20.080(E) Table E, Table F

Approval, timeline & cost

Approval path

CA state law

Ministerial (by right)

No public hearing or discretionary design review for a qualifying ADU.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Approval timeline

CA state law

60 days

The agency must act within 60 days of a complete application — and the ADU is deemed approved if it does not.

Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)

Owner-occupancy

Local rule

Only for a JADU

Owner-occupancy required for JADUs only; not required for ADUs.

Albany Municipal Code § 20.20.080(G)

Impact-fee waiver

CA state law

Waived under 750 sq ft

An ADU of 750 sq ft or less pays no impact fees (the 750 sq ft threshold itself is exempt under § 66311.5); larger ADUs pay fees proportional to the primary dwelling. JADUs (≤ 500 sq ft) are exempt.

Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Permits required

Local rule

Building permit, Deed restriction

Deed restriction required for ADUs/JADUs in addition to building permit.

Albany Municipal Code § 20.20.080(G)(6)

Albany allows up to three units (including a JADU and both a new detached and a converted ADU) on single-family lots under certain conditions. Local maximum sizes for detached and attached ADUs are 850/1,000 sqft, with a 3-foot side/rear setback, but state minimums override where more permissive.

Frequently asked questions

Can I build an ADU in Albany?

Yes. California's statewide ADU law requires Albany to approve a qualifying accessory dwelling unit ministerial (by right), plus a junior ADU (JADU) on a single-family lot.

How big can an ADU be in Albany?

A detached ADU of at least 1,000 sq ft must be allowed, and an ADU of 800 sq ft can never be zoned out by floor-area or lot-coverage limits. A JADU can be up to 500 sq ft.

What are the setback requirements for an ADU in Albany?

Side and rear setbacks are limited to 3 ft. 15 feet (not required for detached ADUs up to 800 sqft per state law).

Is parking required for an ADU in Albany?

None. No parking can be required within ½ mile of transit, for conversions, or for units inside the primary home. When a garage is converted, replacement parking is not required.

How long does ADU approval take in Albany?

A complete application must be acted on within 60 days, with ministerial (by right) — no public hearing or discretionary design review for a qualifying ADU.

Do I have to live on the property to build an ADU in Albany?

Owner-occupancy: only for a jadu. ADUs under 750 sq ft are also exempt from impact fees.

Sources

  • Albany Municipal Code § 20.20.080 (amended 1-16-2024 by Ord. No. 2023-07)
  • Albany Municipal Code § 20.20.080(D)
  • Albany Municipal Code § 20.20.080(B), (D), (G)
  • Albany Municipal Code § 20.20.080(E) Table E
  • Albany Municipal Code § 20.20.080(E) Table E, Table F
  • Albany Municipal Code § 20.20.080(G)
  • Albany Municipal Code § 20.20.080(G)(6)
  • Cal. Gov. Code §§ 66310–66342 (ADU Law)
  • HCD 2025 Accessory Dwelling Unit Handbook
  • Cal. Gov. Code § 66317 (ministerial approval, 60-day deadline)
  • Cal. Gov. Code § 66321 (size minimums & height)
  • Cal. Gov. Code § 66333 (junior ADUs)
  • Cal. Gov. Code § 66322 (ADU parking; § 66334 covers JADU parking)
  • Cal. Gov. Code § 66311.5 (impact fees: none for an ADU ≤ 750 sq ft or JADU ≤ 500 sq ft)

Last updated 2026-06-25. This is an AI-assisted summary of Albany's ADU rules, drawn from its published ordinance and California ADU law — general information, not legal advice, and it may be incomplete or out of date. Verify the controlling rule for your specific parcel with Albany Planning before relying on it.

Will an ADU work on your Albany lot?

Ask GoCodebook about your address and get the size, setback, parking and permit rules that actually apply to your parcel — with the exact citation.

Check my parcel free

Related